Forwards Monthly Operating Rept for Nov 1981
ML20038D154
Person / Time
Site: Farley 
Issue date: 12/09/1981
From: Clayton F
ALABAMA POWER CO.
To:
NRC OFFICE OF MANAGEMENT AND PROGRAM ANALYSIS (MPA)
Shared Package
ML20038D155 List:
References
RTR-NUREG-0588, RTR-NUREG-0737, RTR-NUREG-588, RTR-NUREG-737 NUDOCS 8112160111
Download: ML20038D154 (2)


Text

..

Mailing Aduress Alabama Power Company.

e i

ECD North 18th Street Post Office Box 2641 Birmingham. Alabama 35291 o

Telephone 205 783-6081 F. L Clayton, Jr.

Senior Vice President Alabama Power Flintridge Bui@ng the southem electrc system December 9,1981 co Docket No. 50-348

,f

? l\\;f,,, %

/

N

,9 1

/

?gm L)

Director, Office of Management

~

RT g 01'. e n

@ q(,,gg%o,"-

4j9 Information and Program Control U. S. Nuclear Regulatory Commission Washington, D.C.

20555 8

Dear Sir:

pf 1 -

RE: Joseph M. Farley Nuclear Plant Unit No. 1 Monthly Operating Data Report Attached are two (2) copies of the November,1981 Monthly Operating Report for Joseph M. Farley Nuclear Plant, Unit 1, as required by Section 6.9.1.6 of the Appendix A Technical Specifications. As requested by letter from Mr. John F. Stolz to Mr. Alan R. Barton, dated October 21,1977, a

" Narrative Sunmary of Operating Experience" is included in the attached re-port.

If you have any questions, please advise.

Yours very truly,

., d,

fr>t 4

(AG a

F' layton,j r.

FLCJr/KWM:nac Attachments xc: Mr. Ted Cintula (1 copy)

Director, IE (10 copies)

Director, RII (1 copy) p]o]

i i

8112160111 811209 PDR ADOCK 05000348 R

pop 2 -L w

'4s s,

JOSEPH M. FARLEY NUCIIAR PLANT UNIT 1 NARRATIVE

SUMMARY

OF OPERATIONS NOVEMBER, 1981 The unit continued to be shutdown through the month of November for repair of the main generator and Cycle 3 - Cycle 4 refueling operations.

The following safety-related maintenance was performed in the month of November:

1. Performed miscellaneous maintenance on diesel generators.
2. Performed various design changes required by NUREG-0737 and FJREG-0588.
3. Repaired electrical penetration Q1T52B005-A which had failed local leak rate testing.
4. Supported Westinghouse in baffle peening core internals.