{{#Wiki_filter:- . i APit 2 31993 g7
Docket Nos. 50-456; 50-457 > License Nos. NPF-72;-NPF-77 Commonwealth Edison Company , ATIN: Mr. L. O. DelGeorge ' Vice President,-Nuclear Oversight and Regulatory Services Executive Towers West III 1400 Opus Place, Suite 300 Downers Grove, IL 60515 Dear Mr. DelGeorge: , This refers to the inspection conducted by Messrs. S. G. Du Pont, C. E. Brown, and J. R. Roton of this office on March 2 through April 13, 1993. The inspection included a review of activities authorized for your Braidwood , facility. At the conclusion of the inspection, the findings were discussed with those members of your staff identified in the enclosed report. Areas examined during the inspection are identified in the report. Within these areas, the inspection consisted of selective examinations of procedures and representative records, _ interviews with personnel, and observation of , activities in progress. , ' During this inspection, certain of your activities appeared to be in violation of NRC requirements. The violation involved failure to perform a required surveillance. A Notice of Violation is not being issued because the criteria specified in Sections III.A and V.G.1 of the " General Statement of Policy and Procedure for NRC Enforcement Actions" (Enforcement Policy),10 CFR Part 2, ' Appendix C (1992) were satisfied.
1 In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this letter and the enclosed inspection report will be placed in the NRC Public Document Room. We will gladly discuss any questions you have concerning this inspection. Sincerel 0:isinalbenedbyHartinJ. Tarter 46 86+ ' Martin J. Farber, Chief Reactor Projects Section IA i Enclosure: Inspection Reports No. 50-456/93004(DRP), , No. 50-457/93004(DRP) ' See Attached Distribution RI, II Falber U.122 ! DR ADDCK 05000456 ~ [[ [ ] . 9ao4aoo13e 930423 PDR l l - , -
- . FJYl231993
- [
i Commonwealth Edison Company 2 . Distribution cc: w/ enclosure '! S. Berg, Site Vice President ! K. Kofron, Station Manager ' , A. Haeger, Regulatory Assurance Supervisor ' D. Farrar, Nuclear Regulatory Services ! Manager ! OC/LFDCB l Resident Inspectors, Braidwood, 'i Byron, Zion . D. W. Cassel, Jr. , Esq. 1 R. Hubbard J. W. McCaffrey, Chief, Public ! Utilities Division Licensing Project Manager, NRR R. Newmann, Office of Public ! Counsel, State of Illinois Center ' State Liaison Officer Chairman, Illinois Commerce Commission l l . . 1 1 , 1 .! , . - }}