Text
n-
-n-.
k a
- DUKE :POWEIE COMPANY '
F5wsuBusil>swo 4e2 Sourn Cnuncu StazzT, CruanoTTs, N. C. 2sa4a
- j r o 31 4 3 0 '
Vecy PotsiorNT TttcpwoNt:Anta 704
. src - Paoover.
- September' 28, 1981' Mr. James P.: O'Reilly, Director
,n,dr K
Ig// k,g U. S. Nuclear Regulatory Commission Region II' 8
[
NL(.Julg[
g\\g 101 Marietta Street,; Suite 3100
-Atlanta, Georgia 30303-
'j DECl 41981 73.,
Re:~ RII:PKV u.s.
j,,,,gu,cy s50-413/81-14 s
'E' 50-414/81-14
' QQ! (U
Dear Mr. O'Reilly:
In my August-19, 1981 letter which transmitted-a response to the infraction identified in the above referenced Inspection Report, it was stated that full compliance would be achieved by October 1, 1981. At this time, all of the necessary procedure revisions have not been made; The changes will be made
.and full compliance will be achieved by November 1, 1981.
Very truly yours, jnM2>n a 8erk1sch William O. Parker, Jr.
RWO/php cc: NRC. Resident Inspector Catawba Nuclear Station i.
b
' 8112160159 8109285
~
((Qf h O
?
- fA
..