Text
-
S RELATED COMtESPONDENCE 1
DEBEVOISE & LIBERMAN 1200 S EVENTEENTH STRC ET, N. W.
WASHINGTON D. C. 2OO36-3088 tEOmano w. ett?En C'"E""'"^""*""J"'
(202) 857-9800 W A, = E S..,5 -0 eauCE t oOw=Ev.
..C M A.o C...Ow E
~' ~ ' ~ ' " ~ ' "
Octob 15, 1981 DALE E. MOLLan Och ALD R. Dama g En wtLLIAM A MO RIN SCOTT M. Dw 3OFF W'LLIAM A. REMOE M JOSEPM B. R NOTTS. J4.
RfCMANO D LLOYD.
JAM ES S. LIGERM AN MALCOLM M PMeLtPS. J m.
ReCM ARD LITTELL wlLLIAes J, se ADOE N. JR.
PN O
J. essCesAEL ft.GammT, M at==ETM J.=EiSES y
4C ROS S O'DONOOseUE f*-
numer JOMw P. pmOCv04 CHEmyt Lymes wlLLsaus estCoeOLAS S REvh0LDS JOMN F. WetSON.
FREDERICR ?. S EAmLS THOM AS M. DE SEv0eS E
\\
cov=sEL Jose *Me moses N-
..m...
- m was?tn's cenECT oiAL wCo=n-9831 Herbert Grossman, Esq., Chairman Dr. Frank F.
Hooper Administrative Judge Administrative Judge Atomic Safety and Licensing School of Natural Resources Board Panel University of Michigan U.S.
Nuclear Regulatory Ann Arbor Michigan 48109 Commission
(\\P) g f ge Washington, D.C.
20555
's
,f\\.h
- J Mr. Gustave A.
Linenberger "J
) ",
^
N6$ ga Administrative Judge Atomi'c Safety and Licensing A 00T191981 Board Panel m ixt u #
U.S.
Nuclear Regulatory CC""'" #
Commission 4
Washington, D.C.
20555
/
\\
In the Matter of South Carolina Electric & Gas Company, et al.
(Virgil C.
Summer Nuclear Station, Unit 1)
Docket No. 50-395 Gentlemen:
This is to confirm that Applicants are no longer request-ing that the hearings be reconvened the week of October 19, 1981, 3
inasmuch as the directed certification matter remains unresolved, the Staff advises that their reviews of the reports by Fletcher /
3 Joyner, Trifunac and Luco are continuing, and both Applicants and Staff are proceeding with further work related to the matters
/ D referred to in Mr. Nichols' October 9, 1981 letter to Mr. Denton.
We propose that the hearings be reconvened November 9, 1981 to continue until the evidence of all witnesses for all parties (and, depending on the outcome of the directed certification 9110200283 811015 PDR ADOCK 05000395 i g
b Judge Herberg Grossman Judge Frank'F. Hooper Judge Gustave A. Linenberger October 15, 1981 Page Two matter, Messrs. Fletcher, Joyner, Trifunac and Luco) are heard on the Board's questions regarding seismicity.
Applicants have now deferred their estimated fuel load readiness date to late February 1982, as indicated in Mr. Nichols' October 13, 1981 letter to Mr. Denton.
Never-theless, given the standard intervals set forth in the Commission's Rules of Practice, special efforts by the Parties and by the Board will still be required to complete hearing and posthearing matters, so as to achieve an initial decision by late February.
Therefore, this is to advise that we expect to propose a compressed schedule for proposed findings and decision on the Board's questions regarding seismicity issues.
Since proposed findings by all Parties have already been submitted on most of the issues, and since proposed findings on the emergency planning issues are due to be submitted October 26, 1981 by Applicants, November 3, 1981 by the Intervenor and November 13, 1981 by the NRC Staff, we would request the Board to proceed with its initial decision in three partial decisions, i.e.,
(a) those matters already covered in the proposed findings, (b) emergency planning matters and (c) seismicity matters.
This approach will make manage-able and attainable, we hope, the objective of completing the hearing, posthearing, and decisional processes in time for late February fuel loading.
~
- rely, Jgseph'B. Knotts,}Jr.
At or ey for Applicants JBK/pv cc:
Service list
,w
.m
-, -