ML20035G451

From kanterella
Jump to navigation Jump to search
Addition to Insp Repts 50-498/93-04 & 50-499/93-04
ML20035G451
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 04/22/1993
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20035G447 List:
References
50-498-93-04, 50-498-93-4, 50-499-93-04, 50-499-93-4, NUDOCS 9304270260
Download: ML20035G451 (24)


See also: IR 05000498/1993004

Text

4

-

ATTACHMENT 2

-

.

.

HANDOUT ONE

OUTAGE ORGANIZATION

,

V

I

1

i

9304270260 930422

.

PDR

ADDCK 05000498

PDR

G

.

. -.

. .

.

.

.

-

.

.

.

.

-

'

.

.

4

.

.

E

i

AGENDA

!

,

INTRODUCTION

r

OUTAGE DISCUSSION

Organization

Duration

Scope

,

t

Level 2 Schedule

SIILTfDOWN SAFETY

Organization

s

Process

.

,

,

CLOSING

t

t

,

i

!

>

P

6

i

-.

_ _ _ _ _ -

- _ - - _ _

__

___-_

_

_ _ _ _ _ _

. __.______.

_ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ -

_____ __- _ -__ _-__---____-___ _________ ---- _

.

4

.

2RE03

.

SHUTDOWNRISKASSESSMENT TEAM

.

PLANT

,

AfANAGER

CllAIRAfAN

SRA

PLANT OPS SRO

i

INDEPENDENT

INTEGRATED

SAFETYREVIEW

SHIFT TECIINICAL

PLANNING & SCHED

PLANTANAYLSIS

GROUP

ADVISOR

COORDINATOR &

REPRESENTATIVE

REPRESENTATIVE

SCHEDL1LER

,

4

a

i

_ . . _ , _ . _ _ _

- m-

.

.

. .

. . .

.

.

.

m .

.--

m

.

m.

-

.

E

i

SO m ~~'r

~~ E XAS

3 R Ou E C~~

"" "" :

L

REFUELING OUTAGE IMPLEMENTATION ORGANIZATION

2RE03

l

PLANT MANAGER

i

l

M

l

IPS MANAGER

'm

!

e

s

l

l

l

8

DEPT MANAGER -

8

DEPT MANAGER

DEPT MANAGER

8

OUTAGE MANAGER

PLANT OPFRATIONS

MAINTENANCE

TECHNICAL SERVICES

-

l

l

l

l

l

l

g

8

I

l

l

l

,

,

,

DEPT MANAGER

DEPT MANAGER

DEPT MANAGER

PLANT ENGINEERING

DESIGN ENGINEERING

NPMM

,

  • * MATRIX

-

-

.

=

.

. .

- .

.

-,

, _ . .

.

,

_

.

.

-.

.

.

.

" " " "

SOm-~-

~~ EXAS

3 R Ou EC~~

REFUELING OUTAGE IMPLEMENTATION ORGANIZATION

~

-

2RE03

.

OUTAGE MANAGER

M

OUTAGE SHIFT

MANAGER

ENERIMEM

-,

OUTAGE SCHEDULE

,

SUPERv'ISOR

m

.

l

l

l

I

f

,

COORDINATORS - I

BALANCE

OPERATIONS

OUTAGE

DISONNE

RCB/ MAS

OF PLANT

& TRAINS

i

AREA COORDINATOR

COORDINATOR

M

-

1

I

MM DISCPLINE

EM DISCIPLINE

IC DISCIPLINE

COORDINATOR

COORDINATOR '-

COORDINATOR

,

e

- __,__ _______ _ _

. .

.

-___ .,

..

.

.

_.,

_

.

.

.

, _

_

--

-

-

-

,-

,

.

OUTAGE DISCUSSION

-

ORGANIZATION - See Handout

-

DURATION

Breaker to Breaker = 78 days

=

,

,

Breaker to Mode 4 = 68 days

'

SCOPE

Statistics

-

1596 Service Requests

1697 Preventative Maintenance Activities

948 Surveillance Tests

4241 Total

,

includes:

'

Steam Leaks

Control Room Instruments

Inoperable Automatic Functions

-

Chemistry Monitors

'

Major Components

53 Modifications

.

Major Activities

-

.

-

Emergency Diesel Generators

5 year insp, #21

18 month insp. #22 & 23

MOVATS - 98 valves

-

-

Main Turbine

Replace LP #21 rotor

Repair HP Gland

.

'

-

Sludge Lancing

-

Reactor Coolant Pump Motors - 18 month PM

Feedwater Pumps

-

Main

,

Auxiliary

Boosters

i

'

Startup

Digital Rod Position Indication Inspection

-

>

E!Ll/SRA

_ . _ .

_

_

_ _

-

. __ _-_

_

...

.

.

LEVEL 2 SCIIEDULE

Critical Path

Polar Crane Repair

,

-

'

Crud Burst

-

.

MOVAT Testing Window

-

No Mode Window

-

,

'

-

RO Lineups & Surveillances

,

-

Ramp-up from Mode 4

Train Outages

-

,

Sequence of Mechanical Trains

-

-

Sequence of Electrical Trains

Safety injection Work Windows

-

ESF Loop Test

-

No Mode Window

-

Letdown and Charging

-

RHR & SI Loop Isolation Valves

RCP Work Window

-

Miscellaneous Work Windows

=

-

Sludge Lance

Turbine

-

Cire Water

i

-

!

SJLISRA

l

)

.--

__

_

.

.-

.

+

.

FLANDOUT TWO

.

SHUTDOWN SAFETY

,

L

a

- -

.

- .

.

-.

.-

.

,

-

.

,

.

SHUTDOWN SAFETY

Organization - see handout - make chart

-

Pre Outage Review

-

All Service Request for Scheduling Work Windows

'

-

-

Work Windows Scheduled to Support Plant Condition

Review Station Problem Reports Associated with Shutdown Safety

'

-

Special Review of any Off Normal Evolutions

-

Shutdown Risk Assessment Report Development

-

-

Review SRA Profile Chart

,

-

Incorporate Lessons Learned from Previous Outages

Review High Risk Areas in Schedule and Make Recommendation for

-

Schedule Change and or Contingency Plans

2

Request Calculation for Vessel Time to Boil and Spent Fuel Pool

-

Limitations

'

Review and Complete Risk Assessment Addendums in Accordance with

-

OPGP03-ZA-101

'

,

Finalize and Prepare Report for Plant Review Committee

-

'

Forward Report to IPS Manager for Approval

-

Forward Report to Plant Manager for Approval

-

,

During Outage

a

Conduct Schedule Review Meetings Twice Weekly

-

Review Activity Window Change Report

-

-

Review Activity Scheduled Outside of Window Report

i

SIL1/sRA

i

!

!

-

-

i

..

.- - .

..

-

.

-

..

=

- ...

. .

.

.

-

-

.

.

)

<

Review of Outage Additions Which Require SRA Review

-

Review any Major Schedule Changes

.

Maintain Daily Plant Status Forms

-

Present Plant Status at Daily Outage Meetings

-

F

Provide Review and Recommendations for High Risk Evolutions During

-

Outage as Required.

,

T

9

b

l'

h

, i

r

!

SILLSRA

.

l

- I

. - , . .-

. .

. - - . .

-

- .

. , . - . . . . . . ...

- - . .

.

EXECUTIVE SUMMARY SHUTDOWN R1SK ASSESSMENT-PROF 1LE

..m,

Et1

i

MAW

i

Aew

I

M4'

t

w

!s

73

39

(

t'

to

76

3

in

tr

34

LEst0NES

P

P

P

P

P

P

MODE 6

MODE 5

MODE 4

MODE 5

MODE 6

MCDE 7

ililCAL PATH

"

9

-

h

PLANI SIARfUP

-

GPEN MAIN CEN BRER

COHL

MCOE 2 TO MODE I

1 CCIN OufACEI

0F F L O AD

ENTER

PLANI

RE ACTOR

MODE 2

COOLCCbN

DI S ASSE Mft.ED

-.

-

-

4

ENtfR MO Df 5 tRCS C00tTO

wtActun

6 *t A N I 51ARIUP

CtoiE MAIN

E,

J

~C) N flHE R

6< t A*.it F1DI i

r1t y rf 4 Ill Mi sOf 7

f*F l OW .'00 DIGRff I

I

J

,

NtACIGH

Ha Df F ult t u

t uut

I Nif H MUDt

t. H W

I Nif H MGilE 4 4 8H 5

300 O[CP[

S)

DISASSfMOLv

N' MUDE

i<t L O AD

11 AO 1 [ tG l ONL U

HLAl&D IQ

=

NO MODE ACi1 v iIIt S

r nrif RflOAD

FLANI PWt P AR A T I ON

{NIER MODE i

s.tini t t 11

  1. tha iNIRT 10 M00f 4

(Post R

SU

>

I Udtil N t

LISTING

4A1H OtliACFS

CD

.

r

i

r

.

IR4(N

~8*

MECHAN! CAL OUIAGE

TRAIN

"C'

AGE & MAIN

L3.6RV BUS 2M

ELECTRICAL GUIACE

1RANS50RMER OUTACE

OUTACE

r,

,

r'

4

s

1

1'

4

IRAIN

  • B*

1RA(N

  • A*

ELECTRICAL OUIAGE

TRAIN

'C'

ME CH AN IC AL OUTAct

S T ANDfit

! H A N'J ORM[R 001 ACf

It FCiptC At OUTACF

I '

1

16AIN

"A*

M[CHANICat OgfAC[

s VN AV All ADL E

r-

t;Ni f 2 3RD REFUEtlNG OuiAGE

PL O S DAIEe 29JAN93

is..t

s .e

e

.

O

.

.

~

.

.

Shutdown Risk Assessment

OPGP03-ZA-0101

Rev. 1

-

Page 7 of 21

ADDENDUM 1

.

Midloop Operations

(Page i of 2)

NOTE

A 'NO" answer does not necessarily represent an

unacceptable risk situation, but identifies on

,

area that requires further evaluation or other

'

compensatory measures may be warranted.

YES / NO

1)

Is on-site electrical work which could perturb

mid-loop operation work minimized or avoided

during mid-loop conditions? (Including movement

of Cranes, etc., near transmission lines and

transformers)

/

2)

Is switchyard electrical work which could perturb

_f

mid-loop operations minimized or avoided during

mid-loop conditions?

/

3)

Are Loss of Off-site Power (LOOP) precursor

surveillances minimized or avoided during

,

mid-loop conditions?

/

4)

Are LOOP precursor activities minimized or avoided

in the operation unit during mid-loop conditions?

/

(Verify daily during mid-loop)

5)

Does the schedule support the implementation or

mid-loop procedural prerequisites?

/

6)

Are adequate controls in place to ensure RCB

containment integrity during mid-loop conditions?

/

__

,

7)

Are heavy load lifts in the RCB avoided during

mid-loop operations?

j

8)

Is the time in mid-loop configuration minimized?

/

9)

Are potential fire inducing activities minimized

or avoided during mid-loop configuration?

/

,

10) Are RHR modifications, work request, and tests,

l

not covered by mid-loop procedure requirements,

i

prohibited during mid-loop?

/

l

i

-

.

c

'

i

I

~

.

.

Shutdown Risk Assessment

OPGP03-ZA-0101

i

Rev. 1

Page 8 of 21

'

ADDENDUM 1

Midloop Operations

i

(Page 2 of 2)

,

YES / NO

11) Are RHR power supply modifications avoided during

/

mid-loop?

t

12) Is an adequate RCS vent path available when the

nozzle dams are installed?

/

13) Are there adequate controls to ensure proper

l

RCS level in place during mid-loop?

/

14) Are mid-loop conditions avoided for at least 7

days after shutdown?

/

15) If the answer to any of the above is "NO",

the

action should be reviewed relative to the associated

risk, outage activities and schedules. The outage

schedule should then be adjusted as necessary or

recommendations provided for management resolution.

.

b

.

F

t

t

t

!

?

,

0

$

b

.

.

.

.

'

.

1

,

Shutdown Risk Assessment

OPGP03-ZA-0101

Rev. 1

Page 9 of 21

ADDENDUM 2

Loss of Electrical Power

(Page 1 of 1)

NOTE

A "NO" answer does not necessarily represent an

_I

,

unacceptable risk situation, but identifies an-

area that requires further evaluation or other

compensatory measures may be warranted.

,

YES / NO-

i

1)

Will the emergency transformer (ET) be

available during mid-loop conditions?

/

,

2)

Will the ET be available throughout the outage?

/

3)

Will two Standby Diesel Generators (SDG) be

available during all Mode 5 or 6 operations?

/

4)

Are two sources of offsite power continuously

maintained throughout the outage?

/

5)

Is SDG backfeed capability maintained

'throughout the outage?

/

6)

Are switchyard activities coordinated with

Outage Hanagement to minimize or avoid impact

on operable power supplies?

/

)

!

7)

Is the use of non-standard electrical line-ups

minimized or avoided to meet electrical

requirements?

/

J

8)

If the answer to any of the above is "NO",

the

i

action should be reviewed relative to the associated

risk, outage activities and schedules. The outage

schedule should then be adjusted as necessary or

recommendations provided for management resolution.

'!

l

l

.

-

..

.

.

-

- .

-.

,

-

  • -

.

.

,

Shutdown Risk Assessment

OPGP03-ZA-0101

Rev. 1

Page 10 of 21

ADDENDUM 3

No Mode

(Page i of 2)

NOTE

A "NO" answer does not necessarily represent an

unacceptable risk situation, but identifies an

area that requires further evaluation or other

compensatory measures may be warranted.

YES / NO

1)

Are activities scheduled such that a minimum

of two FHB HVAC trains are available during

/

no mode?

2)

Will one or more-SDGs be available throughout

.'

the no-mode window?

(At least one operable

SDG must support a functional SFPCCS train)

/

s

c

j

3)

Will one or more SFPCCS trains be available

,

'

prior to, during, and immediately following

no mode?

/

4)

Is the functioning train (s) of SFPCCS supported

/

by an operable SDG?

5)

Do Rad monitor maintenance activities support

'

no mode and fuel movement activities?

/

,

.

.

6)

Are contingencies to provide SFP make up

readily available in case of loss of SFP

cooling? (Ref. OPOPO4-FC-0001)

/

7)

Is an operable LHSI pump available in case

of loss of SFP cooling?

/

,

8)

Is the available LHSI pump supported by an

i

/

operable SDG?

9)

Will the use of the in-containment storage

f

area for fuel storage be avoided during

no-mode?

/

10) Are activities avoided or minimized that could

perturb the functioning of the SFPCCS?

/

t

9

- -

- - - -

- -

- - - -

. - -

i

-

.

.

,

.

)

Shutdown Risk Assessment

OPGP03-ZA-0101

'

Rev. 1

Page 11 of 21

ADDENDUM 3

No Mode

(Page 2 of 2)

'

11) Are there two ESF electrical buses available

during no mode?

(one bus backed by a SDG)

/

12) If the answer to any of the above is "NO",

the action

should be reviewed in the relative to the associated

risk, outage activities and schedules.

The outage

i

schedule should then be adjusted as necessary or

recommendations provided for managagement resolution.

i

-

i

!

!

i

I

4

D

,

,

&

h

h

i

.

.

.

,

.

,

'

.

Shutdown Risk Assessment

OPGP03-ZA-0101

Rev. 1

Page 12 of 21

ADDENDUM 4

Pressurization

(Page 1 of 1)

NOTE

A "NO" answer does not necessarily represent an

unacceptable risk situation, but identifies an

area that requires further evaluation or other

compensatory measures may be warranted.

YES / NO

1)

Is Cold Overpressure Mitigating System (COMS)

available as required?

/

2)

Is a vent path established as required?

(Minimum of 2 sq. in.)

/

,

3)

Are high pressure injection systems rendered

-

inoperable at cold shutdown conditions?

(i.e. HHSI)

/

4)

If one or both pressurizer PORVs are inoperable

are the required RHR pumps and discharge relief

valves available?

/

5)

If the answer to any of the above is "NO",

the action should be reviewed relative to the

associated risk, outage activities and schedules.

The- outage schedule should then be adjusted

as necessary or recommendations provided for

management resolution.

,

I

I

1

0

L

.

--

..

.

..

-

+

,

9

'

Shutdown Risk Assessment

OPGt03-ZA-0101

Rev. 1

Page 13 of 21

ADDENDUM 5

Loss of Coolant Inventory

(Page 1 of 1)

l

>

NOTE

A "NO" answer does not necessarily represent an

unacceptable risk situation, but identifies an

area that requires further evaluation or other

compensatory measures may be warranted.

YES / NO

1)

Is a source of borated RCS makeup maintained

throughout the outage? (e.g., RWST, BATS)

/

2)

Is work on valves or other components that

could lead to an RCS draindown minimized or

avoided while fuel is in the vessel?

/

3)

Is the use of freeze plugs in conditions where

,

a f ailure could cause a loss of inventory

,

avoided?

/

i

4)

Is the Reactor Vessel Level Indication

System (RVLIS) calibrated and operable prior

to shutdown and during the outage?

/

5)

Is an alternate source of water available for

RCS make-up?

(e.g., Firewater, RMWST)

___

/

6)

Are there adequate controls to ensure instrument

air is available to the spent fuel pool gates?

/

7)

If the answer to any of the above is "NO",

the acticn should be reviewed relative to the

associated risk, outage activities and schedules.

The outage schedule should then be adjusted as

,

necessary or recommendations provided for

management resolution.

,

i

x -

'

..

m

.

.

Shutdown Risk Assessment

OPGP03-ZA-0101

Rev. 1

Page 14 of 21

ADDENDUM 6

Loss of Cooling

(Page 1 of 1)

,

NOTE

'

A "NO" answer does not necessarily represent an

unacceptable risk situation, but identifies an

-area that requires further evaluation or other

compensatory measures may be warranted.

TES / NO

1)

Are the required number of RHR trains available

for the plant shutdown conditions?

/

.,

2)

Are the required RHR trains supported by

operable SDGs?

/

'

3)

Are LHSI pumps available to mitigate loss of

,

cooling conditions?

/

'

4)

Although not required by Technical Specifications,

are HHSI pumps available to mitigate loss of

cooling conditions?

/

5)

Does the schedule support system / equipment

releases to minimize potential for

interrelated system LOCA's? (ie. RCS via RHR

release)

(Ref. OPOPO4-RC-0006, OPOPO4-RC-0007)

/

-

.

6)

Are electrical activities avoided that could

,

perturb the operable RHR trains?

/

1

7)

Are RCS related activities minimized or avoided

that could perturb the operable RHR trains?

/

l

8)

If the answer to any of the above is "NO",

the action should be reviewed relative to the

i

associated risk and the associated outage

)

activities and schedules. The outage schedule

should then be adjusted as necessary or

recommendations provided for management resolution.

!

j

i

F:

q

1

.

.'

-

,

i

]

.

~;

Shutdown Risk Assessment

OPGP03-ZA-0101

.

Rev. I

j

Page 15 of 21

ADDENDUM 7

Reactivity Management

(Page 1 of 1)

i

NOTE

A "NO" answer does not necessarily represent an

unacceptable risk situation, but identifies an

area that requires further evaluation or other

compensatory measures may be warranted.

'

YES / NO

1)

Is one CCP available during modes 4,

5, and 67

/

2)

Is the required boron injection path available?

/

,

3)

Are the source range monitors supported by an

i

operable SDG (SDG #11/#21) during critical

evolutions?

/

4)

When fuel is in the vessel, are there two

!

source range or extended range neutron

detectors available and supported by an

operable SDG7

/

-

5)

Is work on Boron Dilution Paths avoided?

(Ref. IPSP03-CV-0014)

/

6)

Are hydrostatic testing activities scheduled

to prevent an inadvertent RCS Boron dilution?

/

7)

Is the time minimized that the control rods

are not able to be inserted?

/

r

8)

Is Control Rod Lockout avoided in stodes 3 or 47

/

1

l

9)

Are RCS dilution paths isolated when control rods

'

are locked out in Mode 57

/

>

10) With the Reactor Vessel Heac in place and the control

rods in the Locked-Out Condition can the control

rods be inserted in a timely mann.r?

/

11) If the answer to any of the above is "NO",

the

action should be reviewed relative to the

associated risk, outage activities and schedules.

The outage schedule should then be adjusted

'

as necessary or recommendations provided for

management resolution

t

!

- -

__.

.

'

'

.

e

Shutdown Risk Assessment

OPGP03-ZA-0101

Rev. 1

Page 16 of 21

ADDERDUM 8

.

Containment Integrity

(Page 1 of 1)

NOTE

A "NO" answer does not necessarily represent an

unacceptable risk situation, but identifies an

area that requires further evaluation or other

compensatory measures may be warranted.

YES / NO

1)

Are the openings and closings of the RCB

scheduled appropriately relative to fuel

movements and mid-loop conditions?

/

2)

Do the openings and closings of the RCB conform

with Technical Specification?

/

-

3)

Do Rad monitor maintenance activities support

containment integrity requirements?

/

4)

Can RCB integrity be rapidly restored during

mode 5 conditions?

/

5)

Is there an alternate / temporary source of

electrical power available to power the

equipment match hoists to close the hatch?

(i.e. In the event of a loss of power incident)

/

6)

If the answer to any of the above is "NO",the

action should be reviewed relative to the associated

risk, outage activities and schedules. The outage

schedule should then be adjusted as necessary or

recommendations provided for management resolution.

_

__ _ _ . _ _ _ _ _

- ---

I

.

-*

.

j

-i

.

-1

Shutdown Risk Assessment

OPGP03-ZA-0101

I

Rev. 1

3

Page 17 of 21

ADDENDUM 9

Personnel Safety

(Page 1 of 1)

>

.

'

NOTE

A "YES" answer does not necessarily represent an

unacceptable risk situation, but identifies an

area that requires further evaluation or other

compensatory measures may be warranted.

i

YES / NO

1)

Are there areas in the schedule that have an

increased potential for caustic releases?

/

2)

Are there areas in the schedule that may require

special protective equipment?

/

l

3)

Are there areas in the schedule that will

require a confined space entry?

/

4)

Are there areas in the schedule that may

require special work preparations?

/

,

5)

Are there areas in the schedule where plant

personnel could be exposed to pressurized

system?

/

'

6)

Are there areas in the schedule where plant

personnel could be exposed to high levels

of radiation?

/

7)

Are there areas in the schedule where work

'

activities will require plant personnel to

be in areas where heavy load movements are

taking place?

/

8)

If the answer to any of the above is "TES",

the action should be reviewed relative to the

associated risk, outage activities and schedules.

The' outage schedule should then be adjusted as

necessary or recommendations provided for

management resolution.

L

  1. -

1-

-

.

.

. .

.

.

.

1

..

's -

-

-

.

.

1

.

Shutdown Risk Assessment

OPGP03-ZA-0101

1

_.

Rev. 1

Page 21 of 21

ADDENDUM 13

(Page 1 of 1)

DAILY PLANT STATUS FORM (TTPICAL)

SHUTDOWN SYSTEM AVAILABILITY

MODES 5 AND 6

DATE:

/

/

TIME

Diesel Generators

B or C

RHR System

0

ESF Elec System

2

ECV System

1

CCW System

1

SFPCCS*

1

-

Standby Xfar 2

Main and Aux Xfmr

2 out of 3

Standby Xfar 1

Emergency Xfmr

FHB HVAC

2

FHB Rad Monitors .

1

EAB HVAC

1

SFPCCS must be backed by its associated SDG.

(SFPCC Pump

"A" with SDG

"B",

SFPCC Pump "B" with SDG "C".)

.

I

a

!

,

,

.

A

Shutdown Risk Assessment

OPGP03-ZA-0101

Rev. 1

Page 20 of 21

ADDENDUM 12

(Page 1 of 1)

DAILY ?LANT STATUS FORM (TTPICAL)

'

SHUTDOVN SYSTEM AVAILABILITY

MODES 5 AND 6

DATE:

/

/

TIME

,

_

System

No. Required

No. Available

Diesel Generators

2

RHR Systems

2

EST Elec Buses

2

ECW System

2

CCV System

2

SFPCCS

1

LHSr

0

CCP

1

Standby Xfer 2

Main and Aux Xfmr

2 out of 3

,

Standby Xfar 1

.

Emergency Xfmr

EAB HVAC

2

FHB HVAC

2

Rad Monitoring:

1

.

EAB

FHB

1

RCB

1

,

a