Requests Temporary Exemption from 10CFR50,App E.IV.D.3 Schedule Requirements.Warning Sys Installation & Testing Can Be Completed within Approx 30 Days After NRC Resolves Issue Re Charlevoix County Request for Hearings
ML20039D269
Person / Time
Site: Big Rock Point File:Consumers Energy icon.png
Issue date: 12/28/1981
From: Hoffman D
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To: Crutchfield D
Office of Nuclear Reactor Regulation
Shared Package
ML20039D270 List:
References
NUDOCS 8112310477
Download: ML20039D269 (2)


Text

r

'O Consumers David P Hoffman g{

Nudw lisa usnog AJmuuntr.utuur CamDany General offices: 1945 West Parnati Road, Jackson, Mt 49201 * (517) 788 1636 December 28, 1981 A

e RECgWED OEC30198W Dennis M Crutchfield, Chief supWimumm Operating Reactors Branch No 5 ass gS8" Nuclear Reactor Regulation g

US Nuclear Regulatory Commission Washington, DC 20555 DOCKET 50-155 - LICENSE DPR BIG ROCK POINT PLANT - PROMPT PUBLIC NOTIFICATION SYSTEM By letter dated November 6, 1981, Consumers Power Company (CP Co) committed to the installation of an immediate warning system at Big Rock Point Plant by February 1, 1982. This commitment corresponds to the requirements of 10CFR50 Appendix E as amended on September 16, 1981 (46FR46587 published September 21, 1981). Due to circumstances beyond our control, fulfillment of that commit-ment is in jeopardy as a result of a Charlevoix County Board of Commissioners -

Resolution dated November 25, 1981 (copy attached). This resolution effec-tively prohibits the installation of the warning system equipment and manning of the system at the county sheriffs' office.

This resolution and a letter from the Charlevoix County Board of Commissioners requesting a " simple hearing" on the matter with the NRC were mailed to Robert F Burnett, Director, Division of Safeguards, NRC, on December 10, 1981.

Copies of these two documents.were hand delivered to Richard Emch, NRC Project Manager and Brian Grimes, Director of Emergency Preparedness Licensing Branch, Office of Inspection and Enforcement on December 15, 1981. Copies were also telecopied to William L Axelson, NRC Region III on December 17, 1981.

Since the Charlevoix County Sheriff's Office is the assigned warning point, and CP Co has been prohibited from installing any equipment there, installa-tion of the warning system has been stopped.

It is our understandin that the County Board had set December 30, 1981 as the o

date for the meeting with the NRC, but that the NRC is unable to support that date. As a result, it is apparent that immediate resolution of this issue will not be possible.

CP Co has made a concerted effort to meet the February 1, 1982 commitment. All necessary equipment has been received and is ready for installation. Acquisition of 80% of right-of-way permits has been oc1281-0028a142

~8112310477 811228_

PDRADOCK05000gSd O

r F

\\

$s \\

16 -

i l

Dznnis M Crutchfield, Chief 2-Big Rock Point' Plant December 28, 1981 completed. Until the NRC and the County Board of Commissioners resolve this

]-

issue, however,' system installation and tes' ting cannot.be completed.

-Therefore, in accordance with 10CFR50.12(a) Consumers Power Company, requests a temporary' exemption from _the 10CFR50 Appendix E.IV.D.3 schedule requirements and an indefinite extension of the February 1, 1982 date, until the NRC and i

.the County. Board of Commissioners can resolve this. impasse.

It'is anticipated that system' installation and testing can be completed within approximately 30 days after this issue is resolved.

^

ft4<

David P Hoffman Nuclear Licensing Administrator CC Administrator, Region III, USNRC NRC_ Resident Inspector-Big Rock Point.