Advises That Review of Licensee 900518 Request for Exemption to 10CFR50,app R Will Be Suspended Until Addl Info Submitted
ML20035B021
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 03/23/1993
From: Hopkins J
Office of Nuclear Reactor Regulation
To: Shelton D, Shelton S
CENTERIOR ENERGY, TOLEDO EDISON CO.
References
TAC-M60995, NUDOCS 9303310007
Download: ML20035B021 (3)


Text

-

May 23, 1993 Docket No. 50-346 DISTRIBUTION Docket File OGC Mr. Donald C. Shelton, Vice President NRC & Local PDRs ACRS(10)

Nuclear - Davis-Besse JRoe Region III, DRP Centerior Service Company JZwolinski c/o Toledo Edison Company JHannon 300 Madison Avenue PKreutzer Toledo, Ohio 43652 JHopkins

Dear Mr. Shelton:

SUBJECT:

10 CFR PART 50 APPENDIX R EXEMPTION REQUEST FOR THE DAVIS-BESSE CONTAINMENT ANNULUS (TAC NO. M60995)

By letter dated May 18, 1990, you. applied for an exemption to 10 CFR Part 50 Appendix R for the containment annulus region of the Davis-Besse Nuclear Power Station, Unit No. 1.

Part of the basis for your request is that radiant energy shields consisting of Thermo-Lag 330-1 fire barrier material separate redundant trains of safe shutdown circuits within the containment annulus. Since the submittal of your exemption request, Thermo-Lag 330-1 has become the subject of NRC Information Notices, a Bulletin and supplement, and a Generic Letter regarding its fire endurance capabilities.

By letter dated February 24, 1993, you informed the NRC that, based on the ongoing industry and NRC efforts regarding Thermo-Lag 330-1, you plan to submit additional information in support of the exemption request.

Your schedule for submitting this information is by November 1, 1993.

The NRC staff finds this schedule acceptable; however, due to the amount of time until the material is submitted, the NRC staff is suspending its review of your exemption request and closing TAC No. M60995. We will recommence our review under a new TAC Number when the additional information is submitted.

Contact me if you have any questions.

Sincerely,

/s/

Jon B. Hopkins, Sr. Project Manager Project Direc^ orate III-3 Division of._ actor Projects - III/IV/V Office of Nuclear Reactor Regulation cc:

See next page 0FFICE PDIII-3:LA:DRPW PDIII-3:PM:DRPWTJ/

PDIII-3:PD:DRPW NAME PKreutzerA)

JBHopkins/jbh/bj JHannon Nh-DATE 3 /N2/93 3 /;)J /93 3 /93/93 0FFICIAL RECORD DOCUMENT NAME:

G:\\DAVISBES\\ DAB 60995.LTR pu r m g~,m ec h 250011 E, nu h\\

9303310007 930323 ADOCK0500g6 DR

8' Mr. Donald C'. Shelton Davis-Besse Nuclear Power Station Toledo Edison Company Unit No. I cc:

Mary E. O'Reilly Centerior Energy Corporation Radiological Health Program 300 Madison Avenue Ohio Department of Health Toledo, Ohio '43552 Post Office Box 118 Columbus, Ohio 43266-0149 Mr. Robert W. Schrauder Attorney. General Manager. Nuclear Licensing Department of Attorney

. Toledo Edison Company General 300 Madison Avenue 30 East Broad Street Toledo, Ohio 43652 Columbus, Ohio 43215 Mr. James W. Harris, Director Gerald Charnoff, Esq.

Division of Power Generation Shaw, Pittman, Potts Ohio Department of Industrial Regulations and Trowbridge P

O. Box 825-

'2300'N Street, N.W.

Columbus, Ohio 43216 Washington, D.C.

20037 Regional Administrator, Region Ill Ohio Environmental Protection Agency U.S. Nuclear Regulatory Commission DERR--Compliance Unit 799 Roosevelt Road ATTN: Zack A. Clayton Glen Ellyn, Illinois 60137 P. O. Box 1049 Columbus, Ohio ~ 43266-0149 Mr. Robert B. Borsum Babcock & Wilcox President, Board of Ottawa Nuclear Power Generation Division County Commissioners

-1700 Rockville Pike, Suite 525 Port Clinton, Ohio 43452 Rockville, MD 20852 Resident Inspector State of Ohio U. S. Nuclear Regulatory Commission Public Utilities Commission 5503 N. State Route 2 180 East Broad Street-0ak Harbor, Ohio 43449 Columbus, Ohio 43266-0573 Mr. Murray R. Edelman Mr. James R. Williams Executive Vice President --

State Liaison to the NRC Power Generation-Adjutant General's Department Centerior Service Company Office of Emergency Management Agency 6200 Oak Tree Boulevard 2825 West Granville Road Independence, Ohio 44101 Columbus, Ohio 43235-2712

~

((func vg fo, UNITED STATES 3,, c g

NUCLEAR REGULATORY COMMISSION wasmNGTON, D C. 20555 j

%...../

nay 23, 1993 Docket No. 50-346 Mr. Donald C. Shelton, Vice President Nuclear - Davis-Besse Centerior Service Company c/o Toledo Edison Company 300 Madison Avenue Toledo, Ohio 43652

Dear Mr. Shelton:

SUBJECT:

10 CFR PART 50 APPENDIX R EXEMPTION REQUEST FOR THE DAVIS-BESSE CONTAINMENT ANNULUS (TAC N0. M60995)

By letter dated May 18, 1990, you applied for an exemption to 10 CFR Part 50 Appendix R for the containment annulus region of the Davis-Besse Nuclear Power i

Station, Unit No. 1.

i Part of the basis for your request is that radiant energy shields consisting of Thermo-Lag 330-1 fire barrier material separate redundant trains of safe i

shutdown circuits within the containment annulus.

Since the submittal of your exemption request, Thermo-Lag 330-I has become the subject of NRC Information Notices, a Bulletin and supplement, and a Generic Letter regarding its fire endurance capabilities.

By letter dated February 24, 1993, you informed the NRC that, based on the ongoing industry and NRC efforts regarding Thermo-Lag 330-1, you plan to submit additional information in support of the exemption request.

Your schedule for submitting this information is by November 1, 1993.

The NRC staff finds this schedule acceptable; however, due to the amount of time until the material is submitted, the NRC staff is suspending its review of your l

exemption request and closing TAC No. M60995. We will recommence our review under a new TAC Number when the additional information is submitted. Contact me if you have any questions.

Sincerely, f

A

[ Jon B. Hopkins, Sr. Project Manager l

Project Directorate III-3 Division of Reactor Projects - III/IV/V Office of Nuclear Reactor Regulation CC See next page k

h