Discusses Completion of Work to Address Issues Delineated in Suppl 1 to NRC Bulletin 90-001, Loss of Fill-Oil in Transmitters Mfg by Rosemount. Eight Rosemount Transmitters Removed & Replaced as of 930316
ML20035H048
Person / Time
Site: Brunswick 
Issue date: 04/26/1993
From: Mccarthy D
CAROLINA POWER & LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
IEB-90-001, IEB-90-1, NLS-93-094, NLS-93-94, NUDOCS 9305030030
Download: ML20035H048 (1)


Text

>

l CP&L Carolina Power & Light Company

!APR 261993 l

SERIAL:

NLS-93-094 l

l United States Nuclear Regulatory Commission ATTENTION: Document Control Desk washington, DC 2055' l

BRUNSWICK STEAM ELECTRIC PLANT, UNIT NO. 2 j

DOCKET No. 50-324/ LICENSE NO. DPR-62 I

RESPONSE TO NRC BULLETIN 90-01, SUPPLEMENT 1 LOSS OF FILL OIL IN TRANSMITTERS MANUFACTURED BY ROSEMOUNT Gentlemen:

The purpose of this letter is to provide Carolina Power & Light Company's (CP&L) notification of work completion at the Brunswick Steam Electric Plant, l

Unit No. 2 (BSEP2).

i In our response to NRC Bulletin 90-01, Supplement 1 for BSEF2,-CP&L committed to remove and replace eight (8) Rosemount transmitters to be in compliance with the Bulletin Supplement requirements prior to BSEP2 startup.

The eight (8) Rosemount transmitters have been removed and replaced as of March 16, 1993, as was committed in our response. BSEP2 has therefore complied with item 1 of the Requested Actions for Operating Reactors.

This commitment is considered closed.

If further information is needed, please contact Mr. Fred Emerson at (919) 546-7573.

Yours very truly, e

i s

David C. McCarthy Manager Nuclear Licensing Section JHH/jbw cc:

Mr.

S.

D.

Ebneter Mr. P. D.

Milano Mr. R. L.

Prevatte lA' l O; 3000C.-=>

-=

~-

at t rayetevine stre et. P O. aan 1551. Rai,4gs N c 27602 V

9305030030 930426 l

PDR ADOCK 05000324 M7"3 1

o PDR