Forwards Public Version of Radiological Emergency Response Plan Implementing Procedures,Including Procedures EP-AD-1 Re Plant Emergency Organization & EP-AD-2 Re Emergency Classification Determination
ML20038C377
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 11/25/1981
From: Mathews E
WISCONSIN PUBLIC SERVICE CORP.
To: Harold Denton
Office of Nuclear Reactor Regulation
Shared Package
ML111671041 List:
References
CON-NRC-81-191 NUDOCS 8112100538
Download: ML20038C377 (2)


Text

,

NRC-81-191 WISCONSIN P U B LI C S ERVICE CO RPORATION P.O. Box 1200, Green Bay, Wisconsin 54305 c A M

, eECWg ,

ROV 30 m y November 25, 1981

.k

% p

\, % Y Dr. Harold R. Denton, Director ,

Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D. C. 20555

Dear Dr. Denton:

Docket 50-305 Operating License DPR-43 Kewaunee Nuclear Power Plant Radiological Emergency Response Plan Implementing Procedures Pursuant to 10 CF.R Appendix E, Wisconsin Public Service Corporation hereby submits ten copies of the Kewaunee Nuclear Power Plant Radiological Emergency Response Plan Implementing Procedures listed below. By copy of this letter, three copies of these procedures are hereby submitted to Mr. James G. Keppler, Director, U.S. NRC, Region III, Glen Ellyn, Illinois.

EP-AD-1 Plant Emergency Organization EP- AD-2 Emergency Classification Determination l EP- AD- 3 Unusual Event f EP-AD-4 Alert l EP-AD-5 Site Emergency EP-AD-6 General Emergency EP-AD-7 Notification of Unusual Event EP-AD-8 Notification of Alert EP-AD-9 Notification of Site Emergency EP- AD-10 Notification of a General Emergency EP-AD-12 Personnel Assembly and Accountability EP-AD-15 Recovery Planning EP-EOF-1 Corporate Staff Emergency Response Organization EP-EOF-2 Emergency Operations Facility Activation EP-EOF-3 Corporate Response to an Unusual Event EP-EOF-4 Corporate Response to an Alert EP-EOF-5 Corporate Response to a Site Emergency EP-EOF-6 Corporate Response to a General Emergency EP-EOF-7 Communications and Documentation 38 811204 h

EF afhK05000305 6%

PDR

Dr. Harold R. Denton November 25, 1981 Page 2 EP-SEC-2 Security Force Response to Emergencies EP-SEC-3 Personnel Accountability, Initial and Maintaining EP-RET-2B Gaseous Effluent Sample and Analysis EP-RET-2F Personnel Decontamination EP-RET-4A EOF Radiological Monitoring EP-RET-4B Radiological Controls at the Site Access Facility Several of the enclosed procedures will be revised and reissued based upon findings contained in the NRC Emergency Preparedness Appraisal report dated Octcher 29, 1981. A complete issue of the Emergency Plan Implementing Procedures, in a single binder, will be made during December. Although the enclosed procedures are currently approved, the impending reissue of the implementing procedures should be considered in conducting your review.

Very truly yours,

.k Y)dsb r nt)

E. R. Shthews, Senior Vice President Power Supply & Engineering snf Enc.

cc - Mr. J. G. Keppler, Region III - NRC (3)

Mr. Robert Nelson, NRC Resident Inspector - w/o enc Mr. Jesse Pagliaro, US NRC - w/o enc l

l l