_
=
s b~.
Portland General Electric Company
~
CE James E. Cross Vice President and Chief Nuclear Officer Afarch 15,1993 Trojan Nuclear Plant Docket 50-344 License NPF-1 U. S. Nuclear Regulatog Commission Attn: Document Control Desk Washington, DC 20555
Dear Sirs:
Exclusion From Certain Title 10 to the Code of Federal Reculations (10 CFR) Regulations On January 27,1993, Portland General Electric Company (PGE) submitted a License Change Application requesting that the Trojan Nuclear Plant (TNP) Operating License be amended to a Possession Only License (POL). The POL, when approved by the Nuclear Regulatory Commission (NRC), will allow PGE to possess special nuclear, source, and byproduct material but not operate the nuclear reactor.
PGE notified the NRC via letter dated Febmag 2,1993, that the reactor fuel has been permanently off-loaded from the reactor vessel and placed in the spent fuel pool. By letter dated February 17,1993, PGE cenified to the NRC that fuel would not be moved back into the Trojan Containment Building without prior NRC approval.
On the basis of a resiew of 10 CFR regulatory requirements, PGE has concluded that the 10 CFR sections listed in Attachment I will no longer be applicable to TNP upon NRC approval of the POL. The requirements of these regulations are premised on power operation of the nuclear reactor. After receipt of the POL, power operation will be prohibited and therefore the i
regulations stipulated in Attachment I will no longer be applicable.
i Sincerely, T. D. Walt for J. E. Cross j
190046 Attachment k(iki 9303220020 930315 PDR ADOCK 05000344 1
P PDR H \\
.I
_j 121 SW Salmon Street, Portland. OR 97204
.503/464-8897
t i
Document Control Desk March 15,1993 I
Page 2 I
c:
Mr. John B. Martin Regional Administrator, Region V U. S. Nuclear Regulatory Commission Mr. David Stewart-Smith State of Oregon Department ofEnergy i
Mr. Kenneth Johnston NRC Resident Inspector l
Trojan Nuclear Plant l
i 1
1 i
I m- -
- ---m-+
t Trojan Nuclear Plant Document Control Desk D,ocket 50-344 March 15,1993 i
License NPF-1 Attachment I Page1of3 j
10 CFR Regulati;ns No Longer Applicable At POL l
Regulation l
Basis for Non-Applicability l
10 CFR 26, Fitness for Duty 10 CFR 26 is applicable to licensees authorized to Programs operate a nuclear power reactor. Upon approval of the Possession Only License (POL), Portland l
General Electric Company (PGE) will not be authorized to operate the Trojan Nuclear Plant 2
(TNP) as a nuclear power reactor. Although this regulation is not applicable to TNP with a POL, j
PGE has committed sia letter dated January 27, l
1993 to maintain the current Fitness for Duty Program at TNP after receipt of the POL.
10 CFR 50.44, Standards for This regulation is applicable to fueled nuclear
}
Combustible Gas Control System power reactors. The TNP reactor has been in Light-Water-Cooled Power defueled permanently. Thus, this regulation is not Reactors applicable to TNP following receipt ofPOL.
10 CFR 50.46, Acceptance Criteria This regulation is applicable to fueled nuclear for Emergency Core Cooling power reactors. The TNP reactor has been Systems for Light Water Nuclear defueled permanently. Thus, this regulation is not Power Reactors applicable to TNP following receipt of POL.
10 CFR 50.48, Fire Protection This regulation applies to operating nuclear power plants. TNP has been defueled and will not be l
authorized under the POL to opera:e as a nuclear
)
power plant again. Thus, this regulation is not applicable to TNP following receipt of POL.
10 CFR Appendix R, Fire This regulation applies to operating nuclear power Protection Program for Nuclear plants. TNP has been defueled and will not be Power Facilities Operating Prior to authorized under the POL to operate as a nuclear l
January 1,1979 power plant again. Thus, this regulation is not applicable to TNP following receipt of POL.
10 CFR 50.49, Emironmental This regulation applies to operating nuclear power Qualification of Electrical plants. TNP has been defueled and will not be Equipment Important to Safety authorized under the POL to operate as a nuclear for Nuclear Power Plants power plant again. Thus, this regulation is not applicable to TNP following receipt of POL.
Trojan Nuclear Plant Document Control Desk D,ocket 50-344 March 15,1993 License NPF-1 Attachment I Page 2 of 3 10 CFR Regulations No Longer Applicable At POL (Continue <l)
Regulation Basis for Non-Applicability 10 CFR 50.55a, In-Senice 10 CFR 50.55a Paragraphs (f) and (g) specify
[
Inspection Requirements requirements for in-senice testing of pumps and valves and in-senice inspection of components (including supports), respectively.10 CFR 50.55a l
Paragraphs (f)(4) and (g)(4) indicate that Paragraphs (f) and (g) of the rule are applicable thrrughout the senice life of the plant. Since TNP is no longer in senice, the regulation is not applicable.
10 CFR 50.60, Acceptance Criteria 10 CFR 50.60 requires licensees to meet the for Fracture Prevention Measures requirements of10 CFR Appendices G and H.
for Light Water Nuclear Power Appendices G and 11 are not applicable to TNP Reactors for Normal Operation following receipt ofPOL.
10 Cf R 50.61, Fracture Toughness This regulation applies to operating nuclear power Requirements for Protection plants. TNP has been defueled and will not be Against Pressurized Thermal authorized under the POL to operate as a nuclear Shock Events power plant again. Thus, this regulation is not l
applicable to TNP following receipt ofPOL.
10 CFR 50, Appendix G, Fracture 10 CFR Appendix G specifies fracture toughness Toughness Requirements requirements of the reactor coolant pressare boundary to provide adequate margin of safety during any condition of normal operation over its senice lifetime. The TNP Reactor Coolant i
System is no longer operating and has completed its senice life. Thus, this regulation is no longer applicable to TNP following receipt of POL.
10 CFR 50, Appendix II, Reactor 10 CFR Appendix H provides the requirements of i
Yessel Material Surveillance a reactor vessel material surveillance program.
Program Requirements The data obtained from this program are utilized as required by Sections IV and V of Appendix G.
)
Appendix G is no longer applicable to TNP and thus Appendix 11 is also no longer applicable.
i a
i o
I s
l Trojan Nuclear Plant Document Control Desk Docket 50-344 March 15,1993 License NPF-1 Attachment I Page 3 of 3 10 CFR Regulations No Longer Applicable At POL (Continued)
Reculation Basis for Non-Applicability 10 CFR 50.62, Requirements for The ATWS mitigation system for a pressurized Reduction ofRisk From water reactor is intended to actuate auxiliary Anticipated Transients Without feedwater and initiate a turbine trip under Scram (ATWS) Events for conditions indicative of an ATWS. The issuance Light-Water-Cooled Nuclear of the POL will preclude power operation at Power Plants Trojan, and thus this regulation is not applicable following receipt of the POL.
10 CFR 50.63, Loss of All This regulation applies to operating nuclear power Alternating Current Power plants, ensuring that the reactor core is cooled and containment integrity it maintained in the event of a station blackout. The reactor core at TNP has been ofIloaded to the spent fuel pool and PGE will not be authorized under the POL to operate Trojan as a nuclear power plant again. Thus, this regulation is not applicable to TNP followmg receipt ofPOL.
10 CFR 50.71(e), Maintenance of This regulation applies to operating nuclear power 4
Records, Making of Reports plants. TNP has been defueled and will not be authorized under the POL to operate as a nuclear power plant again. Thus, this regulation is not applicable to TNP following receipt of POL.