ML20035H335

From kanterella
Jump to navigation Jump to search
Insp Rept 50-302/93-10 on 930330-0402.No Violations or Deviations Noted.Major Areas Inspected:Engineering & Technical Support & Mgt Response to Operational Events
ML20035H335
Person / Time
Site: Crystal River 
Issue date: 04/27/1993
From: Fillion P, Shymlock M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20035H331 List:
References
50-302-93-10, NUDOCS 9305040244
Download: ML20035H335 (7)


See also: IR 05000302/1993010

Text

I

.

"I

.[(g" 4

g

UNITFD STATES

-

fg

NUCLEAR REGULATORY COMMISslON

.)

g

n

REGION Il

,j

101 MARIETTA STREET, N.W.

5

-y

,

l

f

ATLANT A. GEORGI A 30323

g

/

.....

I

Report No.: 50-302/93-10

Licensee:

Florida Power Corporation

3201 -34th Street, South

St. Petersburg, FL 33733

i

Docket No.: 50-302

License No.: DPR-72

i

Facility Name: Crystal River 3

-

Inspection Conducted: March 30 - April 2, 1993

4[BM93

Inspector:

/

PaulJ.Fiyion

Date' Signed

Approved by:

7

fffh2[$7

YW 7 -93

Milton B. Shymfock, Chief

Date Signed

Plant Systems Section

Engineering Branch

Division of Reactor Safety

SUMMARY

Scope:

This routine, announced inspection was conducted in the areas of engineering and

technical support and management response to operational events. The analysis

of and corrective actions for operational events was evaluated by the inspector.

Results:

In the areas inspected, violations or deviations were not identified.

In the

aftermath of a major storm on March 13, 1993, the stability of the offsite power

supply became an issue. The licensee's decisions and actions in relation to this

situation were reasonable.

A loss-of-power event occurred on March 29, 1993,

during an outage. Analysis of cause and corrective actions were adequate.

930504o244 930427

PDR

ADOCK 05000302

0

PDR

.

!

'

.

i

REPORT DETAILS

-

,

1.

Persons Contacted

Licensee Employees

N. Barbeito, Senior Standards Engineer, Substation Standards

D. Carrico, Supervisor, Systems Protection, Crystal River Complex

  • M. Fitzgerald, Supervisor, Systems Engineering
  • E. Froats, Manager Nuclear Compliance
  • F. Fusick, Manager, Design and Modifications
  • B. Hickle, Director, Nuclear Plant Operations

W. Morgan, Field Supervisor, Substation Maintenance

S. Puckett, Supervisor, Central Division Area Substation

R. Sweeney, Shift Technical Advisor

  • R. Widell, Director, Nuclear Operations Site Support
  • R. Wiemann, Senior Nuclear Electrical Engineer, Systems Engineering
  • K. Wilson, Manager, Nuclear Licensing

Licensee employees contacted during this inspection included engineers

and technicians.

NRC Personnel

  • R. Freudenberger, Resident Inspector
  • P. Holmes-Ray, Senior Resident Inspector
  • Attended exit interview

2.

Inspection Details

a.

Background Information

On March 13, 1993, Crystal River 3 was in their mid-cycle

e

maintenance outage. A major storm system lasting two days brought

high winds and high tides to the area surrounding the plant.

Consequences of these climatic conditions at the site included a

>

buildup of salt on the switchyard insulators and flooding of the

!

switchyard for one tide cycle. The buildup of salt on the

insulators was due to the fact that on the second day of the storm

there was high onshore winds carrying salt laden sea spray, but

there was no rain to wash off the insulators.

Some insulators in

the switchyard were damaged by wind induced vibrations or

missiles. Also as a result of the storm the entire transmission

system was degraded. About 1000 miles of transmission line were

deenergized. The buildup of salt on the insulators meant that

,

insulators would have to be washed. That work was done on March

r

17 for the 230 kV switchyard and on March 25, and 26, for the 500

kV switchyard.

i

-

.

-

.

.

_

.

.

2

Then on March 29, automatic tripping of all 500 kV circuit

breakers in the ring bus (refer to diagram) resulted in loss of

power to plant auxiliaries because the source of power at that

time was the 500 kV bus via the generator stepup transformer as is

normal for outage time.

Post-event analysis showed that the

circuit breaker tripping was caused by a short-circuit in a cable

trench.

Given this background, the inspection plan was to evaluate the

licensee's decision making process with respect to the timing of

the insulator washdown. The inspector would evaluate the

licensea's efforts in determining the root cause of the loss-of-

power.

Particularly NRC wished to determine whether or not the

March 29, event was caused by storm related damage.

Operational consequences of these power outages will be addressed

in the resident inspectors report covering the time period.

Preliminary, analysis indicates that all safety-related systems

performed as designed.

b.

High-Voltage Insulator Washdown

On the day of the storm, Saturday, March 13, flooding of the

switchyard had subsided by late day which allowed insulator

>

replacement work to commence. On Sunday, insulator replacement

work continued. Bushings on 230 kV transformers for Crystal River

3 were cleaned as part of normal outage scheduled maintenance. On

1

Monday, no major work was taking place. The Field Supervisor for

the switchyard observed some partial discharge on the surface of

the vertical bus bar insulators in the 230 kV yard. Partial

discharge is an electric discharge which only partially bridges

,

the insulation between conductors.

Partial discharges occur when

the local electric field intensity exceeds the dielectric strength

of the dielectric involved, resulting in localized ionization and

breakdown. He was able to observe this because partial

discharges are often accompanied by emission of light and sound.

The partial discharges were due to the fact that the high winds of

Sunday had deposited salt on the insulator surfaces. The 500 kV

yard had little or no visible partial discharge taking place

because the bus bars were overinsulated to 700 kV.

,

So the situation was that the 500 kV was relatively stable and it

was not in imminent danger of flashover. The plant was being

powered from the 500 kV. The 230 kV had visible partial discharge

,

indicating that insulator washing should be scheduled. The

partial discharges were not at a level that called for immediate

action.

The situation on Tuesday was basically the same as Monday.

9

At about 4:00 am, on Wednesday, a fine mist or drizzle of rain

,

commenced.

The combination of salt and moisture created a

,

.

-

~

.

.

3

condition of lowered effective insulated leakage distance along

the surface of the insulator which allowed an excessive leakage

current to flow which resulted in insulator flashovers in the 230

kV yard. Some circuit breakers went through their reclosing

cycle, which is a rapid opening and closing.

The 230 kV yard was deenergized by operator action on the

afternoon of Wednesday, March 17, and the insulators were washed.

t

It is feasible to wash insulators while energized, but the

deenergized method was chosen. The washing evolution took about

six hours. Once the washing was completed, the 230 kV bus was

reenergized and no further flashover or partial discharges were

experienced.

The insulators in the 500 kV yard were washed on March 25, and 26.

I

This was strictly precautionary because the 500 kV buses never

>

experienced severe partial discharge problems.

-

With respect to the preceding discussion and the main thrust of

the inspection, the relevant requirement is to provide reliable

-

sources of offsite power and to maintain due regard for shutdown

!

risk. The inspector reviewed the evolutions that took place in the

aftermath of the storm of March 13 in light of these

considerations, and concluded that the licensee's decisions and

actions were reasonable.

,

c.

Loss-of-Power Event of March 29

,

At approximately 1:50 am, on March 29, 1993, the plant experienced

a loss-of-offsite-power during a mid-cycle maintenance outage

while backfeeding through the generator stepup transformer. The

licensee formulated a theory on the sequence of events leading to

'

the loss-of-power.

First, a short-circuit occurred on either a

250 VDC cable or a 480 V cable. The short-circuit occurred in a

cable trench in the 500 kV switchyard. The 250 VDC and 480 V

i

cables were lying adjacent to each other.

The 250 VDC cable was a

nine conductor cable running between a relay rack in the

switchyard relay house and 500 kV motor operated switch MOS1873

(refer to diagram for location of this switch in the system.) The

480 V cable was a one conductor cable which was one phase of a

three phase circuit running between a motor control center in the

plant and a 230 kV transformer. Each conductor of a three phase

480 V circuit is 277 V above ground potential.

Second, regardless

of which cable shorted first eventually both cables were damaged,

'

conductors of each came in contact and as a result 277 Y was

,

superimposed on the switchyard DC System. This caused spurious

operation of auxiliary relays which caused tripping of all 500 kV

'

circuit breakers in the ring bus.

The inspector reviewed all available information, and concluded that the

i

licensee's hypothesis on the cause of the loss-of-pcwer event was valid

and the most probable cause that could be deduced from the evidence.

r

,

?

?

.

'

.

.

4

The following specific inspection activities were performed in this

effort.

l

(a)

Reviewed the substation sequence of events recorder

'

printout.

i

(b)

Reviewed the plant computer alarm printout.

'

(c)

Reviewed the control diagram for.MOS1873. This was relevant

j

because the switch partially opened and the sequence of

i

events recorder and plant computer show the switch rapidly

cycling. The recorder printout was actually a false signal

!

caused by the short-circuit, but it does indicate the time

i

that the fault occurred.

!

f

(d)

Examined the faulted cables.

(e)

Inspected the cable trenches.

(f)

Held discussions with the substation engineers.

,

The root cause of the cable fault has not as yet been determined with

any certainty. The damaged cables were sent to a cable manufacturer's

.

laboratory for root cause analysis. A report from the laboratory is

i

expected to be forwarded within two weeks of this inspection. The

i

preliminary conclusion is that the short-circuit is not directly related

to the flooding.

Submergence of the cables' was of-relatively short

duration and therefore by itself would not be expected to have caused

-j

the failure of a cable starting with good integrity.

Probabl, some pre-

'

existing cable defect interplayed in some manner with the flooding to

j{

-

,

produce a delayed reaction (16 days.) Cables away_ from the fault looked

normal and there has been no history 'of cable failures according to the

1

substation engineers, although they do not keep records.of all cable

faults.

.I

In order to maintain a record of the type of cable involved and the

>

method of installation, the following information is given. The control

!

cable was rated 600 V.

Each of the nine conductors had polyethylene

insulation and a polyvinyl chloride jacket. The assembly had_a

j

helically wrapped copper shield and an overall polyvinyl chloride-

1

Jacket. The conductors were No. 9 American Wire Gauge copper. The power

l

cable was rated 600 V and it- was single conductor 250 thousand circular

j

mils copper.

Insulation was type-THW/THHN/THWN as described in the

National Electrical Code. The control cable was installed about 17

i

years ago and.the power cable was-installed about two years ago. Both

q

cables run cold in normal operation because they carry relatively low

currents.- They were installed in a trench having a sand bottom, concrete

sides and a heavy gauge aluminum top. The purchase specification stated

'

that the cables would be installed in a trench, and they were Florida

i

Power Corporation's standard type cables.

1

?

!

!

!

I

-

.

-

-

-

- - -

. .

. - - - -

-

.

.

-

.

.

5

e

The licensee's corrective actions for the loss-of-power problem

included:

(a)

Inspection and insulation resistance measurement of all

!

cables in the trench.

(b)

Removal and replacement of any damaged cable or cable having

a relatively low resistance reading. About 15 cables were

replaced.

(c)

Testing of any circuits affected by the cable replacement

.:

work.

'

(d)

Inspection of all trenches in the 500 kV and 230 kV

switchyards.

'

(e)

Documentation of the cable replacements and circuit testing.

(f)

Evaluation of the root cause of the event.

(g)

Examined MOS1873 for possible damage. This was a

precautionary measure taken because there was some

possibility that the switch had opened under load. No

deterioration of the switch was found.

(h)

The event and corrective actions were reviewed by the Plant

Safety Review Committee.

(i)

A complete design review from the reliability perspective of

the switchyard was initiated. This was well beyond the

minimum actions necessary to respond to this event.

In relation to the inspection of this event, the most relevant NRC

requirement is the requirement to ascertain the root cause of events and

to implement appropriate corrective actions. The inspector's conclusion

was that the licensee met the requirements, because the event cause

analysis was correct and the corrective actions appropriate and

conservative.

!

3.

Exit Interview

The inspection scope and results were summarized on April 2,1993, with

those persons indicated in paragraph 1.

The inspector described the

areas inspected and discussed in detail the inspection results.

Proprietary information is not contained in this report. Dissenting

comments were not received from the licensee.

,

i

?

i

i

.

-

-

.

-

,

k

,

.

.

s

m

sn

-

3

)

.

.

,

R(

an7

-

.

-

6

-

c

4

6'

1

5

1

+

1

S

.

l

O

,

l

'

P

-

-

-

-

.

A

-

-

D

,

I

_

R

-

.

,

D

5

-

.

L

.

8/

N

4

F

8

1

0

--

<

_

1

1

6

9

l.

15r

l

5

8

A

l

l

-

T

S(

S)

,

R

,

N

O

O

E

M

.

N

bi

_

,

C

9

.

3

(8

,

i

3

.

,

1

-

9

.

0 1e

1

,

5 f"j

-

-

3

2

,

8

H

8

N

_

i

R O

-

t

- s-

E

I

[

N

0

,

V T

^5

-

6

6

A )

I

6

-

1

R T S

-

1

S U

-

D

L B B

M

.

s

A U G

0

-

ki

T S N

66

os

S

I

1Sy

E

'

/. i

Y V R

3

D

G

R K

(

N

-

1

6

C 0

_

D

6

.

-

I

,

0

_

RE

-

C

v

O

2

5

SI

_

O

w

M

.

.

s

R

e

-

_

.

i

B

-

.

>

.

1]-

_

c

r

-

N

4

!

.

I

2

8

.,

8

,

1

,

3

-

N

?-

,

7

I

8

-

C

,

I

%s

J_

-

1

t

'

n

z

SO

e

-

S

(

_

.i

0

S

,-

9

2

8

$_

,

6

i

l*

l

-

S

I

-

-

O

,

S

M

-

O

, "

N

-

,

,

.

'

n

_

-

_

t

'

a

-

3

.

,

-

3

-

hv R.

3

-

.

w

~

e

,

C

-

-

.

,

.

  • a ?!8w $a g*sia

,

3

A? M "

.

,e

,

  • %

+

I

-

-