Application to Amend Licenses DPR-53 & DPR-69 Re Containment Purge Sys Incorporating New Tech Spec 3/4 6.1.7 & Revising Applicability & Isolation Time Requirements
ML20038C846
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 12/07/1981
From: Lundvall A
BALTIMORE GAS & ELECTRIC CO.
To: Clark R
Office of Nuclear Reactor Regulation
Shared Package
ML20038C847 List:
References
NUDOCS 8112140191
Download: ML20038C846 (4)


Text

.

B ALTIMORE G AS AND ELECTRIC COMPANY P.O. BO X 14 7 5 B A LTIM O R E, M A R YL A N D 212o3 ARTHun E. LUNOVALL,JR.

Decemb >r 7,1981 Vect Persecteet Sumv 0

e, 4

Office of Nuclear Reactor Regulation

//

[/n e' /-

U.S. Nuclear Regulatory Commission kCJ

  • ' /;

g Washington, DC 20555 0

ATTENTION:

Mr. Robert A. Clark, Chief D Da.k" ISg Operating Reactors Branch #3 C

Division of Licensing G.-4,

SUBJECT:

Calvert Cliffs Nuclear Power Plant Unit Nos.1 & 2; Docket Nos. 50-317 & 50-318 Request for Amendments

REFERENCES:

a.

Letter from R. A. Clark to A. E. Lundvall, Jr., dated October 20,1981, "Long-Term Review of Containm nt (and Venting)

Systems" b.

Letter from C.

H. Poindexter to D.

G.

Eisenhut, dated December 30,1980, RE: NUREG-0737, item II.E.4.2.(5)

Gentlemen:

In your letter of October 20,1981, (Reference a) your staff reviewed five specific items concerning our Containment Purge System. These items are individually addressed below and additional information is submitted.

Item I requested additional information to requalify our containment purge isolation valves such that they may be open during power operations. We understand that our i,

continued operations in MODES I through 4 with the containment purge isolation valves j

closed will eliminate the requirement to submit the additional information specified by

of Reference a.

Item 2 requested submittal of Technical Specification (TS) changes to close the " valve operability" issue. The TS change is attached and addressed below (Change 1).

,ho i 5

Item 3, " Safety Actuation Signal Override", was specifically identified as complete in

/

Reference a.

///

Item 4 addressed, " Containment Purge Isolation Valve Seal Deterioration", and requested l

a TS change incorporating test requirements as identified in Enclosure 1 of Referencepypo a.

It also requested the details of that testing program. Enclosure 5 of this submittaf outlines the pertinent leakage rate testing program employed at Calvert Cliffs. Our valve seals have never failed and our leakage rate testing has not identified any degraded seal performance.

Based upon our environmental conditions and infrequent use of containment purge isolation valves, we have determined that our current test program is adequate and no additional TS requirements are necessary.

8112140191 811207 PDR ADOCK 05000317 P

PDR

4 d

Mr. Robert A. Clark 2

December 7,1981 Item 5 addressed a " Technical Evaluation" of the " Minimum Containment Pressure Setpoint", (Reference a, Enclosure 6), which provides a pre-implementation analysis establishing a limit of 3.0 psi for an isolation setpoint margin, over the normal i

containment pressure, for total loop error.

Based upon this loop error, which differs from that considered in Reference b, our existing containment pressure setpoint of 4.0 psig (maximum) is conservative and consistent with NUREG-0737, Clarification of TMI Action Plan Requirements, Item II.E.4.2. Position 5.

Baltimore Gas and Electric Company (BG&E) hereby requests Amendments for Operating i

Licenses DPR-53 and DPR-69 for Calvert Cliffs Units 1 and 2, respectively, with the submittal of the enclosed proposed changes to the Tecnical Specifications. The proposed Technical Specifications changes attached and discussed below are intended to satisfy all of the requirements of Reference a including the review of our TS against the sample provided in Enclosure 7 of Reference a.

TECHNICAL SPECIFICATION CHANGES CHANGE NO.1 Incorporate new Technical Specification 3/4 6.1.7 as shown on the attached marked-up pages 3/4 6-9a and revise applicability and isolation time requirements specified in Tables 3.3-3 and 3.3-5 as shown on the attached marked-up pages 3/4 3-13 and 3/4 3-30 (Enclosures 1 and 2).

DISCUSSIONS AND JUSTIFICATION Items 1 and 2 of Reference a identified that containment purge isolation valves will be closed during MODES 1, 2, 3, and 4.

Therefore, isolation times for these valves during these modes are subsequently Not Applicable.

Isolation during MODES 5 and 6 are specifically covered and are consistent with Table 3.6-1 of the Technical Specifications.

i i

CHANGE NO. 2 Revise Technical Specification 3/4 6.4 and Table 3.6-1 as shown on the attached marked-

)

up pages 3/4 6-17 through 6-25 (Enclosures 3 and 4).

I DISCUSSION AND JUSTIFICATION Specific exclusions of the containment purge isolation valves is required in Technical Specification Limiting Condition for Operation (LCO) 3.6.4.1 to resolve inconsistencies between our closed isolation valves and their OPERABILITY (TS 3.6.1.7 and 3.6.4.1).

l Surveillance requirement 4.6.4.2 is revised to identify Channel A/B test signal actuations and to add Safety injection Actuation Signal (SIAS) Channel A/B test signal actuation.

Technical Specification 4.6.4.3 and 4.6.4.4 maintain consistency with Technical Specification 3.6.1.1, 4.6.1.2.d and 3.9.9 f or Table 3.6-1 and Containment Isolation of the Containment Purge System.

1

Mr. Robert A. Clark 3

December 7,1981 SAFETY COMMITEE REVIEW These proposed changes to the Technical Specifications have been reviewed by our Plant Operations and Safety Review and Off-Site Safety and Review Committees, and they I

have concluded that implementation of these changes will not result in an undue risk to the health and safety of the public.

FEE DETERMINATION We have determined, pursuant to 10 CFR Part 170 Paragraph 170.22, that this Amendment request consists of Class III and Class I amendments for Calvert Cliffs Unit Nos. I and 2, respectively, and, accordingly, we are including BG&E Check No. B079684 in the amount of $4,400.00 to cover the fee for this request.

BALTIMORE GAS AND ELECTRIC COMPANY By:

_ u[fli-i 6

"' Vice Pr6 sic bnt - Supply J

/

4 STATE OF MARYLAND:

TO WIT:

CITY OF BALTIMORE:

Mr. Arthur E. Lundvall, Jr., being duly sworn, states that he is Vice President of the Baltimore Gas and Electric Company, a corporation of the State of Maryland; that he executed the foregoing Amendment for the purpose therein set forth; that the statements made in said Amendment are true and correct to the best of his knowledge, information, and belief; and that he was authorized to execute the Amendment on behalf of said Corporation.

I rt2 0444. /,1.o Witness my Hand and Notarial Seal:

th 'm My Commission Expires:

I 'IV AEL/GCW/gla Enclosures I

J

Mr. Robert A. Clark 4

December 7,1981 cc:

J. A. Biddison, Esquire G. F. Trowbridge, Esquire D. H. Jatte R. E. Architzel

ENCLOSURE 1 Page 1 of 3 CONTAINMENT SYSTDIS CONTAINMENT PURGE SYSTDI LIMITING CONDITION FOR OPERATION 3.6.1.7 The containment purge supply and exhaust isolation valves shall be closed by isolating air to the air operator and maintaining the sole-noid air supply valve denergized.

APPLICABILITY:

MODES 1, 2, 3, and 4 ACTION:

With one containment purge supply and/or one exhaust isolation valve open, cloce the open valve (s) within one hour or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

SURVEILLANCE REQUIRDIENTS 4.5.1.7 The 48-inch containment purge supply and exhaust isolation valves shall be determined closed at least once per 31 days, by verifying that power to the solenoid valve is removed.

l

(

8112140194 7

PDR ADOCK 0 PDR P

CALVERT CLIFFS - UNIT 1 3/4 6-9a Amendment No.

,N58x -

m c

N O

)

o c.

I T

8 C

1 A

8 7

7 dna b.

E LBS 1

3 3

AE 6

CD I O LM 5

6 2

2 a.

P 1

P 1

1 A

s t

i n

n o

u f

f i

0 t

I l

T a

a A

SE r

n T

MLL t

o N

UEB e

i E

MNA n

s s

t M

I NR e

u u

U NAE P

B B

cn T

I l P

/

/

/

u S

MCO 2

3 3

3 l

f l

(

l I

n S

M o

A i

E I

t

)

T S

d S

a e

Y S

r y

u S

LP t

b n

El e

Ni n

s s

l d

i t

0 NT e

u u

t e

A P

B B

n I

t liO

/

/

/

o T

a O

(C A

CT 1

2 2

2 i

U t

T i

3 C

n n

A o

i i

3 E

t o

3 R

.S a

s U

OL r

l E

T NE t

a L

A N

e B

E LN n

s s

s A

F AA e

u u

l i

T_

Ti P

B B

Y OC

/

/

/

n T

T 2

4 4

4 o

E F

i F

O t

A a

S l

d D

n sf s e os E

o uo ud i

R e) i B

B a E

vs t

s r

e E

l e a

ys yg N

ah i

co ce v

f l

I V c d

nL nl G

N t

a e(

e(

av EO ei R

r g

g 4

f E

GI gw o

re re e

RT rS t

t eg eg g

ma ma UA u

n i

PL Pl e

n R

Et Et ru O

( o m

o E

l) l)

TS r

n M

W voe voe p

T, NI l t ih O

k vg k vg t

I E

an aga P

ra ra N

S uo ti e 6 et 6 et n

1 U

iE nC nlir F

1 dl 1 dl e

f no m

l l V a

o A

O

.no L

AL M

C 4UV 4UV n

i A

TA S

a N

NV S

t O

O O

L a

b n

r I

C a

t o

T C

C O

N A

U F

6 7

h%n nC1 L 2 c, ;g Y 6.

- =

a a

Ei-1

~

k

ENCLOSURE 1~

p.,,,, 3 h e + 3 TABLE 3.3-5 ENGINEERED SAFETY FEATURES RESPONSE TIMES g

INITIATING SIGNAL AND FUNCTION RESPONSE TIME IN SECONOS 1.

Manual a.

SIAS Safety Injection (ECCS)

Not Applicable b.

CSAS Containment Spray Not Applicable c.

CIS Containment Isolation Not Applicable d.

RA$

Containment Sump Recirculation Not Applicable e.

Auxiliary "eedwater Initiation Not Applicable 2.

Pressurizer Pressure-Low a.

Safety Injection (ECCS) 1 30*/30**

g 3.

Containment Pressure-Hich a.

Safety Injection (ECCS) 1 30*/30**

b.

Containment Isolation 1 30 c.

Containment Fan Coolerc 1 35*/10**

4.

Containment Pressure--Hich a.

Containment Spray 1 60*/60** (I) 5.

Containment Radiation-High a.

Containment Purge Valves Isolation 17 s

CALVERT CLIFFS - UNIT 1 3/4 3-20 Amendment No. Ah, 54

y

. _. = -

.3

-w--

s_

y- --

ENCLOSURE 2 Page 1 of 3 CONTAINMENT SYSTE'tS CONTAINMENT PURGE SYSTEM LIMITING CONDITION FOR OPERATION 3.6.1.7 The containnent purge supply and exhaust isolation valves shall be closed by isolating air to the air operator and maintaining the sole-noid air supply valve denergized.

APPLICABILITY:

MODES 1, 2, 3, and 4 ACTION:

With one containment purge supply and/or one exhaust isolation valve open, close the open valve (s) within one hour or be in at least IIOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SilUTDOW'i within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

SURVEILLANCE REOUIREMENTS 4.5.1.7 The 48-inch containnent purge.;npp1:/ and exhaust isolation valves shall be determined closed at least once per 31 days, by verifying that power to the solenoid valve is removed.

CALVERT CLIFFS - U';IT 2

3/4 6-9a Amendment No.

h 0

~

O o

o TABLE 3.3-3 (Continued) h EllGINEERED SAFETY FEATURE ACTUATI0fl SYSTEM If1STUMENTATI0ft M

MINIMUM b

TOTAL fl0.

CilANilELS CllAfillELS APPLICABLE

}

FurtCTI0f1AL liflIT OF C}{ANilELS TO TRIP OPERABLE MODES ACTION 6.

C0flTAllif1ENT PURGE N

E VALVES ISOLATION a

u a.

Manual (Purge Valve Control Switches) 2/ Penetration 1/ Penetration 2/ Penetration 5, 6 8

tr.

Containment Radiation -

liigh Area Monitor 4

2 3

6 8

N r-8 7.

LOSS OF POWER e:n m

t' ln a

a.

4.16 kv Emergency Bus y

Undervoltage (Loss of g

Voltage) 4/ Bus

.2/ Bus 3/ Bus 1, 2, 3 7"

b.

4.16 kv Emergency Bus Undervoltage (Degraded Voltage) 4/ Bus 2/ Bus 3/ Bus 1, 2, 3 7*

O Containment purge valve isolation is also initiated by SIAS (functional units 1.a. 1.b, and 1.c).

A R.

=

r hm b

ENCLOSURE 2 Page.3 of'3 TABL E 3.3-5 ENGINEERED SAFETY FEATURES RESPONSE TIMES Jgg INITIATING SIGNAL AND FUNCTION RESPONSE TI'ME IN SECONDS-1.

Manual ~

a.

SIAS Safety Injection (ECCS)

Not Applicable b.

CSAS Containment Spray Not Applicable c.

CIS Containment Isolation Not Applicable d.

RA$

Containment Sump Recirculation Not Applicable e.

Auxiliary Feedwater Initiation Not Applicable 2.

Pressurizer Pressure-Low a.

Safety Injection (ECCS) 5.30*/30**

(l) 3.

Containment Pressure-Hich a.

Safety Injection (ECCS) 3,30*/30**

b.

Containment Isolation 3, 30 c.

Containment Fan Coolers 3,35*/10**

l 4.

Containment Pressure--Hich a.

Containment Spray 5,60*/60** (I) l i,

5.

Containment Radiation-Hich a.

Containment Purge Valves Isolation 3.7 p

I i

()

r l

CALVERT CLIFFS - UNIT 2 3/4 3-20 Amendment No. 21.37 i

---2 f*1

. _,. _ __._. _ _.,, _,. -,., ++m 1 :M

-1 u.a.

. fa_

2 ESCLOSURE 3 Page 1 of 9

(}

CONTAINMENT SYSTEMS 3/4.6.4 CON'TAINMENT ISOLATION VALVES LIMITING CONDITION FOR OPERATION 3.6.4.1 The containment isolation valves

  • specified in Table 3.6-1 shall be OPERABLE with isolation times as shown in Table 3.6-1.

APPLICABILITY: MODES 1, 2, 3 and 4 ACTION:

With one or more of the isolation valve (s) specified in Table 3.6-1 inoperable, either:

a.

Restore the inoperable valve (s) to OPERABLE status within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />, or b.

Isolate each affected penetration within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> by use of at least one deactivated automatic valve secured in the isolation 7~3

(_)

position, or Isolate the affected penetration within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> by use of at c.

least one closed manual valve or blind flange; or d.

Be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

SURVEILLANCE REQUIREMENTS 4.6.4.1.1 The isolation valves specified in Table 3.6-1 shall be demon-strated OPERABLE prior to returning the valve to service af ter maintenance, repair or replacement work is performed on the valve or its associated actuator, control or power circuit by perfornance of a cycling test and verification of isolation time.

Ccutainnent purge isolation valve., of Table 3.6-1 shall be closed in "0 DES 1, 2, 3, and 4; Isolation t i m. s specified do nifapply, technical Specificatinn 1/4 6.1.7 refer.s.

CAL'/ERT CLIFFS - UNIT I 3/4 6-17 Amendment ':n.

I ENCLOSURE 3 Page 2 of 9 CONTAINMENT SYSTDiS SURVEILLANCE REQUIRDIENTS (Continued) 4.6.4.1.2 Each isolation valve specified in Table 3.6-1 shall be demonstrated OPERABLE during the COLD SHUTDOWN or REFUELING MODE at least once per 18 months by:

a.

Verifying that on each containment isolation Channel A or Channel B test signal, each required isolation valve actuates to its isolation position.

b.

Verifying that on each Containment Radiation-High Test Channel A or Channel B test signal, both required containment purge valves actuate to their isolation position.

c.

Verifying that on each Safety Injection Actuation Channel A or Channel B test signal, each required isolation valve actuates to its isolation position.

4.6.4.1.3 The isolation time of each power operated or automatic valve of Table 3.6-1 shall be determined to be within its limit when tested pursuant to Technical Specification 4.0.5 4.6.4.1.4 Containment purge isolation valve operability shall be determined at least once every 18 months by verifying that when the measured leakage rate is added to the leakage rates determined pursuant to Technical Specification 4.6.1.2.d for all other Type B or C penetrations, the combined leakage rate is less than or equal to O.60 La.

l l

CALVERT CLIFFS - UNIT 1 3/4 6-18 Anendment No.

[

O O

o TABLE 3.6-1 h

CONTAINMENT ISOLATION VALVES M

E ISOLATION PENETRATION ISOLATION ISOLATION VALVE

[

NO.

CHANNEL IDENTIFICATION N0.

FUNCTION TIME (SECONDS) n

'm m

1A SIAS A CV-5465 R.C. and Pressurizer Sampling

<7 77 SIAS A CV-5466 E

77 SIAS A CV-5467 Q

37 SIAS B CV-5464 E

1B SIAS A CV-2180 Containment Vent Header To Waste 17 O

SIAS B CV-2181 Gas 17 8

E u

R 1C SIAS A CV-506 RCP Seals Controlled Bleedoff 17 o

SIAS B CV-505 17 T.

10 SIAS B SV-6529 0xygen Sample 17 2A SIAS A CV-515 Letdown Line

<13

-713-SIAS B CV-516 NA 7M3-1 NA m

~,

g NA 7M3-1 NA j

i R

u a

NA CV-517 Charging Line NA

[

2B NA CV-518 NA

.e p

NA CV-519 NA NA NA SP-210M3-2 NA 210M3-2 NA

TABLE 3.6-1 (Cont.)

o#

CONTAINMENT ISOLATION VALVES j

\\

~

=

ISOLATION 1 SOLATION VALVE PEflETRATION I SOI.AT ION IDENTIFICATION NO.

FUNCTION TIME (SECONDS) n{

NO.

CHANNIM.S

?

Blind Flange ILRT NA 7A NA l9~l Ei NA Z

7B NA Blind Flange ILRT NA NA Q

NA 19-1 E

m 8

SIAS A MOV-5462 Containment Nonnal Sump 113 l

SIAs n MOV-5463 113 k'u I

T 9

NA 238M3-1 Containment Spray NA NA E$

NA 238M3-2 10 NA 238M3-1 Containment Spray NA NA NA 238M3-2 S

13 STAS A, cRS A CV-1410 (3)

Purge Air Inlet

<7**

2' 57**

h SIAS L, CRS B CV-14ll (3) s-f O~

n Z

.o e

e e

i

O O

O TABLE 3.6-1 (Cont.)

h CONTAINMENT ISOLATION VALVES PENETRATION ISOLATION ISOLATION VALVE ISOLATION n[

NO.

CllANNELS IDENTIFICATION N0.

FUNCTION TIME (SECONDS) n U

7 14 SIAS A, CRS A CV-1412 (3)

Purge Air Outlet 1 **

e 7

c SIAS B, CRS B CV-1413 (3) 1 **

Oa a

15 SIAS A CV-5291 Purge Air Monitor

-<7 SIAS B CV-5292 17 y

e 8

16 CIS ^

CV-3832 Component Cooling Water Inlet 118 l

u wA 18 CIS B CV-3833 Component Cooling Water Outlet 118 i'

S 19A NA 223-1 Instrument Air NA CIS A M0V-2080 113 19B NA 19-2

  • Plant Air NA g

NA 130-1

  • NA b

20A NA 223-1 Nitrogen Supply NA u

5 NA CV-612

  • NA g-Z NA CV-622
  • NA NA CV-632
  • NA NA CV-642
  • NA

TABLE 3.6-1 (Cont.)

9

]

CONTAINMENT ISOLATION VALVES E

P PENETRATION I SOI.AT ION ISOLATION VALVE ISOLATION NO.

CHANNEL IDENTIFICATION NO.

FUNCTION TIME (SECONDS) c; 20B NA 223-1 Nitrogen Supply NA 3

NA 223-2 NA 20C NA 223-1 Nitrogen Supply NA m

NA 223-2 NA 5

E m

55 23 sIAs A CV-4260 R.C. Drain Tank Drains 17 m

w 24 SV-6531 0xygen Sample Line 17 SIAs B

[

37 na 29-1 Plant Water NA m

ga 142-1 NA 38 NA CV-5460

  • Demineralized Water NA E

2 e

w*

h 39 NA 130M3-1 Safety Injection Tank Test Line NA g

NA 130M3-2 NA o

n m

z e

?

41 NA MOV-652 (2)

Shutdown Cooling NA NA MOV-651 (2)

NA O

O O

O O

O TABLE 3.6-1 (Cont.)

CONTAINMENT ISOLATION VALVES 9

G9 PENETRATION ISOLATION ISOLATION VALVE ISOLATION

~'

NO.

CllANNEL IDENTIFICATION NO.

FUNCTION TIME (SECONDS)

C 44 NA 238-1 Fire Protection NA NA 238-1 NA NA M0V-6200 =

NA g

-i 47A NA SV-6540A Hydrogen Sample Outlet NA E

NA SV-6507A NA l

E x*

47B NA SV-6540E Hydrogen Sample Outlet NA NA SV-6507E NA l

1 47C NA SV-6540F Hydrogen Sample Outlet NA m;

NA SV-6507F NA

'?

O 47D NA SV-6540G liydrogen Sample Return NA NA SV-6507G NA E

48A NA MOV-6900 Hydrogen Purge Outlet NA E

5" NA MOV-6901 NA u

k k

x

.o

I TABLE 3.6-1 (Cont.)

g

-CONTAINMENT ISOLATION VALVES g

g H

PENETRATION ISOLATION ISOLATION VALVE ISOLATION p

NO.

CHANNEL IDENTIFICATION NO.

FUNCTION

. TIME (SECONDS) s

?

1 48B NA 238-1 Hydrogen Purge Inlet NA NA MOV-6903 NA g

i r

=a 49A NA SV-6540B Hydrogen Sample NA g

NA SV-6507B NA n

E N:

49B NA SV-6540C Hydrogen Sample NA NA SV-6507C NA w

49C NA SV-6540D Hydrogen Sample NA

{

NA SV-65070 NA T

's 50 NA Blind Flange ILRT NA NA Blind Flange NA

'c S

59 NA 29M3-1 Refueling Pool Inlet NA h

NA 29M3-1 NA o

z 60 NA 130-2 Steam to Reactor Head Laydown NA e

NA 19-1 NA O

O O

O O

O TABLE 3.6-1 (Cont.)

C0llTAlflMENT ISOLATION VALVES C

1 G

U1 ISOLATI0t(

ISOLATION VALVE

~i PEllETRATI0ll ISOLATION P

NO.

CHAN$EL IDEllTIFICATI0li NO.

FUNCTION TIME (SECONDS)

M 3

61 NA 76Y-1 Refueling Pool Outlet NA NA NA 293tt-1 c-NA NA 293t4-1 33 NA

-1 NA 293M-1 62 SIAS A MOV-6579 Containment Heating Outlet 113 64 NA 238-1 Containment. Iteating Inlet

'NA R

m 5

?

~~

G m

E RJ (1) Manual or remote manual valse which is closed during plant operation.

(2) May be opened below 300*F to establish shutdown cooling flow.

(3) Containment purge isolation valves will be shut in MODES 1, 2, 3, and 4 per TS 3/4 6.1.7.

May be open on an intermittent basis under administrative control.

Containment purge isolation valves isolation times will only apply for MODES 5 and 6.

y Isolation time is NA for MODES 1, 2, 3, and 4 per TS 3/4 6.1.7.

y

+

P, m

Zo I

%w

_E!; CLOSURE 4 Page 1 of 9-(])

C0fiTAINMENT SYSTEMS 3/4.6.4 CON'TAINMENT ISOLATION VALVES LIMITING CONDITION FOR OPERATION 3.6.4.1 The containment isolation valves *specified in Table 3.6-1 shall be OPERABLE with isolation times as shown in Table 3.6-1.

APPLICABILITY: MODES 1, 2, 3 and 4.

ACTION:

With one or more of the isolation valve (s) specified in Table 3.6-1 inoperable, either:

Restore the inoperable valve (s) to OPERABLE status within 4 a.

hours, or b.

Isolate each affected penetration within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> by use of at least one deactivated automatic valve secured in the isolation

,- 3 U

position, or Isolate the affected penetration within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> by use of at c.

least one closed manual valve er blind flange; or d.

Be in at least HOT STANCBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the folicwing 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

SURVEILLANCE REQUIREMENTS 4.6.4.1.1 The isolation valves specified in Table 3.6-1 shall be denon-strated OPERABLE prior to returning the valve to service af ter maintenance, repair or replacement work is performed on the valve or its associated actuator, control or power circuit by performance of a cyclina test and verification of isolation time.

contain,nt paru r solo. im v. > 1 w - of rable 3.6-1 < hall be c 'ord i n ' '.N.S 1,

2, 3,

,nd 4; I ;ola t i on t in *

  • upecified do n d ippi.

Technical Sp ec i f ica t i on 1/4 6.1.7 referw.

CALVERT CLIFFS - UNIT 2 3/4 6-l' en! ment ':n.

3 ESCl.0SURC 4 Page 2 of 9 COSTAIN':ENT SYSTEMS i

SURVEILLANCE REQUIRDIENTS (Continued) 4.6.4.1.2 Each isolation valve specified in Table 3.6-1 shall be demonstrated OPERABLE during the COLD SliUTD0'JN or REFUELING MODE at i

least once per 18 months by:

a.

Verifying that on each containment isolation Channel A or Channel B test signal, each required isolation valve actuates to its isolation position.

l b.

Verifying that on each Containment Radiat ion-liigh Test Channel A or Channel B test signal, both required containment purge valves actuate to their isolation position.

c.

'Je ri f y ing that on each Safety Injection Actuation Channel A or Channel L test signal, each required isolation valve actuates to its isolation position.

4.6.4.1.3-The isolation time of each power operated or automatic valve of Table 3.6-1 shall be deter nined to be within its limit when tested pursuant to Technical Specification 4.0.5 4.6.4.1.4 Containment purge isolation "alve operability shall be determined at least once e ve ry 18 nonths by verifying that when the measured leakage rate is added to the leakage rates determined pursuant to Technical Specification 4.6.1.2.d for all other Type B er C penetraticna, the cembined leakage rate is less than or equal to l

0.6o ta.

CALVERT CLIFFS - I' NIT 2

4 6-18 Arendment No.

O O

O TABLE 3.6-1 C0tiTAlflMErlT ISOLATI0tl VALVES

=

N pef!ETRAT10tl Isot.ATION ISOLATION VALVE ISOLATI0tl

[

tl0.

CllANNEL IDEtiTIFICATI0il fl0.

FurtCTI0tl TIME (SEC0!lDS) 7, w

1A sIAs A CV-5465 R.C. and Pressurizer Sampling 17 c;

sras A CV-5466

<7 7_7 5

SIAs A CV-5467 sIAs B CV-5464 17 re 18 stas A CV-2180 Containment Vent Header To Waste 17 5

SIAs B CV-2181 Gas 17

s El s~

R 1C sIAs A CV-506 RCP Seals Controlled Bleedoff

$7 s

SIAS B CV-505 17 T

m*

10 SiAS B SV-6529 0xygen Sample 17 2A SIAS A CV-515 Letdown Line

<l3 SIAs B CV-516 713 T

(

iA m

NA 7M3-1 NA 7tt3-1 flA i

e g

z NA CV-Sl7 Charging Line flA R.

28

.F NA CV-518 flA o

NA CV-519 NA NA SP-210M3-2 flA NA 210M3-2 flA

TABLE 3.6-1 (Cont.)

C0f1TAlfiMEfiT ISOLATI0fl VALVES ifi Ei ISOLATI0ft VALVE ISOLAT10ft o

pef 1ETRATI0ft IsoLAT Io;;

h fi0.

en.m ri,s IDEfiTIFICATI0ft fl0.

FUf1CTI0ft TIME (SEC0! IDS)

Ul 7A

A Blind Flange ILRT fiA Ei
s 19-1 11A Z

td 7B

A Blind Flange ILRT flA
A 19-1 f1A G

O

-g m

8 sIAs A MOV-5462 Containment fiormal Sump

<13 E*

sIas a fl0V-5463 713 g

e s.

{

9

A 238M3-1 Containment Spray itA

!s

>:A 238M3-2 flA 10

.:A 238M3-1 Containment Spray ftA

A 238M3-2 flA 13 sras A, c;<s A CV-1410 (3)

Purge Air Inlet

<7**

2 fr SI As n, cits a CV-1411 (3) 17**

3 i

g s~

O

?

j

~ex_

L

O O

O I

TABLE 3.6-1 (Cont.)

h C0tlTAltiMENT ISOLATI0tl VALVES 2

S i

PENETRATION ISOLATION ISOLATION VALVE ISOLATION nC (10.

CHANNELS IDENTIFICATION NO.

FUNCTION TIME (SEC0flDS)

I m

14 SIAS A, CRS A CV-1412 (3)

Purge Air Outlet

<7**

F.

SIAS B, CRS B CV-1413 (3) 77 **

I U

15 s1As A CV-5291 Purge Air Monitor

<7 SIAS B CV-5292 77 E

~

9 e

16 cIs A CV-3832 Component Cooling Water Inlet

$18 l

1 M

2

^

18 CIs a CV-3833 Component Cooling Water Outlet 118 T

N i

19A NA 223-1 Instrument Air NA I

CIS A MOV-2080 113 i

19B NA 19-2

  • Plant Air flA g

NA 130-1

  • tlA I

E c.

c 20A NA 223-1 fiitrogen Supply flA u

n NA CV-612

  • flA o

y NA CV-622

  • flA T

NA CV-632

  • NA NA CV-642
  • NA 4

=

,_ _.f%=w %.-

!:Nats"n3 Page 6 of 9 l

l ZC OZ

~C Wu

< LJ

.. : a

= <

< rr N

ts v}

v1 Z=

Z ZZ ZZ Ov I

~%

El I

l

~

~!

O C

r-I u

v1 O

H eq C

M C

m L

d Zl L

O O

H O.i C

C o

?

c C

O P-- I h

h A-3 O

C s,.3 c:>

e-e--

C e

.e LU Z!

L1 Q.

O O

"O M

P

--4 L._ !

C l

C 1

L Dj C.

C F-r-

O U

O ql ei,

+

w U

O

.N u,

m C

u c.;

e u

C

>l i

r-C 4.J C

Cl

!*l C

C m

m n

n

~

C uj O

b 3

L 3

O O

a C

C c

I C

i O

O M

C u

"O H

L L

cn C

O p

i a

j 4J u

h,

c E

3 e

w r

x O

e

.C O

Z l C I

Cw C

A W

C. '

I m

m f

I l

1 w

La I

i l

w H1 i

8 C

Z I

i et, u)I b

i Z

i i

~I w Ol I

<l i

i

>Z l

l a

< Zl

~~

Z u

l j

O

>O, 4

NN ZH I

I i

a<

l l

O c

-N j

N-

-u

, e m

i e i i em H~

-N l

r-- N i

N W

r-r MM C 'O ef Lu !

1 Q

EE f

I I

e i

  • 7 C

f I

3

_; ~

mm mm i

i i

a N i

OO a-cs N t

e; N i

!mm I oo e -r mZ mN t

c;c;

! u m

N-u i Ex

- u.

r a

l 1

l

-l l

l

'I i

5

-' {

1, i

{

i

}

i g

i.

t i

j c

i I

1, l

l i

I f

a l

C i

i i

j i

i

~

i i

i I

I 5-i i

et r.

(.)

I Z Cj C

C M

er tw CO H Zl r;

N ca f

m m

'l Ci M

[

'?

W l

I l

i, l

1 e

i LJ C+.

l 1

(4 v

CALVESI CLIFES - OlI.'

3/d 0-22

. nd 1n t '!o.

O O

O TABLE 3.6-1 (Cont.)

C0tiTAINMEf1T ISOLATI0fi VALVES

-=9 PEtlETRATIO!1 ISOLATION ISOLATI0fl VALVE ISOLATI0f1

~*

tt0.

CHANNEL IDEtiTIFICATION li0.

Ful1CTI0fi TIME (SEC0 fids)

C 44 NA 238-1 Fire Protection flA NA 238-1 tiA NA MOV-6200

  • flA g

.=,

47A

a SV-6540A liydrogen Sample Outlet flA E

3a SV-5507A flA Q

w 55 47B ga SV-6540E ilydrogen Sample Outlet fiA na SV-6507E ilA 47C sa SV-6540F Hydrogen Sample Outlet NA w'g sa SV-6507F flA T

U 47D NA SV-6540G liydrogen Sample Return flA NA SV-6507G ilA 48A NA MOV-6900 Hydrogen Purge Outlet fiA m

El NA MOV-6901 NA

~

p e

0

f TABLE 3.6-1 (Cont.)

??

C0f1TAlfiMEf1T ISOLATI0ft VALVES G

93 pef 1ETRATI0fl ISOLATION ISOLATI0f4 VALVE ISOLATI0f4 P

fi0.

cilANNr.L IDEflTIFICATI0ft fl0.

FUtiCTI0ff TIME (SEC0f1DS) 9 lA 48B NA 238-1 ilydrogen Purge Inlet flA c;

NA MOV-6903 f1A 49A NA SV-6540B llydrogen Sample f1A NA SV-65078 fiA g

o 49B NA SV-6540C llydrogen Sample fiA NA SV-6507C f4A 49C

':A SV-6540D llydrogen Sample f1A

,,g Na SV-6507D fiA 7

2 50

A Blind Flange ILRT flA NA Blind Flange fiA k

y 59 NA 29M3-1 Refueling Pool Inlet fiA fr NA 29M3-1 f1A 6

m g

o y

60 NA 130-2 Steam to Reactor Head Laydown fiA e

NA 19-1 f1A O

O O

l

ENCLOSURE -4 Pap q of 9

-m

(~}

h.c tJ o=

-o wu m

<W

m l

.=

v ov

==

m

>== W rs

=:-

.~,-

e-4 C

C

    • J N

C M

C th c

H rA M

L W

G M

0 C

c.

O c-C M

c--

C Z

5 C-O L

p O

e-e e

.J t

O cJ e-O Ch M

C Z

4 C

C-L C

^,

o 3

-c=

-e-c w

o a

a C.

g C

C*

H c

c-O 3

0 0

0 U

$ s*

m U

r-W

=

0

=

=

a

~

~

C b

g-o

^

"O O

C t.)

J W

C.

M M

C C

r--

Ch m

cc 9

C C4 0

0 C.

C C

o z

o O

C E

E y

=

r-C C

c) w w

.-4 %

w a

r. -

e r-C O

O u

-A m o

n C

-e-O C

C 4

e-W 3

4 L

U Z

b 3 (a m

U H

1 C

C 3

t3 J

D O

O

  • Q C

C E

A O

CC U

U 3:

?b

~

C b

"J "O

O C-c)

"C d

(*)

m E

)W v1 M

C O

3 Q

g 4

e-

.C

~~

.% 3 n

cc z

U D

y s

w

.=

3 u 5 E

U1

.C m

n 2

  • c=

D a

.C r<

s LaJ C e-*

M O

OM

>Z 4

n H

J U

O 3

Z a

(

Z

<Z d

N

(

C

>C 4

4.J Z

.0 Z

u ZH CB 3:

U1 "J

C J

  • O C

>~

N

.O <

-- u eme-t.n U

4 O

E u

C fM

[

H r i : i c

C

> W k

c:' !

  1. CEE 3

i e-

+>

>= M CO C

e c, M M oo o

M u.

C Ee J=

c" mC SNNN E

N O

.U

.% #d

~

C C

C a

a.

nu u

~w u

Q YC 5

O Y

J

~

O u

e Z *k""

Z C

C5 A

  • e4
  • h, i

C C

L C

_ Z I

a

^

't C

r y.a H <'

f

<Z O

L L

C$

't. Z 1 %

'A

?

E c

r C

= o c, ;

e a

c

a. e

.s 4.J w

c l

z o

.)

C u a l

^-a C

t.,,

1 O

C S

C 90 n

o ao C

C +

o,

~

c 4 u

~

C

.O C C a

u-

\\

C h

r=

n l

W 5;

c d

yC i

d d

~I' c-: C e--

N

&2 D

D

%3 U

l e

i

=

N m

e W

5 v

v v

n l

l I

el1/ tK i-L rr3 - Uh$l i

./*

Amendment llo,

Y O

.i u

l I

ENCLOSURE 5 Leakage rate testing for Containment Purge Isolation Valves is accomplished under CCNPP STP-M-571, which is the leakage rate test for all containment penetrations except the air locks. This test procedure utilizes 10 CFR 50 Appendix J and ASME Boiler and Pressure Vessel Code IWV for Type C, Category A 6" or greater valve pressure decay test method. Test volume (between the two supply or exhaust isolation valves) is pressurized to at least Pa by penetration number (i.e., penetration #13 or #14). Pressure is applied and monitored through a test connection utilizing a leak rate monitor while pressure decays over a one hour period, with data recorded every fifteen (15) minutes. The highest leakage rate of the five (5) readings is considered as valve leakage rate and used in total leakage rate calculations. This highest leakge rate figure is compared to:

a) Previous leakage rate (trend analysis),

b) Expected leakage rate (per ASME Code IWV3427b),

c) Action Icakage rate (7092 sccm or per IWV 3427b) to determine increa.w d surveillance, and d) Technical Specification leakage contribution for containment purge isolation valves, identified as 40,000 seem (pursuant to TS 4.6.1.2.d) to identify seal inspection, repair, or replacement.

To date, no seal replacements have been required per the following data:

UNIT 1 LEAKAGE RATE TEST DATA DATE l-CP-1410 & 1411 CV's 1-CP-1412 & 1413 CV's PRE-OP 200 sccm 64 sccm 12/05/75 0 seem 189 sccm 03/24/77 1945 scem 2347 sccm 03/30/78 1458 seem 0 seem 07/15/79 486 sccm 417 sccm 12/18/80 979 sccm 1458.5 scem UNIT 2 LEAKAGE RATE TEST DATA DATE 2-CP-1410 & 1411 CV's 2-CP-1412 & 1413 CV's 10/15/77 594 sccm 489 seem 10/23/78 12154 scem 0 scem 12/03/79 1944 sccm 0 scem 03/05/81 972.3 scem 833.6 scem