Forwards Monthly Operating Rept for Nov 1981
ML20038D145
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 12/09/1981
From: Clayton F
ALABAMA POWER CO.
To:
NRC OFFICE OF MANAGEMENT AND PROGRAM ANALYSIS (MPA)
Shared Package
ML20038D146 List:
References
NUDOCS 8112160103
Download: ML20038D145 (2)


Text

. .- Mallirtg Address Alabama Power Company 600 North 18th Street Post Offsce Box 2641 Birmirgham, Alabama 35291 Telephone 205 783-6081 F. L Clayton, Jr.

Cf,'J '3%'"' Alabama Power fhe soorten t kttx system December 9, 1981

,m Docket No. 50-364 s

G[ lip Director, Office of Management Information and Program Control Og0 l
  • p I f

/'

U. S. Nuclear Regulatory Comission '

u., % ,g 788 Washington, D.C. 20555 -7  %'sibsg/g-/fO b, -

Dear Sir:

/n thi j g\ .\ Q).N RE: Joseph M. Farley Nuclear Plant '~

Unit No. 2 Monthly Operating Data Report Attached are two (2) copies of the November,1981 Monthly Operating Report for Joseph M. Farley Nuclear Plant, Unit 2, as required by Section 6.9.1.10 of the Unit 2 Technical Specifications. As requested by letter from Mr. Joh'1 F. Stolz to Mr. Alan R. Barton, dated 21, 1977, a " Narrative Sumary of Operating Experience" is included in the attached report.

If you have any quertions, please advise.

Yours very truly, S .h lOk Clayton, Jr'.

s

.FLCJr/KWM:nac l Attachments l xc: Mr. Ted Cintula-(1 copy)

Director, IE (10 copies)

Director, RII (1 copy) l l

i. 8112160103 811209 e PDR ADOCK 05000364 R  ?PDR. '%

JOSEPH M. FARLEY NUCLEAR PLANT UNIT 2 NARRATIVE

SUMMARY

OF OPERATIONS NOVEMBER, 1981

~

There were two (2) power reductions and one (1) automatic shutdown in the month of November.

The following safety-related maintenance was performed in the month of November:

1. Performed miscellaneous maintenance on diesel generators.

!