ML20032B070

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-440/81-14 & 50-441/81-14 on 810929-1002. Noncompliance Noted:Failure to Follow Procedures Re Protection of Termination Cabinets & Spacing Between Adjacent Cables in Cable Trays
ML20032B070
Person / Time
Site: Perry  
Issue date: 10/21/1981
From: Gardner R, Hawkins F, Mendez R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20032B067 List:
References
50-440-81-14, 50-441-81-14, NUDOCS 8111040350
Download: ML20032B070 (6)


See also: IR 05000440/1981014

Text

e

.

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT.

REGION III

L

Report No. 50-440/81-14; 50-441/81-14

Docket No. 50-440; 50-441

License No. CPPR-148; CPPR-149

Licensee: Cleveland Electric Illuminating Company

Post Office Box 5000

Cleveland, OH 44101

Facility Name: Perry Nuclear Power Plant, Units 1 and 2

Inspection At: Perry Site, Perry, OH

Inspection Conducted: September 29 - October 2, 1981

'i

Inspectors:

. Gar ner

/O/2 / / B i

I

i

s

i

p

R.

e

}O/21/ B 1

v

i

I

a

Approved By: h .

.WHawkins, Acting Chief

/0/21/Al

~

Plant Systems Section

/

-' ~ ~

Inspection Summary-

Inspection on September 29 - October 2, 1981 (Report No. 50-440/81-14;

50-441/81-14)

Areas Inspected: Observation of electrical cable installation activities,

observation of electrical component work activities and review of records.

This inspection involved a total of 60 onsite inspection-hours by two NRC

inspectors.

Results: Of the three areas inspected, no items of noncompliance or

deviations were identhied in two areas. One apparent item of noncompliance

(Severity Level VI - examples of failure to follow procedures - Paragraphs Ib

and Ic) was identified in one area.

.

8111040350 811023

PDR ADOCK 05000440

G

PDR

.-

-

-

-

-

. - - - - - - - .

_ _ - - - - _ _ _ _ _ _ _ _ - -

- - - - .

-

)

.

.

DETAILS

Persons Contacted

Cleveland Electric 1.

minating Company (CEI)

  • M. Edelman, Manager, Nuclear Engineering Department

i

  • R. Farrell, Manager, Nuclear QA Department
  • E. Riley, Supervisor, CQS
  • G. Leidich, Supervisor, CQE
  • S. Tulk, Lead Electrical Quality Engineer
  • J. Kline, Generation Supervising Engineer
  • B. Barkley, Generation Supervising Engineer
  • D. Green, Senior Project Engineer, Nuclear Design

Kaiser Engineering, Inc.

  • D. Howard, Director, QA Programs
  • P. Gibson, Project QA Manager
  • Denotes those present at the exit interview.

Functional or Program Areas Inspected

1.

Observation of Electrical Cable Installation Activities

,

a.

The RIII inspectors selected six Class IE electrical cables

-

which had been installed in Unit 1.

The routing of each cable

i

was compared with the routing requirements identified on the

respective pull cards. The inspectors observed the following:

(1) 5KV power cable IR22H-5A was observed to be routed correctly

from 4.16KV switchgear Bus EH11 to 4.16/.48KV transformer

EHF-1-B.

(2) 15KV power cable IR22H-7B was observed to be routed correctly

from 4.16KV switchgear Bus EH12 to 4.16/.48 KV transformer

EHF-1-D.

(3) 600 volt control cable .'221C-41A was observed to be routed

correctly from Power Generation Control Complex (PGCC)

termination cabinet 1"13-P715 to 4.16KV switchgear Bus E!Ill.

(4) 600 volt control cable 1G41C-32A was observed to be routed

correctly from Motor Control Center (MCC) EFIA09 to PGCC

termination cabinet 1H13-P748.

(5) 600 volt control cable IM26A-6B was observed to be routed

correctly from PGCC termination cabinet 1H13-P746 to hCC

i

EFID09.

-2-

-

1

.

.

(6) 600 volt control cable 1M51A-2A was observed to be routed

correctly from PGCC termination cabinet 1H13-P743 to MCC

EFIB07.

The RIII inspectors observed that the raceway internals were

free of hazardous debris and sharp edges. Conduit bushings

were installed as required. The cables and raceways were

properly identified and undamaged. No separation problems

were identified.

b.

The inspectors observed numerous cables in the Unit I control

room which were coiled at the PGCC termination cabinets and

supported by cable ties. The inspectors observed that the

method the licensee used to protect coiled cable jackets from

being damaged by sharp edges on cable ties, involved the use

of cloth which isolated the caole jacket from the cable ties.

However, the inspectors observed that the cable jackets of

cables coiled at PGCC termination cabinets IH13-P743 and

1H13-P746 were not protected from damage due to sharp edges

on cable support ties. The inspectors observed that the

cable jacket on Class IE cable IP45C-19A was damaged by the

sharp edge on its cable support tie. Furthermore, the jackets

on several other coiled cables were observed to be impinging

on the sharp edges of their respective cable support ties.

This condition is contrary to the requirements of paragraph

3.2.24 of L. K. Comstock cable pulling procedure 4.3.3 which

states in part, "...

the cable shall be protected so that

the tie does not damage the cable jacket."

This failure to accomplish activities affecting quality by

documented procedure * is considered an item of noncompliance

with 10 CFR 50, Apr.ndix B, Criterion V as described in

Appendix A of the report transmittal letter.

(440/81-14-01)

The inspectors observed that the Class 1E medium voltage

c.

armored power cables installed in cable trays A106, B256, and

B268 were laid such that direct contact was maintained between

adjacent cables. This condition is contrary to the requirements

of paragraph 3.2.17 of L. K. Comstock cable pulling procedure

4.3.3 which states in part, " Class 1E medium voltage armored

power cable ...

shall be installed in their exclusive cable

tray with a nominal spacing of 3/8" between adjacent cables."

This failure to accomplish activities by documented procedures

e

is a further example of noncompliance as cited in Paragraph 1.b.

(440/81-14-01)

d.

The inspectors observed that Class iE cables were pulled through

core drilled penetration ECC 4368 having neither a sleeve nor a

sleeve bushing to protect the cables. The inspectors questioned

the licensee concerning the measures being taken to protect such

-3-

t

-

,

cables from the rough edges where cables enter and exit such pene-

u ations. The inspector:: were shown a copy of field question

No. 15502, dated July 27, 1981, which addressed this concern.

The engineering response to the subject document inclu hd a

procedure for the repair of rough eiges on core drilled penetra-

tions. The inspectors observed core drilled penetration ECC 4368

and determined that the penetration was free of rough edges.

The inspectors observed that Class 1E cable tray B1332 and non-

e.

class IE cable tray X1146, located in the cable spread room, had

a horizontal separation of 3" in lieu of the required 12" separa-

tion. The inspectors reviewed Gilbert Associates raceway in-

sta11ation drawing D-214-142, revision H, and determined that

a separation barrier was to be installed between the subject

trays at a later date.

L licensee stated that during raceway

installation inspections the quality control inspector will

verify either adequate separation is maintained b> tween raceway

of different divisions or that separation barriers are identified

on raceway installation drawings. The licensee further stated

that, should a required separation barrier noc be identified on

a raceway installation drawing, the quality control inspector

will issue an Inspection Report (IR) to identify and control the

missing barrier. The RIII inspectors observed that the quality

control inspector who sign-J the raceway installation card for

Class IE tray B1332, indicated on the card that the separation

barrier was verified as being identified on the raceway drawing.

f.

The RIII inspectors observed the installation activities pertain-

ing to the PGCC interconnecting electrical cables and determined

the following:

(1) The divisional floor ducts, which serve as raceway for the

interconnecting cables, were free of sharp edges.

(2) The inspectors observed that there was no separation barrier

installed at the transition point (coordinates X-001, Y-0024,

25) in which a division III floor duct becomes a non-divisional

floor duct. The licensee stated that Field Design Instruction

(FDI) WNKI was being issued by General Electric which would

require the installation of additional firr barriers. The

inspectors reviewed a marked up drawing of the PGCC floor

duct complex which identified the need for a barrier at the

aforementioned location.

2.

Observation of Work Activities - Electrical Components

The inspectors observed the installation activities pertaining

to the following electrical components:

a.

Residual Heat Removal Pump Motor (5KV), IE12-C002C

-4-

,. ..

(1) The installation records Indicated the subject motor was

!

stored in place.

(2) Receipt inspections were performed and documented on a

Receip. Inspection Report, dated January 20, 1977.

(3) The motor heater was energized as required.

(4) Storage and maintenance requirements were deliueated.

Records indicated that these requirements were being

implemented.

b.

Reactor Core Isolation Cooling Water Leg Pump, IE51-C003

(1) The installation of the subject motor was acceptable. The

motor was installed by traveler No. T1-E51-01, revision 0,

in accordance with procedure GEP-1P-0103, revision 1.

(2) Receipt inspections were performed and documented on a-

Receipt Inspection Report, dated May 15, 1980.

(3) Storage and maintenance requirements were delinented. Records

indicated that these requirements were being implemented.

c.

Motor Operated Valves 1E12-F105, IE51-F0010

(1) The installation of the subject motor operated valves (MOV)

was acceptable. MOV 1E12-F105 was installed in accordance

with Pullman isometric drawing IE12-49, revision 10A. MOV

IE51-F0010 was installed in accordance with Pullman isometric

drawing IE51-5, revision 8.

(2) Receipt inspections were performed and documented on Receipt

Inspection Reports.

(3) At the inspector's request, the licensee removed the operator

housings from the subject MOV's.

The inspectors verified

that internal heaters were energized and that the MOV internal

components were free of damage or corrosion.

(4) Storage and maintenance requirements were delineated. Records

indicated that these requirements were being implemented.

d.

The inspectors questioned the licensee concerning the subject of

underrated terminal boards, previously identified on Limitorque

valve ope.ators. The inspectors were shown a copy of a licensee

memo r .,nna requesting the station Nuclear Test Section to perform

inspections on Limitorque valve operators to ensure that under-

rated term.nal boards are not included in Perry installed M0V's.

-5-

__

_

.

..

.s

3.

Review of Records

'

The inspectors _ reviewed the receipt inspection records, storage and

maintenance records, and installation records pertaining to the

electrical components identified in Section 2 of this report. The

records were retrievable and acceptable.

Exit Itierview

The inspectors met with licensee representatives _(denoted in the Persons

Contacted paragraph) at the conclusion of the inspection on October 2,

1981. The inspectors summarized the scope and findings of the inspection.

The licensee acknowledged the information.

_,

-

-6-