ML20034F183

From kanterella
Jump to navigation Jump to search
Insp Rept 50-395/93-04 on 930125-29.Violation Noted.Major Areas Inspected:Adequacy of Licensee Actions Taken Re Concerns Noted During GL 89-10 Phase 1 MOV Insp on 920127- 31
ML20034F183
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 02/22/1993
From: Branch M, Hunt M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20034F172 List:
References
50-395-93-04, 50-395-93-4, GL-89-10, NUDOCS 9303020367
Download: ML20034F183 (12)


See also: IR 05000395/1993004

Text

.

..

-

'

e

.

4 *%jo

UNITED STATES

,

NUCLEAR REGULATORY COMMISSION

+

.

g,

[

c,

REGION 11

f

-$'

$

101 MARIETTA STREET, N.W.

t

'*

1"

ATLANTA, GEORCI A 30323

'

R, + * * o ,/

i

FEB 2 3 1993 -

'

Report No.:

50-395/93-04

Licensee:

South Carolina Electric & Gas Company

Columbia, SC 29218

Docket No.:

50-302

License No.: NPF-12

Facility Name:

V.C. Summer

Inspection Conducted: January 25-29, 1993

'

Inspector:

/ ITICl4wJ/

Rd73

'

M. D. Hunt '

"

"

D6te Sitned

Accompanying Inspector:

M. N. Miller

Approved by:

-

M11/95

>

M. W. Branch', Chief

Date Signed

Test Programs Section

Engineering Branch

Division of Reactor Safety

SUMMARY

Scope:

This announced inspection was conducted to assess the adequacy of the

licensee's actions taken regarding the concerns identified during the GL 89-10

Phase I Motor Operated Valve Inspection (MOV) conducted January 27-31, 1992,

(NRC Inspection Report No. 50-395/92-02).

'

Results:

In the areas inspected, three examples of inadequate acceptance criteria were

identified in the test procedures used for MOV operability testing, this

'

finding is identified as violation 50-395/93-04-01, Inadequate Acceptance

Criteria in MOV Procedure. (See paragraph 3.c.)

'

In the area of training, the engineering staff had not received MOVATS

training for signature analysis of motor operated valve test data.

In the

area of staffing, there was only one engineer assigned:as MOV Coordinator, and '

'l

~

one electrician assigned to the MOV program. The current staffing level may

explain the delays noted in resolving those open program issues identified in.'

the NRC Inspection Report No. 50-395/92-02. Overall, the licensee's MOV

Program needs additional enhancements to meet the intent of the

!

9303020367 930223

j

PDR

ADOCK 050003951

10

PDR

.

. _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _

_ _ _ _ _ _ _ - _ _ _ _ _ _

. _ _

._

_ _ _ _

1

,

.

k'

.2

1

recommendations in GL 89-10. An Inspector Follow-Up Item was identified to

I

address the concerns that still need to be addressed in the licensee's

program.

The Inspector Follow-up Item, 50-395/93-04-02, is identified as GL 89-10

Program Open Items.

1

'

1

__

__

_ _ _ _ _ _ _

__ - _ ____

_ __ __ __ _ _ _ - - _ - _ _ _ _ _ = __

_ _ -

,

_ _

.

o

.

.

t

REPORT DETAILS

]

1.

Persons Contacted

}

Licensee Employees

i

  • J. Berley, Specialist, Nuclear Licensing
  • C. Bowman, Manager, Maintenance

r

  • M. Browne, Manager, Design Engineering

,

  • R. Fowlkes, Manager, Nuclear _ Licensing .

,

  • M. Hazel, Motor Operated Valve Coordinator, Design Engineering

!

  • G. Meyer, Senior Mechanical Engineer, Design Engineering
  • B. Norcutt, Electrician, Maintenance Department

.

  • J. Pease,. Specialist, Nuclear Licensing
  • C. Price, Coordinator, Engineering Services
  • M. Quinton, General Manager, Engineering Services
  • J. Skolds, Vice President, Nuclear. Operations
  • N. Smith,-Test Coordinator, Technical Services

,

  • B. Williams, Manager, Operations

i

NRC Personnel

,

R. Haag, Senior Resident Inspector

-

  • T. Farnholtz, Resident Inspector
  • Attended exit interview

'

)

2.

GENERIC LETTER (GL) 89-10 " SAFETY-RELATED MOTOR-0PERATED VALVE (MOV)

TESTING AND SURVEILLANCE" (2515/109)

The Nuclear Regulatory Commission (NRC). Region 11 conducted a Part I M0V

inspection during January 27-31, 1992, of the V.C. Summer Nuclear Plant

i

(NRC Inspection Report No. 50-395/92-02). The inspection examined the

,

licensee's actions taken in response to Generic Letter'89-10,

Safety-Related Motor-0perated Valve Testing and Surveillance, and

identified thirteen concerns. Additional information was requested for

two concerns and the eleven other concerns required no written response.

The licensee responded to these two concerns by letter dated May 27,

1992.

,

The purpose of this inspection was to review the licensee's actions

taken for each of the concerns identified in the GL 89-10 Part I MOV

3

Inspection Report 92-02 and the responses submitted in their letter.

Each concern is listed and discussed below.

.

?

The first part of each section lists the concern as written and

i

discussed in the GL 89-10 Part-I MOV Inspection Report 92-02. The.

,

second part discusses the findings of this-inspection.

t

!

.

_.

_

,

.

-

-

-

. .

-

-

.

-

.

.

I

a.

Concerns Identified - Written Response Requested (WRR)

Concern 1 (WRR)

This concern was discussed in Section 3.d of the Part 1 MOV

report. The licensee has identified 35 groups of MOVs based on

similarity in design, functional characteristics, and operating

conditions.

This grouping methodology takes credit for equivalent

group of MOVs based on successful differential pressure testing of

the least capable MOV within a group.

Implementation of this

methodology will not result in performing a differential pressure

(DP) test where practicable, as recommended in the generic letter.

The licensee does not have a verifiable basis for the assumptions

'

used for the grouping methodology. The omission of differential

pressure testing on MOVs where practicable is contrary to the

generic letter 89-10 recommendations and the licensee's commitment

to comply with the generic letter.

'

,

The licensee's response to this concern was submitted May 27,

1992.

A summary of the licensee's response follows. The licensee

will increase the scope of MOVs to be differential pressure (DP)

tested.

The information gained from this expanded testing along

with technical feedback from industry programs will be utilized to

verify assumptions in the static setup and testing of valves which

are not tested under DP conditions. A grouping concept based on

design similarities and environmental conditions will then be

i

utilized for these valves. As the predictability of valve

performance improves, through advancements in test equipment,

valve performance history, and industry initiatives, the licensee

will evaluate and adjust the scope of their testing accordingly.

1

The expansion of the DP testing will impact their current

commitment to complete initial testing of MOVs by the Fall of

1994.

The licensee will assess the impact of their commitment and

revise it accordingly following the refueling outage in the Spring

of 1993.

Until additional testing is performed during the upcoming

outage,and the extent of the licensee's testing plans are

finalized, the quantity of MOVs to be tested can not be

determined.

This concern will be closed but is included as part

of Inspector Follow-up Item (IFI) 50-395/93-04-02, Program Open

Items.

Concern 2 (WRR)

This concern was discussed in Section 3.c of the Part I M0V

report. The licensee has bypassed the torque switch on the PORV

block valves and used the close limit switch for de-energizing the

motor during MOV close operation.

This practice is not

recommended by Limitorque. Additionally, industry experience has

-.

_

.

.

.-

.

q

,

+

.

.

'1

.i

3

"

shown that these MOVs have had difficulty closing under highly

loaded conditions. The licensee needs to justify use of the above

practice.

.

The licensee's response to this concern was stated in their

.i

May 27, 1992, letter to the NRC. A summary of the licensee

,

response follows. Westinghouse, as NSSS designer of VCSNS (plant),

'

modified certain valves to the limit close feature in order to

assure closure of the valve under design basis' conditions.

In

some cases the design loads are beyond the known operator range of

calibration such that the torque switch cannot be set with the

confidence that the set point is both adequate and within the

a

stall limit of the motor.

The principal benefit of the' limit

closed method is to minimize structural loads imposed on valve and

>

the operator.

Subsequent to the modification to the limit close

mode of operation, DP testing was performed on' valves similar and

in the same group as the PORV block valves to confirm operation

under design basis conditions.

Limit switch seating of MOVs is

considered to be appropriate to preclude exceeding the valve or

'

actuator ratings at VCSNS. Additionally, leak tightness is

assured. This response was accepted by the NRC.

This item is

closed.

b.

Concerns Identified - No Written Response Requested (NWRR)

Concern 1 (NWRR)

This concern was discussed in Section 3 b.of the Part I MOV

report. Inconsistencies were noted in the licensee's draft design

basis review documents (DBD).

Further engineering review of these

documents will be required to ensure that the licensee's MOV

,

torque switches are set appropriately.

I

The licensee will review any inconsistencies and make appropriate

changes to the DBD prior to issuing it. The inspectors found that

DBD has not been completed and further review is still needed.

In

addition, design engineering is still reviewing the " master" DBD

and MOV calculations performed by their contractor, ABB Impell

Corporation.

The review of licensee's engineering notes indicated

that changes were also needed in the " master" DBD.

This concern

is closed.

However, it will be addressed in IFI 50-395/93-04-02.

(See paragraph 3.d).

Concern 2 (NWRR)

.

This concern was discussed in Section 3.b of the Part I MOV

report. The licensee's generic letter 89-10 program does not make

provisions for evaluating the effects of high ambient temperature

on motor developed torque. The licensee informed the inspectors

that they are waiting for Limitorque to issue a report concerning

high temperature effects on motors. The licensee' called

Limitorque January 26, 1993, to find out when the report would be

.

.

.

4

issued.

Limitorque informed the licensee that the high

temperature effects on motors would be issued the next. week.

The

licensee is waiting for the Limitorque information befcre

performing any evaluation of data to be included in the MOV

ralculations. This item is closed. However, it will be addressed

in IFI 50-395/93-04-02. (See paragraph 3.d).

Concern 3 (NWRR)

This concern was discussed in Section 3.c of the Part I M0V

report. The licensee's use of a 0.3 valve factor in calculating

thrust requirements for gate valves is non-conservative. The

licer,see needs to validate this value of valve factor v.ia dynamic

tests or develop specific justification for its use. The licensee-

has now expanded their DP testing to include all valves that are

practical to test. All valve factors will be verified during this

DP testing using new stem cells (strain gauges) and torque thrust

cells In cases where DP testing can not be performed,

justification will be provided by using similar or like kind or

types during an engineering evaluation. The inspectors verified

that the DP testing has been expanded and considered this response

appropriate. This concern was closed based on the evaluation that

ast be performed as discussed in the Concern 4 (NWRR).

Concern 4 (NWRR)

This concern was discussed in Section 3.c of the Part I MOV

report. The generic letter program does not make provisions for

evaluating DP test results in order to determine available thrust

margin.

Test results are not reviewed to validate assumptions

i

used in thrust equations.

l

The licensee will add margin to the DBD to account for. uncertainty

I

in stem friction factors when determining the minimum required

thrust limit.

Review of DP test results will be performed in a

manner necessary to account for stem friction and load sensitive

i

MOV behavior.

Engineering Services Procedure E-424, MOV Program

'

Implementation , Revision 0 would be revised to specify the

requirements and criteria for implementing the engineering

evaluations concerning margins. This concern is closed. However,

it will be addressed in IFI 50-395/93-04-02.

(See paragraph 3.d).

j

i

Concern 5 (NWRR)

'

This concern was discussed in Section 3.h of the Part 1 MOV

,

report.

The generic letter program needs to clearly identify the

margin, related to lubricant aging effects, that is applied to

required thrust numbers. Additionally, the licensee needs-to

evaluate MOV test results to identify the " rate of loading"

effects on load sensitive MOVs.

i

o

- - - - . _ _ _ _ - - . - . _ - -- _ _ . _ . - - -

s

'

. .

5

The inspectors conducted walkdowns to examine stem lubrication on

various MOVs. All valves inspected were adequately lubricated.

The licensee has a regular lubrication program for the_MOVs

specified in Engineering Services Procedure ES-418. Margin, and-

" rate of loading" effects should be included in licensee's

revision of Procedure E-424 discussed in Concern 4 (NWRR)

evaluation. This item is closed.

Concern 6 (NWRRl_

This concern was discussed in Section 3.f of the Part I MOV

report.

Limit switch seating MOVs, that have leakage criteria,

requires a switch setting that ensures adequate leak tightness

without exceeding the valve or actuator. ratings.

The licensee's response to Concern 2 (WRR) in the May 27, 1992,

letter to the NRC addressed this concern.

The inspectors verified

that the leak tightness of the MOVs was adequately addressed in

General Test Procedure GTP-302, Inservice Testing Of Valves. The

licensee uses the torque switch during the setting of the limit

switches, to determine that over thrusting is not occurring during

closure of the valve. Once this is determined, the limit switches

are set and the torque switch is removed from the electrical

circuit. The electrical circuit can be restored as needed for any

additional limit switch adjustments.

This item is closed.

Concern 7 (NWRR)

'

This concern was discussed in Section 3.e of the Part I HOV

report.

Inconsistencies were noted in the licensee's draft thrust

calculation documents.

Further review of these documents will be

required to ensure that the licensee's generic letter MOV torque

switches are set appropriately.

.

The torque switch setting should be included as part of the DBD.

See the inspectors finding for Concern 1 (NWRR).

This item is

closed.

However, it will be addressed in IFI 50-395/93-04-02.

(See paragraph 3.d).

Concern 8 (NWRR)

.

This concern was discussed in Section 3.c of the Part I M0V

report. The licensee needs to review OP test results, to the

extent necessary, to ensure operability of an MOV prior to

returning the system to operation.

The inspectors reviewed the

acceptance criteria for the MOV test procedures (See

concerns /connents in paragraph 3.c), and the licensee's program-

for initiating a non-conformaace report (NCR). While the test

procedures acceptance criteria appeared to be inadequate,.there

-

was sufficient evidence that the M0Vs that have been tested to

date, were evaluated for operability where necessary. The test

acceptance was based on the full closure of the valve under ' full

6

r

-

,

er

w

..%

,

e

i

.

6

DP. A NCR was initiated requiring an engineering evaluation to

determine acceptability and operability for the MOVs that did not

successfully close during full DP testing. The inspectors

determined that the existing program for using a NCR was adequate

-

to address this concern. This item is closed.

Concern 9 (NWRR)

,

This concern was discussed in Section 3.e of the Part I MOV

report. The program did not justify the use of static tests to

periodically verify M0V capability in accordance with the generic

letter recommendations.

The licensee plans to DP test all those MOVs that are practical to

test. At the present time, it is not necessary or required

(in GL 89-10) to perform DP retesting unless the MOV is replaced,

modified, or overhauled to the extent that existing DP test

results are not representative of tne MOV in its modified

condition.

The licensee's initial testing was to only have the

spring pack displacement monitored using the " thrust measuring

device" (TMD) to determine thrust. The licensee will now use both

the torque thrust cell (TTC) and the TMD.

In addition the

licensee contracted to have calibrated stem strain gauges

installed during the Spring 1993, refueling outage, to supplement

.

using the TTC. The inspectors determined that the licensee's

planned methods were adequate at this time. This item is closed.

Concern 10 (NWRR))

inis concern was discussed in Section 3.1 of the Part I MOV

report.

Use of thrust measuring device (TMD) to measure thrust

during dynamic tests will affect the licensee's ability to detect

load sensitive MOV behavior.

The licensee now uses a TTC in addition to the TMD. (See response

to concern 9). The inspectors determined that the licensee's

methodology for using additional instrumentation to measure. thrust

and loading is acceptable.

This item is closed.

Concern 11 (NWRR)

7

This concern was discussed in Section 3.1 of the Part I MOV

report.

Calculating maximum expected differential pressure using

,

design values for up stream pressure could result in overly

l

conservative assumptions. Therefore, achievement' of the

identified worst case conditions during DP test may not be

possible.

The licensee currently considers conservatism an asset. -Expected

test values have been determined such'that margin can be defined.

The inspectors reviewed the licensee's program procedures and

determined the procedures need to be enhanced to clearly define

j

.

.

.

.

7

the testing limits criteria and how these test limits would.be

evaluated.

Engineering Services Procedure ES-424 will be revised

to address test limits and specifically address the test limits

when it will be less than the worst case DP condition. (This

specifically means that if the required DP test limiticould not be

set up and a reduced DP test limit was used; the acceptance-

criteria for the engineering evaluation would be specified in

ES-424). Other changes for ES-424 are also discussed in the

inspectors findings for Concern 4.

This item was closed and

incorporated as part of item 4 of IFI 50-395/93-04-02.

3.

INSPECTION FINDINGS

a.

Documentation

The inspectors reviewed the licensee's GL 89-10 MOV program

documentation to determine if it had been completed since the last

MOV inspection (January 27-31,1992) and was adequate to support

the MOV program. The documents reviewed included (1) ABB Impell

Instruction 0980-077 ."I-001, Maximum Design Basis Differential

Pressure Determination, and associated calculations, (2) the

licensee's draft MOV design basis document, (3) design

Modification Package MCM No. 21745 E dated December 9, 1992, and,

(4) various engineering, test, and electrical maintenance

procedures.

The licensee informed the inspectors that the

" master" document for the MOV program was the ABB Impell

!

Instruction and associated calculations contained in six volumes

(six 3-ring binders).

The ABB Impell documents were considered to be the completed

design basis documents (DBD) until the licensee completed their

draft DBD and issued it.

The licensee's draft DBD was supposed to

be a copy of the ABB Impell documents.

However, the licensee's

draft DBD was not signed and no additional work to complete it was

,

identified by the inspectors.

In addition, the inspectors found

the licensee was still in the process of updating the ABB Impell

3

DBD.

For example, the maximum valve thrust listed in the

'

calculations of the ABB Impell DBD for valves XVK1633A-FW,

XVK1633B-FW, and XVK1633C-FW was 9772 pounds.

For the same valves

i

listed in Design Modification Package MCM No. 21745E, the maximum

thrust was 14,647 pounds. .The licensee's design modification

,

package had changed these values.

!

Another area of concern with the ABB Impell DBD was that the data

used for the calculations was crossed out-in red and new values

hand written in.

For example, Calculation No. 0980-077-DB-002,

pages 120 - 126, for valves XVG6516-VU, XVG6517-VU, XVG6518-VU,

and XVG6519-VU-had hand written changes.

Engineering ~ explained

that several changes to the ABB Impell DBD were not finished at

this time, but engineering was aware of what needed to be done to

complete the DBD and work was in progress to complete the DBD.

The inspectors were satisfied that engineering knew what was

,

.

..

.

.

4

8

needed to accomolished to complete the GL 89-10 program.

However, the inspectors could not identify how the licensee

planned to complete the program with'the existing personnel

assigned. Overall, the inspectors determined that the licensee's

documentation for the GL 89-10 MOV program was incomplete at this

stage and'had expected more progress based on the fact that M0V.

testing is to be performed during the upcoming March outage.

b.

Training and Staffing

The inspectors noted that currently there were only two persons

who were active in the MOV program, one engineer ( MOV

Coordinator) and the other was an electrician who directed the

testing. .The inspectors also noted that only the electrician had

,

received M0 VATS training. The inspectors were informed that one

'

other electrician had received this training but that person was

not presently assigned to the MOV program. The electrician,

currently in charge of testing, explained that he had given

training to other electricians.

The MOV Coordinator had not

received M0 VATS Training. During a meeting with the licensee, the.

inspectors were advised by engineering management that.they did

not feel it necessary that the engineers who perform the

diagnostic trace reviews have the training to perform diagnostic

testing.

However the licensee indicated that additional training

would be made available.

The licensee advised the inspectors that when valve testing is

performed during the next outage, there would be sufficient

trained personnel available to accomplish the necessary testing

and evaluations.

During the last outage the licensee had used

M0 VATS technicians and would take the steps to use qualified

j]

contract personnel again during the next outage. The inspectors

remarked to the licensee that the two personnel presently assigned

i

to the MOV program needed additional support to accomplish the

various tasks to meet the licensee's program schedule commitment.

c.

Testing

,

l

The inspectors reviewed the results of the licensee's

justification of 44 valves that were excluded from DP testing.

This group of valves consisted of suction valves for the' RHR and

SI pumps, and reactor building spray discharge valves. Other .

valves contained in the list were the main steam supply valves tc

j

the emergency feedwater pump turbines, accumulator isolation

I

valves, and containment isolation valves for the CRDMs cooling

water supply. The evaluations listed the justifications and the

j

inspector verified the justifications by review of the appropriate

system P&ID drawings. In the judgement of the inspector, the

licensee demonstrated justification for valves that are exempted

'i

since the testing of these valves could present a safety problem

or damage equipment.

1

i

.-

.

.

,-

-.

.

,

.

<

-

..

,

J

-;

'

10

.

A summary of the open concerns for IFI 50-395/93-04-02 are:

(1) Concern 1 (WRR) Additional testing is required to

determine the scope of the MOV testing program.

7

(2) Concern 1 (NWRR) Further engineering review of the'DBD

!

needs to be completed.

'

(3) Concern 2 (NWRR) The effects of high ambient

temperature on the actuator motors needs to be

evaluated.

.

(4) Concern 4 and 5 (NWRR) The engineering services

procedure ES-424 needs to be up-dated and revised to

i

include the requirements and criteria for implementing

-

engineering evaluations concerning margins.

(5) Concern 7 (NWRR) Inconsistencies were noted in the

draft DBD thrust calculations. The DBD needs to be

-

completed.

4.

EXIT INTERVIEW

The insp'ection scope and findings were summarized on' January 29, 1993,

.)

with those persons indicated in paragraph 1.

The inspectors described

the areas' inspected and discussed in detail the inspection results.

Proprietary information is not contained in this report.

Dissenting

comments were not received from the licensee.

1

The inspectors informed the licensee that one violation, with three

examples, concerning inadequate acceptance criteria in the M0V

procedures was . identified as Violation 50-395/93-04-01, Inadequate

Acceptance Criteria in MOV Procedures.

1

The licensee was also informed that the remaining open concerns

discussed in the report would be identified as an Inspector Follow-up

Item 50-395/93-04-02, GL 89-10-Program Open Items.

5.

Acronyms and Initialisms

ABB

ASEA BROWN B0VERY

DBD

DESIGN BASIS DOCUMENT

j

DP

DIFFERENTIAL PRESSURE

EPRI

ELECTRIC POWER RESEARCH INSTITUTE,

)

GL

GENERIC LETTER

1

IFI

INSPECTION FOLLOW-UP ITEM

l

IR

INSPECTION REPORT

MOV

MOTOR-0PERATED \\ALVE

i

M0 VATS

MOTOR-0PERATED VALVE ANALYSIS AND TEST SYSTEM

l

l

. - .

. .

.

.

I

.

-

.

.-

.

.

.

. ..

~.

.

,

4

11

NRC

NUCLEAR REGULATORY COMMISSION

NWR

NO WRITTEN RESPONSE REQUESTED

- NSSS

NUCLEAR STEAM SYSTEM SUPPLE

NWRR'

NO WRITTEN RESPONSE REQUIRED

PORV

POWER OPERATED RELIEF VALVE

l

RII

REGION II

.

TMD

THRUST MEASURING DEVICE

TI

TEMPORARY INSTRUCTION

TTC

TORQUE THRUST CELL

VCSNS

V.C. SUMMER NUCLEAR SITE

WRR

WRITTEN RESPONSE REQUIRED

I

!

-