Monthly Operating Rept for Mar 1993 for Songs,Unit 1.W/
ML20035E862
Person / Time
Site: San Onofre 
Issue date: 03/31/1993
From: Darling J, Marsh W
SOUTHERN CALIFORNIA EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9304190348
Download: ML20035E862 (7)


Text

_

l n+t**?!Y?

Southem Califomia Edison Company 23 PARKER STREET 1RVINE. CALIFORNIA 92718 WALTER c. uARss April 14, 1993 mo mo j

.ss....~.aEn.

g,..

...n NUOL.E AR REGULATORY AFF.dR$

?

I i

U. S. Nuclear Regulatory Commission Document Control Desk

-i Washington, D.C.

20555

Subject:

Docket No. 50-206 Monthly Operating Report for March 1993 l

San Onofre Nuclear Generating Station, Unit 1 Technical Specification 6.9.1.10 to. Possession Only License DPR-13 for the San -

Onofre Nuclear Generating Station. Unit 1, requires SCE.to provide a Monthly Operating Report which includes routine operating statistics, shutdown experience, and all challenges to pressurizer safety and relief valves.

j This letter transmits the March 1993 Monthly Operating Report for Unit 1.

There were no challenges to pressurizer safety or relief valves during this j

reporting period.

If you require any additional information, please let me know.

l t

l l

l l

Sincerely, Mb l

I l

Enclosure cc:

J. B. Martin, Regional Administrator, NRC Region V S. W. Brown, NRC Project Manager, San Onofre Unit 1 C. W. Caldwell, NRC Senior Resident-Inspector, Units 1, 2 & 3 R. F. Dudley,fSection Chief, Non-Power,. Decommissioning, and l

Environmental Project, Directorate of Reactor Projects-3, 4 & 5-i i

i 6

9304190348 930331 PDR ADOCK 05000206

///

R PDR

l l

l j

Document Control Desk NRC MONTHLY OPERATING REPORT DOCKET NO:

50-206 UNIT NAME:

SINES - 1 DATE:

A 'N 1 4 1993 COMPLETED BY:

J. L. Darlina TELEPHONE:

(714) 368-6223 OPERATING STATUS 1.

Unit Name: San Onofre Nuclear Generatino Station. Unit 1 2.

Reporting Period:

March 1993 3.

Licensed Thermal Power (MWt):

None Authorized 4.

Nameplate Rating (Gross MWe):

456 5.

Design Electrical Rating (Net MWe):

436 6.

Maximum Dependable Capacity (Gross MWe):

Not Applicable 7.

Maximum Dependable Capacity (Net MWe):

Not Applicable 8.

If Changes Occur In Capacity Ratings (Items Number 3 Through 7)

Since Last Report, Give Reasons: A Possession Only License was issued on October 23. 1992 and became effective on March 9. 1993.

9.

Power Level To Which Restricted, If Any (Net MWe):

See Item 10 10.

Reasons For Restrictions, If Any:

A Possession Only License was issued on October 23. 1992 and became effective on March 9. 1993.

This Month Yr.-to-Date Cumulative l

l 11.

Hours In Reporting Period 744.00 2160.00 221.325.00 12.

Number Of Hours Reactor Was Critical 0.00 0.00 129.980.09 13.

Reactor Reserve Shutdown Hours 0.00 0.00 0.00 14.

Hours Generator On-Line 0.00 0.00 126.040.52 15.

Unit Reserve Shutdown Hours 0.00 0.00 0.00 16.

Gross Thermal Energy Generated (MWH) 0.00 0.00 158.041.722.52 17.

Gross Electrical Energy Generated (MWH) 0.00 0.00 52.949.635.00 18.

Net Electrical Energy Generated (MWH)

(582.00)

(4699.00) 49.938.088.00 19.

Unit Service Factor

  • NA 20.

Unit Availability Factor

  • NA NA 57.14%

NA 57.14%

21.

Unit Capacity Factor (Using MDC Net)

  • NA NA 51.94%

22.

Unit Capacity Factor (Using DER Net)

  • NA NA 51.94%

23.

Unit Forced Outage Rate

  • NA NA 17.90%
  • Final Lifetime Factors.

24.

Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):

On November 30.1992 SONGS 1 was permanently shutdown.

25.

If Shutdown At End Of Report Period, Estimated Date of Startup:

NA 26.

Units In Test Status (Prior To Commercial Operation):

Forecast Achieved INITIAL CRITICALITY NA NA INITIAL ELECTRICITY NA NA COMMERCIAL OPERATION NA NA mor. mar /2

l t

j Document Control Desk l

(

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO:

50-206 UNIT NAME:

SONGS - 1 DATE: APR 1 4 1993 i

COMPLETED BY:

J. L. Darlina TELEPHONE:

(714) 368-6223 MONTH: March 1993 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net)

(MWe-Net) 1 0.00 16 0.00 2

0.00 17 0.00 l

l 3

0.00 18 0.00 4

0.00 19 0.00 5

0.00 20 0.00 6

0.00 21 0.00 7

0.00 22 0.00 8

0.00 23 0.00 9

0.00 24 0.00 10 0.00 25 0.00 11 0.00 26 0.00 12 0.00 27 0.00 13 0.00 28 0.00 14 0.00 29 0.00 15 0.00 30 0.00 31 0.00 j

mor. mar /3

Document Control Desk UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO:

50-206 UNIT NAME: JS 3GS - 1 REPORT MONTH: March 1993 DATE:

A"H I 4 1993 COMPLETED BY:

J. L. Darlina TELEPHONE:

(714) 368-6223 Method of Shutting Cause & Corrective Duration Down LER System Component Action to No.

Date Type' (Hours)

Reason Reactor' No.

Code' Code' Prevent Recurrence 2

157 921128 S

744 H

1 NA NA NA See note below Note:

Unit was shut down following completion of cycle 11.

The shutdown commenced at 1900 on 11/28/92 and was completed at 0501 on 11/30/92.

The Unit will not resume operation.

'F-Forced

' Reason:

' Method:

'IEEE Std 805-1984 S-Scheduled' A-Equipment Failure (Explain) 1-Manual B-Maintenance or Test 2-Manual Scram.

C-Refueling 3-Automatic Scram.

'IEEE Std 803A-1983 D-Regulatory Restriction 4-Continuation from E-Operator Training & License Examination Previous Month F-Administrative 5-Reduction in the Average G-Operational Error (Explain)

Daily Power Level of more H-Other (Explain) than 20% from the previous day 6-Other (Explain) mor. mar /4

i I

Document Control Desk

SUMMARY

OF OPERATING EXPERIENCE FOR THE MONTH DOCKET NO:

50-206 UNIT NAME: SONGS - 1 DATE:

APR 141993 COMPLETED BY:

J. L. Darlina TELEPHONE:

(714) 368-6223 Date Time Event 03/01/93 0001 Unit began the month in Mode 6, Upper internals removed.

03/02/93 0848 Commenced fuel offload.

03/06/93 1335 Last fuel assembly placed in spent fuel pool, core offload complete.

03/16/93 0033 Reactor vessel head installed.

03/31/93 2400 Unit is defueled, systems being aligned for SAFSTOR.

l l

i l

mor. mar /5

Document Control Desk REFUELING INFORMATION DOCKET N0:

50-206 UNIT NAME:

SONGS - 1 DATE:

APR 1 4 1991

~

COMPLETED BY:

J. L. Darlina TELEPHONE:

(714) 368-6223 1

l MONTH:

March 1993

1. Scheduled date for next refueling shutdown.

Unit permanently shutdown on November 30, 1992

2. Scheduled date for restart following refueling.

None.

3. Will refueling or resumption of operation thereafter require a Technical Specification change or other license amendment?

Operation will not be resumed.

A Possession Only License was issued on October 23, 1992, which became effective on March 9, 1993 when the NRC was notified that all fuel had been offloaded from the core.

4. Scheduled date for submitting proposed licensing action and supporting i

information.

Permanently Defueled Technical Specifications (PDTS) are in the process of being developed.

Submittal of the proposed PDTS is forecast to occur in late April or early May 1993.

I I

mor. mar /6

)

i

l 1

Document Control Desk REFUELING INFORMATION DOCKET NO:

50-206 UNIT NAME:

SONGS - 1 DATE: APR i 41993 COMPLETED BY:

J. L. Darlina TELEPHONE:

(714) 363-6223 MONTH:

March 1o93

5. Important licensing considerations associated with refueling, e.g. new or different fuel design or supplier, unreviewed design or performance analysis methods, significant changes in fuel design, new operating procedures.

Not applicable.

6. The number of fuel assemblies, a)

In the core.

O b)

In the spent fuel storage pool.

207

7. Licensed spent fuel storage capacity.

216 Intended change in spent fuel storage capacity.

None

8. Projected date of last refueling that can be discharged to spent fuel storage pool assuming present capacity.

During March the final Unit 1 core, of 157 fuel assemblies, was discharged into the spent fuel pool.

mor. mar /7

'