Forwards Safety Insp Repts 50-373/93-12 & 50-374/93-12 on 930330-0402.No Violations Noted.Poor Communication Flow from Emergency Response Facilities to Control Room Simulator Noted During 1992 & 1993 Exercises
ML20035F993
Person / Time
Site: LaSalle  
Issue date: 04/19/1993
From: Pederson C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Delgeorge L
COMMONWEALTH EDISON CO.
Shared Package
ML20035F994 List:
References
NUDOCS 9304260002
Download: ML20035F993 (2)


See also: IR 05000373/1993012

Text

'

Oco

-,

. - .

,

.

APR 1S1933

-

Docket No. 50-373

Docket No. 50-374

l

Commonwealth Edison Company

l

ATTN: Mr. L. O. DelGeorge

l

Vice President

i

Nuclear Oversight and

i

Regulatory Services

Executive Towers West III

'

1400 Opus Place

Downers Grove, IL 60515

^

!

Dear Mr. DelGeorge:

h

SUBJECT:

1993 LASALLE EMERGENCY PREPAREDNESS EXERCISE INSPECTION

!

This refers to the routine safety inspection conducted by Ms. H. Simans of

this office and others on March 30 - April 2, 1993. The inspection included a

review of authorized activities at your LaSalle facility. At the conclusion

of the inspection, the findings were discussed with those members of your

i

staff identified in the enclosed report.

!

Areas examined during the inspection are identified in the report. Within

these areas, the inspection consisted of a selective examination of procedures

!

'

and representative records, interviews with personnel, and observation of

activities in progress.

,

+

No violations of NRC requirements were identified during the course of this

l

inspection.

During both your 1992 and 1993 exercises, our inspection staff identified poor

communication flow from your emergency response facilities to the control room

!

simulator. Although this issue does not rise to an exercise weakness, the NRC

i

-

views good communications between your emergency response facilities as

important and is concerned about the repeat nature of this issue.

Please

'

provide in writing within 30 days of the date of this letter the actions you

have taken or plan to take to resolve this issue.

Subsequent to the onsite inspection, an April 7,1993 telephone conversation

t

between J. Lockwood of your staff and H. Simons of my staff was held to

address the Inspection Followup Item identified in Section 2 of the enclosed

- .

'

Inspection report.

Based on this telephone conversation, it is our

understanding that repairs and satisfactory retesting of the Technical Support-

i

Center's emergency ventilation system will be accomplished by June 30, 1993.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of

this letter, the enclosure, and your response to this letter will be placed in-

,

the NRC Public Document Room.

1

(3$

I

9304260002 930419

,

PDR

ADOCK 05000373

,

G

PDR

<

.

-44--_.

-

'

!

!

_

.

.,-

Commonwealth Edison Company

2 APR 191993

,

We will gladly discuss any questions you have concerning this inspection.

'

Sincerely,

"Originsi s' d by CynNs D. Pederson"

p

Cynthia D. Pederson, Chief

Reactor Support Programs Branch

,

Enclosure:

Inspection Reports

No. 50-373/93012(DRSS);

No. 50-374/93012(DRSS)

.

cc w/ enclosure:

W. Murphy, Site Vice President

G. Spedl, Station Manager

J. Lockwood, Regulatory Assurance

Supervisor

'

,

D. Farrar, Nuclear Regulatory

Services Manager

'

OC/LFDCB

Resident Inspectors LaSalle

+

Dresden, Quad Cities

-

Richard Hubbard

J. W. McCaffrey, Chief, Public

Utilities Division

l

Licensing Project Manager, NRR

'

Robert Newmann, Office of Public

Counsel

,

State Liaison Officer

Chairman, Illinois Commerce

'

Commission

'

I. Johnson, CECO, Corporate EP Director

A. Williams, FEMA, Region V

bcc:

PUBLIC

~[

!

4

yes

!

R

RT I

RIII

RII,

RIII

RI I

h] son

okick-Barger

Simons/sd

L

1 ski

pHb ue

M

04/s3 /93

g

Qpff

gg

!

L-

-

-

- --

A