Forwards IE Insp Repts 50-338/81-16 & 50-339/81-13 on 810608-12 & Notice of Violation
ML20031E830
Person / Time
Site: North Anna  
Issue date: 08/20/1981
From: Kellogg P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Leasburg R
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
Shared Package
ML20031E822 List:
References
NUDOCS 8110160472
Download: ML20031E830 (2)


See also: IR 05000338/1981016

Text

~

1

..

_

yc//ou)

'

'

,

,

MG 2 01991

Virginia Electric and Power Company

ATTN:

Mr. R. H. Leasburg, Vice President

Nuclear Operations

P. O. Box 26666

Richmond, VA 23261

Gentlemen:

Subject: Report Nosh /8bl6)d50-339/81-13

This refers to the routine safety inspection conducted by Mr. J. M. Puckett of

this office on June 8-12, 1981, of activities authorized by NRC License Nos.

NPF-4 and NPF-7 for the North Anna facility.

Our preliminary findings were

discussed with Mr. W. R. Cartwright, Station Manager, at the conclusion of the

inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report.

Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews with

personnel, and observations by the inspectors.

During the inspection, it was found that certain activities under your license

appear to violate NRC requirements.

These items and references to pertineet

requirements are listed in the Notice of Violation enclosed herewith as Appen-

dix A.

Elements to be included in your response are delineated in Appendix A.

We have examined actions you have taken with regard to previously identified

enforcement matters and unresolved items. The status of these items is discussed

in the enclosed report.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this

letter and the enclosed report will be placed in the NRC's Public Document Rnom.

If the report contains any information that you believe to be exempt from dis-

closure under 10 CFR 9.5(a)(4), it is necessary that you: (a) notify this office

by telephone within ten days from the date of this letter of your intention to

file a request for withholding; and (b) submit within twenty-five days from the

date of this letter a written application to this office to withhold such infor-

r.ation.

If your receipt of this letter has been delayed such that less than

seven days are available for your review, please notify this office promptly so

that a new due date may be established. Consistent with section 2.790(b)(1),

such application must be accompanied by an affidavit executed by the owner of the

information which identifies the document or part the eof sought to be withheld,

and a full statement of the reasons on the basis of w'ich it is claimed that the

information should be withheld from public disclosun e.

Th's section further

requires the statement to address with specificity the considerations listed in

8110160472 811 '

PDR ADOCK OS

G

DR

.

. -

-

-

-

.

l

~

,

.

'

'

'

AUG 2 0198;

Virginia Electric and Power Company

2

10 CFR 2.790(b)(4). The information sought to be withheld shall be incorporated

.as far as possible into a separate part of the affidavit. If we do not hear from

you in this regard within the specified periods noted above, the report will be

placed in 'the Public Document Room.

Should you have any questions concerning this letter, we will be glad to discuss

them with you.

Sincerely,

<w_r

'

Paul J. Kellogg, Chief

Reactor Projects Branch 2

Division of Resident and

Reactor Project Inspection

Enclo sures.:

1.

Appendix A, Notice of Violation

2.

Inspection Report Nos. 50-338/81-16

and 50-339/81-13

cc w/ encl:

J. H. Fergusen, Executive

Vice President

W. R. Cartwright, Station Manager

bec w/ encl:

NRC Resident Inspector

Document Management Branch

Commonwealth of Virginia

. -

.

RII

RI

RII

pRII

-

~JMPuckett:aw

CMHos

AFGibson

L4tt%ew4s

8/ 4/81

8/g/81

8/4/81 ~

8/gg/81'