ML20034C592

From kanterella
Jump to navigation Jump to search
Insp Rept 50-285/90-14 on 900312-16.Violations Noted.Major Areas Inspected:Abnormal & Alarm Response Procedures & Followup of Previously Identified Insp Findings
ML20034C592
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 04/16/1990
From: Galiardo J, Hunter D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20034C590 List:
References
50-285-90-14, NUDOCS 9005040184
Download: ML20034C592 (9)


See also: IR 05000285/1990014

Text

-

l

.=

.

.

APPENDIX-B

U.S. NUCLEAR REGULATORY COMMIS$10N-

P.EGION IV

NRC Inspection Report: 50-285/90-14

Operating License: DPR-40

- l

Docket: 50-285

Licensee: OmahaPublicPowerDistrict(OPPD)

L

444 South 16th Street Hall

3

Omaha, Nebraska- 68102-2247

Facility Name: FortCalhounStation(FCS)

Inspection =At:

FCS, Blair, NE

Inspection Conducted

March 12-16, 1990

"

Inspector:

/

l

. R.

'nter, Senior Reactor Inspector,

DaJe i

.,

era

nal Program Section

.

  1. k

g

oz

,-

Approved:

'l

i

J.\\E. Gyliardo, Chief, Operational Program

Datei

Section, Division of Reactor Safety

j

Inspection Summary

i

Inspection Conducted March 12-16, 1990 (Report 50-285/90-14)

Areas Inspected: Routine, unannounced inspection of abnormal and alarm

response procedures and the followup of previously identified inspection

findings.

Results: Within the two areas inspected, one violation was identified

(inadequate abnormal operating procedures, paragraphs 2.2 and 2.3).

!

The overall upgrade of the abnormal operating procedures was completed by the

[

licensee in December 1989; however, deficiencies were identified during.this

-

inspection regarding the scope / coverage of two of the three abnormal procedures

selected for review. The deficiencies were associated with malfunctions-which

1

would likely result in a plant transient. The licensee had not fully assessed

i

the need for detailed written off-normal procedures and had continued to depend

heavily on-the overall experience and expertise of the operating crews to

respond properly to the events.

SD$h $$$

-

j

. - - - - _

,

,

,

.

-

,,

--2-

The licensee had recently determined that the station electrical and certain

other procedures were within-the scope of the initial safety-related procedure

upgrade program.

The licensee was in the' process of developing and fornelizing

procedure classification _ criteria and reassessing all the plant procedures to

ensure proper classification. Additionally, the licensee had recently-

commenced the upgrade of the 1408 annunciator response procedures'with plans

for completion in early 1991. Selected-groups of the annunciator procedures

had been.given priority in order to have the procedures available for initial ~

sinolator activities commencing in mid-1990.

,

1

1

!

l

I

l

-I

- I

3

.

.

'

.

-3-

DETAILS

1..

PERSONS CONTACTED

OPPD'

>

  • W. G. Gates. Division Manager, Nuclear Operations
  • R. L. Andrews, Division Manager; Quality & Environmental Affairs
  • S.-K. Gambhir, Division Manager, Production Engineering;
  • G. R. Peterson, Manager
  • J.- K. Gasper, Manager, Training-

-

  • R. L. Jowarski, Manager, Station Engineering

-

  • L. T. Kusek, Manager, Nuclear Safety Review -
  • T. J. McIvor, Manager, Nuclear: Projects

' *R. Phelps, Manager, Design Engineering (.QA)/ Quality Control (QC) -

l

  • W. W. Orr, Manager, Quality Assurance

..

.

  • P. Swartz, Manager, Electrical

Instrumentation and Control-(I&C)

,

  • J. W. Tills, Assistant Manager

!

  • R. Mueller . Supervisor, Nuclear Projects
  • D. J. Mathews, Supervisor, Station Licensing
  • T. G. Therkildsen, Supervisor,-Nuclear Licensing

.

  • D. W. Dale, Supervisor, QC-

-D. Trausch, Supervisor, Operations

!

J. Fluehr, Supervisor, Technical Training-

  • C. Huang, Supervisor, HPES/RCA
  • C

F. Simons, Station Licensing Engineer

'a

  • T. C. Mathews, Station Licensing Engineer
  • D

Stice, Licensing Engineer

D. Stading, Procedures Review Project

i

M. Lazar, Supervisor,. Technical Training

'

  • S. Swearingen, Nuclear Safety Review Specialist
  • R. Short, Supervisor, Special Services Engineering
  • C.- Boyd, Special Services Engineer
  • R. Lippy, Special Services Engineer
  • P. Hamer, Special Services Engineer

NRC

  • J. Gagliardo, Chief Operational Programs Section

1

  • P. Harrell, Senior Resident Inspector,.FCS

Other members of the technical and administrative staff were also contacted,

i

  • Denotes those attending the management exit on March 16, 1990.

!

l

l

_

_.

_ _

_

_

_ _ _ _

E

.

-

.-

.

l

'

'

..

-4-

1

!

l<

2.

FOLLOWUP ON PREVIOUSLY IDENTIFIED INSPECTION FINDINGS (92701)

j

2.1

(0 pen)InspectorFollowupItem(285/8936-01): Development o'f Acceptance'

.

Criteria Regarding the Classification of Safety-Related Procedures.

The lack of definitive acceptance criteria associated with the classification

"

of the safety-related procedures to be included in the procedures upgrade

program was identified'during the previous inspection conducted in September-

4

1989.

Document reviews and interviews revealed that seven electrical procedures had

been added to the. list of safety-related procedures. The' initial review of the

list of operations procedures by the licensee revealed that 43 other procedures-

,

were.apparently safety-related and another 31 procedures were potentially-

safety-related. The system for the classification of procedures _was. presently

t

being developed. The project completion,- including the reassessment of all-

procedures, was scheduled for April 1990. This issue will remain open as an-

. inspector followup item pending the: completion of the project by the licensee.

2.2 '(0 pen) Inssector Followup Item (285/8936-03): AbnormalOperating(A0P)

j

'

'

and Alarm Response (ARP) Procedures. The AOPs and ARPs required further

review following the completion of the procedure apgrade project by the

l-

licensee.

L

The inspector reviewed selected A0Ps for scope'and content to ensure that;the

l-

procedures addressed the requirements of Technical Specification 5.8,

Procedures; ANSI N18.7-1972, Sections 5.3, " Operating and Maintenance'

Procedures"; Sections E and F (5 and 6) of Appendix A to RG 1.33; FCS.QA

Program, Appendix A to USAR, Section A.6, " Instructions, Procedures, and

I

drawings"; FCS QA Plan, Section 2.1, " Procedures and Instructions"; and USAR,

-

1

Section 12.3, " Conduct of Operations."

.

Document reviews and interviews revealed that the licensee completed the A0P'

upgrade / rewrite program on December 7, 1989, and the revised procedures became

,

l

effective on January 4,1990. The A0P upgrade project included procedure

!

restructure and reformating, some regrouping, and a comparison of the FCS plant

l

procedures to certain other plants. However,.a specific project directive or

charter was not provided. The writer's guide, utilized for the upgrade

project, was subsequently issued as a Station Procedure 50-G-74, " Fort'Calhoun

E0P/A0P Writer's Guide," Revision 0 (December 12,1989). The results of the

g

review of specific procedures is discussed in the following sections.

.'

2.2.1 A0P-02, "CEA and Control System Malfunction," Revision 0 (January 4,

1990)

The AOP addressed the following situations:

Section I, Inoperable, Stuck, or Untrippable Control Element Assembly

(CEA);

<

.

.

.

.

,

-

-

I

-

-

'

'

l

.*

.,

-5-

I

Section II, Hisaligned CEA;

"

Section III, Unplanned / Uncontrolled CEA Withdrawal; and-

q

"

Section IV, Loss of Position Indication or Function.

The inspector reviewed the procedure.and associated ARPs to determine if.the .

.AOPincluded-selectedforeseeablereactor/planttransients(excursionsand/or

perturbations) resulting from a control system malfunction. An unplanned /uncon-

trolled CEA insertion (negative reactivity insertion-and reactor power reduction)

producing reactor-turbine power mismatch was.not sufficiently addressed in

'the procedure. This scenario would result in ~a reactor trip from system low . ,

pressure (transient / excursion / perturbation)intheabsenceofpositivecorrective:

actions by the operators to return the plant to stable conditions. The procedure-

did not specify the prompt operator actions to: terminate the transient, and-

prevent the challenge.to the reactor protection system by the elimination

of the reactor-turbine power mismatch.

Interviews with the licensee revealed that the rod control selector switch was

generally maintained in the "0FF" position when not in use; therefore, the.

chances for CEA withdrawal or insertion events were minimized.

In addition-to-

.the AOP, the inspector reviewed the anunciator. response procedures (ARP)

associated with the reactor controls (Panel CB-4, Annunciators'A7 and A8). The

ARPs provided minimal guidance regarding1the automatic actions, immediate-

-

operators actions, and long-range operator actions to. address'the response and

recovery actions associated with this foreseeable event.

The review of A0P-02 by the inspector also revealed an apparent inconsistency

regarding the use of applicable Technical-Specifications (TS) references. The

applicable TS was not generally referenced; however,-(in one instance).

TS2.10.2(1),regardingshutdownmarginrequirements,wasspecifically

referenced in Section I of the procedure. The methodology for including the TS

,

i

requirement within the procedure and/or referencing the TS requirement was not

addressed by the A0P/E0P Writer's Guide (50 G.74). This item was discussed

i

with the licensee.

A specific cross reference to the documents providing the basis for A0P-02 was

!

notprovided(e.g...specificUSAR,TS,orcommitment). Discussions with the

licensee revealed that a " Design Basis Document" was being.develo

A0P which would provide.the specific bases and cross references. ped for each

The licensee

indicated that these docun'ents were scheduled to.be: issued sometime in the

.!

April 1990,

l

i

2.2.2 A0P-16, " Loss of Instrument Bus Power," Revision 0 (January 4,1990)

-The A0P addressed the four safety-related 120V AC inverter buses (AI 40A, 40B,

40C,and40D). Document review and interviews revealed that vital equipment-

receiving electrical power from the inverter buses, including inputs to the CEA

clutch power panels, the radiation monitoring panels, the reactor regulating

,

a

,:.

,

,

..'

-6-

systems, and the feedwater regulation systems. The procedure did not address

the impact of the foreseeable loss, partial loss, and/or degradation of these

vital power sources on the reactor plant and other vital equipment. Positive

operator corrective actions were not adequately addressed.

Interviews revealed

that the licensee had not provided a detailed evaluation of the loss of the

120V AC inverter buses and the impact on the plant.and other vital equipment.-

The specific operator actions required to cope with these foreseeable conditions,

are'needed'to assure safe; operation of the plant.

i

The failure to address adequately the loss or degradation of the vital bus

power- sources (120V AC . inverter buses 40A.- 40B, 40C, and 40D) including the

impact on the plant and'the required-operator actions is an apparent

violation (285/9014-01) of Technical Specifications 5.8.1, which requires'that

written procedures shall be established to provide guidelines to the operators

for off-normal conditions that could-' degenerate into true emergencies.

The inspector also questioned the fact that the A0Ps did not address the loss of

twoadditional120VACinverterbuses(Al42A/IB1AandA142B/IB1B),which

provided power to the steam plant and turbine control board,

2.2.3 AOP-07, " Evacuation.of-'the Control Room," Revision 0 (January 4; 1990)

~

The inspector. reviewed the procedure for overall content and checked the'

'!

procedure specifics to ensure that adequate directions were provided to

operators regarding the-performance of the procedure-steps (e.g.. valve

numbers, panel numbers, specific locations)

,

No deficiencies were identified in this procedure.

2.2.2 AnnunciatorResponseProcedures(ARP)-

The inspector reviewed the status of the ARP-rewrite program. Document reviews

and interviews revealed that the ARP rewrite program was in progress. The

detailed project plan and a writer's guide for ARPs-(S0 G-75) had been drafted.

Theilicensee had identified 1408 annunciator windows associated with 55 alarm

panels. The licensee was in the process of placing.a priority for upgrading

!

,

the ARPs based on a judgement regarding the importance of the panels and to '

assure they would be availab!c for initial simulator activities.

The project had been estimated to require over 2 man-years of effort and

additional manpower was assigned to the project. The projected completion date

.

was early 1991.

'

"

This matter will remain open pendire the completion of the ARP rewrite program.

..

_.

. . . . . - - . . .

l

____

,lw

.

.

P

, . . - .

-7-

2.3 (Closed)Inge,;torFollowupItem(285/8936-04): Loss or Degradation of

Power to Vital AC Buses (4160V AC and 480 V AC) and Associated Load

Distribution Centers

The need for these procedures was . identified to the licensee during.the

i

previousinspection-(50-285/89-36) in September 1989. During the review of;

E0P-2, " Loss of Off-Site Power / Loss of Forced Circulation " the inspector-

,q

noted that-the licensee-apparently had no procedures which addressed the

'

actions to be taken for a loss or degradation of_ electrical' power to the; vital-

AC buses. During the exit interview, the-licensee acknowledged the concern

and stated that they would evaluate the issue and take appropriate action'to;

correct the concern.

,

'

1

Although the licensee had revised Item 48 of the Safety Enhancement Program-(SEP)

to incorporate the revision to the ARPs as discussed in paragraph 2.2.2 above,.

-_they had not revised Item 49, " Revise and Conduct Training on Emergency and-

Abrormal 0perating' Procedures." When questioned about this, a licensee represen-

4

. tative stated that this. issue had not been included in a revision =to Item 49

-

-;

'because of an oversight. He stated that Item 49 had already been closed.and-

,

.they had no' desire to reopen it.- The licensee's representative agreed that

1

there was'a need to evaluate the loss.or degradation'of the electrical power

l

" supplies, including the 4160V AC, 480V AC, 480V AC motor control centers? l20V

AC and 125V DC. The licensee: representative stated that on or about yay 1,;

1990, they would begin.to evaluate-the-total plant-electrical' power systems for

impact and to determine the need for providing appropriate procedures to.

'

respond to the identified conditions. Their plans were to complete this effort

1

by early 1991.

1

-

.

The failure to provide procedures addre'ssing the loss or degradation of

j

electrical power sources (e.g., 4160V AC, 480V AC, 125V DC) including'the

impact on the plant and the required operator actions is another example of'the-

violation (285/9014-01) of TS <5.8.1 cited in paragraph'2.2.1.

2.3.1 E0P-07,"StationBlackout," Revision 1(January 25,1990)

The. inspector reviewed the emergency operating procedure for recovery a station

blackout (lossofboth4160VACvitalbuses).

,

1

The.. inspector noted:that the entry point of the procedure (E0P-07) ~was from the

1

reactortripprocedure(EOP-00)-hotshutdownfollowinga_reactortrip/ turbine

'

trip. The procedure addressed the use of the turbine driven auxiliar

feedwater pump (FW-10) in accordance with the operating instruction (y01-FW-4)

or E0P-20, " Functional Recovery Procedure." The . inspector identified to the

. licensee that a' station blackout.might occur at conditions when E0P-00 could

not be easily applied to the situation. The-inspector's review of-S0-G-74,

'"EOP/A0PWriter'sGuide," Revision 0(December 12,1989), Section 2.1

!

-(Procedure' Network) revealed that.the procedure specified that for events more

-

serious than normal transients, but not severe enough to require a reactor trip

,

l

'

e

.

-. ..

_-

.

.

-

. . - -

.

, , . .

-8-

j

or for which the reactor' is already shutdown, shall be included in an A0P.

It:

was not apparent to the inspector which procedure or procedures would be

utilized by the operators to address a station blackout at other than normal'

Mode 1 or 2 conditions.

-.

This situation was discussed with the licensee for consideration' and followup

to ensure the. operators have clear' guidance _regarding this type of situation.

.

It was noted'that this question may have generic-implications. .The inspector-

had no further questions regarding this issue.

1

The inspector reviewed'the procedure E0P,-" Functional Recovery (Procedure," safety

Revision 7 (January 25,1990) for the recovery of.125Y DC bus

-

bus _and the success paths (Resource Tree B) to recover one 125V DC bus.

The inspector noted that- EOP-20 addressed the recovery of the 125V DC

battery / bus; however, the procedure did not address the. foreseeable' impact on

the plant, systems, or components resulting from the initial loss or

degradation of the 125V DC battery / bus.

r

This situation was discussed with the licensee for consideration and to ensure

that the loss or degradation of the.'125V DC was to be considered'during the

'

upcoming evaluation of the electrical buses.

-3.

PROCEDURES - GENERAL (42700)

The inspector reviewed selected procedures regarding the implementation of the

off-normal: procedures,

h

l

Standing Order SO 0-1, " Conduct of Operations," Revision 0 (February 26

.

j

1990)

'

-

Section 10. " Plant Operating Procedures,"' addressed procedure compliance

requirements for operating-procedures only;-however, the1 standing order

did not adequately address the procedure compliance for other types _of

,

i-.

procedures and no other guidance documents addressed the ~other types of

ll

_ procedures. The inspector discussed this-item with the licensee.

Standing' Order S0-16, " Operating Procedures," Revision 7 (July 25,1990).

,;

Section 7.2, regarding performance requirements, addressed OP-10 (annunciator

response-procedures-ARPs),Lnoting that the ARPs-provided corrective

actions-for alarms caused by specific conditions; however, the interface

<

between ARPs, A0Ps, and'EOPs was not addressed. The inspector discussed

this matter with the licensee.

' '

,

Standing-Order S0-18, " Emergency Operating Procedures," Revision 5

E

Wuly 25,1988) .

L,

.

L

No performance requirements such as the purpose of the E0Ps and the

L

interfaces _between-the EOPs, A0Ps, and ARPs were specified in the

procedure. The inspector discussed this matter with the licensee.

i.

.

L

l

,

.-

-.

-

_

-

_ _ _ _ - _ _

.

,:

.

,

'

  • *

,

.

-9-

.

I

Standing Order 50-18A, " Abnormal Operating Procedures," Revision 1

(April 11, 1987)

No performance requirements such as the purpose of the A0Ps and the

l

interfaces between the A0Ps, E0Ps, and ARPs were specified in the

procedure. The inspector discussed this item with the licensee._

.

No Yiolations or deviations were identified in the review of this program

_

a rea :, -

,

4.

@ALITYASSURANCEAUDITS

The inspector reviewed the status of the planned.QA audit regarding procedures.

(QAAudit67).

Document review and-interviews revealed that the QA audit regarding the E0Ps

,

and A0Ps was presently scheduled to be performed in May through June _1990.

.

This time period was chosen to; assure the use of_the plant simulator;during the

c

audit.

,

The.. inspector discussed the overall involvement of the: QA staff in these and

other special safety-related activities, considering early and frequent-

involvement in ongoing projects.

Regarding the off-normal procedures'(E0Ps, A0Ps,cand:ARPs),QA'noted'that'asa-

i

- result of the accomplishment of the root cause analyses associated with recent-

loss of electrical power events, several program / procedure-inadequacies:would:

likely be identified. These deficiencies may have generic as well as-specific-

'

implications and QA would be following the matters.-

The specific involvement. of:the QA group in the procedure upgrade program _

.

,

associated with the off-normal procedures upgrade projects is considered to be

'

an inspector followup-item and will be reviewed further during a subsequent

!

inspection. -(285/9014-02)-

No violations or deviations were identified in the review of this program-area.

5.

EXIT INTERVIEW

The inspector summarized the inspection scope and findings with the individuals

tuentified in paragraph 1.

Ine licensee-indicated that a previous commitment had been made to complete the

rewrite of the ARPs by January 15, 1991. No information reviewed by the-

inspector was identified by the licensee as proprietary.

4