ML20039D562

From kanterella
Jump to navigation Jump to search
Provides Quarterly Update of Const Progress,In Response to NRC 810609 Request.Unit 1 Estimated 87% Complete as of 811025.Quantities of Commodities Erected from Sept-Nov 1981 Listed
ML20039D562
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 12/28/1981
From: Parker W
DUKE POWER CO.
To: Adensam E, Harold Denton
Office of Nuclear Reactor Regulation
References
NUDOCS 8201050210
Download: ML20039D562 (2)


Text

-_-_- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _. _ _ .

e %

DUKE POWER CO31PANY POWER DUII. DING 422 Sourn Cuuncu Srazer, Ciuumtre, N. C. asa4a I

witu Au o. PAnxcm, s.

l Vicr entsIDENT TELEPHONE: A9E4 704 src. Paeovctio- December 28, 1981 373-4083 Mr. Harold R. Denton, Director // 4 Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission f4ECEIVED Washington, D. C. 20555 -

- JAN 4 1982> -

~

Attention: Ms. E. G. Adensam, Chief 6- nummiapWWWWE Licensing Branch No. 4 8"" g""8E U Re: Catawba Nuclear Station Docket Nos. 50-413 and 50-414

Dear Mr. Denton:

Your letter of June 9, 1981 to W. S. Lee requested quarterly updates of the projected construction completion date for Catawba Unit 1. The following provides an update of our construction progress including erection rates for various commodities.  ;

Catawba Unit 1 is estimated to be 87% complete as of October 25, 1981. This unit is currently four months behind the August 1983 fuel load date. The slippage of mechanical systems scheduled for turnover to the Steam Production Department for functional testing continues to impact ourf projected comple-tion date. Special emphasis is being placed on the resolution of problems which delay these system turnovers.

Several major milestones in our construction schedule were achieved the last three months. Cleaning of the Chemical and Volume Control System (NV), began October 13, 1981, was completed November 12, 1981. We are now preparing to test this system hydrostatically. Work on this system is currently on the project critical path.

The main turbine was placed on its turning gear December 7, 1981. The high level leak test of the condenser war also completed about this time. Our next major milestone is the Alkaline Wash of the Condenser and Condensate system piping. We expect to begin this cleaning on January 4, 1982.

Our total Construction workforce increased from 3,589 on August 31, 1981, to 3,670 on November 23, 1981. In addition, there are 310 contractor personnel on-site. Second shift work is continuing in the hanger crection area. Over-time is used where necessary to complete work on critical systems.

The following quantities of listed comiaodities were erected during the September, 0 00

- os j

a %

Mr. Harold R. Denton, Director December 28, 1981 Page 2 October, and November accounting periods (12 weeks).

Quantity Erected Quantity Remaining Commodities During Period To Be Erected Structural Concrete (cy) 1,953 590 Piping (weighted value) 4,189 7,773 Cable Pulls (each) 768 2,905 Cable Terminations (each) 3,081 13,527 Instruments (equivalent loops) 376 2,566 Piping Support / Restraints (each) 4,872 17,268 Work continues in an etiort to meet near-term schedule milestones. In parallel with continuing work we are in the process of accomplishing an overall schedule reassessment. The reassessment will require many manhours and several itera-tions between the Design Engineering, Construction and Steam Production depart-ments. A new realistic but challenging schedule will be developed for the project over the next few months.

Ver,y truly yours,

/

- C

\ '

w_.. G, ,

William O. Parker, Jr ROS/php cc: W. H. Lovelace P. K. VanDoorn f M. R. Guild Palmetto Alliance l