ML20031D934

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-454/81-11 on 810727 & 0826-28.Noncompliance Noted:Failure to Follow Procedures in Verifying Instrument Calibr & to Adequately Review Manual Revision Re Categorizing Procedure Changes
ML20031D934
Person / Time
Site: Byron 
Issue date: 09/23/1981
From: Hind J, Jackiw I, Ring M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20031D926 List:
References
50-454-81-11, NUDOCS 8110140383
Download: ML20031D934 (5)


See also: IR 05000454/1981011

Text

.

_

-

.. .-

.

.

U.S. NUCLEAR REGUI ATORY COMMISSION

,

OFFICE OF INSPECTION AND ENFORCEMENT

REGION III

Report No.- 50-454/81-11

,

!

Docket No. 50-454

License No. CPPR-130

i.icensee: Commonwealth Edison Company

P. O. Be:- 767

Chicago, 2L 60690

Facility hame: Byron Station, Unit 1

Inspection At: Byron Site, Byron, IL

Inspection Conducted: July 27 and August 26-28, 1981.

/]1N.O [

f[</Tr

Inspectors:

M. Ring

i

<

m

v.4 1

J. Hinds (July 27)

9/b//

2

-

w ' f 'kiv, Acting Chief

7

".,d

6>,

fl. b ~'

-

/

Approved By:

I.N. Jac

/

Test Programs Section

'

Inspection Summary

,

Inspection on July 27 and August 26-28, 1981 (Report No. 50-454/81-11

Areas Inspected:

Routine announced inspection to review preoperational

test procedures and results; previous open items relating to the pre-oper-

stional test program and the cold hydrostatic test procedure for the reactor

coolant system. The inspection involved 31 inspector-hours onsite by two

NRC inspectors including 0 inspector-hours onsite during off shifts.

Results: Of the four areas inspected, no apparent items of noncompliance

or deviations were identified in one area.

Within the three remaining areas

two apparent items of noncompliance were identified, one of which contained

examples in two areas (failure to follow procedures-Paragraphs 4, 5a, and 5b;

failure to perform adequate review of changes - Paragraph 3.

110140383 811001

JgDRADOCKOSOOOg5]

.

.-*r-e----or ,-.

--.,%,.

-,.-w,

. . , , , - - , + . - ~ . -

,..-,+.,--.-,--,,..-,.,,c.-.,

,w-,

--%---

-,w-

. . . - ,

--v,-.--+

,

,m.-,,,

.,-.-,--,..c,

y

-

-

.

DETAILS

,

1.

Persons Contacted

-

R. Querio, Station Superintendent

  • R. Ward, Assistant Superintendent, Administration an/. Support
  • R. Pleniewicz, Assistant Superintendent, Operating
  • L. Sues, Assistant Superintendent, Maintenance
  • M. Stanish, Quality Assurance Superintendent
  • R. Tuetkin, Assistant Project Superintendent
  • P. Ervin, Tech Staff Supervisor
  • J. DeRosia, Field Engineer-Construction
  • R. Westberg, Lead Quality Assuranca Engi .eer, Operations
  • R.

Grams, Master Instrtment Mechanic

A. Chernick, Preoperational Test Coordinator

P. Johnson, Electrical Group Leader

T. Didier, Quality Control Supervisor

R. Branson, Operating Engineer

S. Swan, Start-up Staff

G. Schwartz, Master Electrician

D. Johnson, Instrument Foreman

  • Denotes those attending the exit interview.

2.

Licensee Action on Previous Inspection Findings

a.

(Closed) Open Item (454/80-23-08): The inspector reviewed-

Revision 0 of B0C-HK-1, Station Housekeeping Surveillance,

dated July 1981 and interface agreements between the Opera-

tions and Construction organizations. The inspector dis-

cussed comments with the licensee and determined the above

items to be acceptable.

b.

(C1csed) Open Item (454/80-23-09): The inspector reviewed

Revision 0 of BAP 400-4, Control of Station Measuring and Test

Equipment, dated June 1981 as the licensees procedure which

pr vides overall control and direction to several more detailed

proceJures covering usage of test and measuring equij ent.

The

procedure appears to be adequate.

c.

(Closed) Open Item (454/81-06-01): The inspector reviewed

Revision 1 of BQI 23.2, Monitoring of Pre-Op fests, dated

August 13, 1981. The procedure incorporated pre-operational

test specific audit procedures pertaining to such things as

preparation by audit personnel, extent of audit and surveill-

ance coverage and assignment of responsibility. The procedure

appears to be adequate.

d.

(Closed) Open Item (454/81-06-02): The inspector also review-

ed BQI 23.2, Monitoring of Pre-Op Tests for specific job-related

.

-2-

-

. _ _..___, _ . - _ -

.

. .

.

.

. .

-

-

._ _

. _ _

.__ _. _, _

_

.

_ _

_ . .

_.

_ . _

.

.

)

1

iw

activities and training requirements relative to the pre-opera-

tional test phase. The procedure appears to be adequate in ti-is

area.

(Closed) Open Item (454/80-23-05):

This item dealt with comments

e.

,

made by the inspector when tte Start-up Guidelines document was

i

elimated via Revision 2 to the Startup Manual. Revision 5 to the-

Startup Manual was reviewed by the inspector as centaining the

i

resolution to those comments. Revision 4 adequately resolved

the inspector's comments and therefore the item is considered

closed.

i.

f.

(0 pen) Open Item (454/80-23-07): The inspector discussed _com-

ments with the licensee resulting both from the pre-performance

review and the completed test review of Pre-Operational Test

'

2.21.10, 125 V DC Distribution. Since neither the Station nor

the Project Engineering Department have yet accepted this test,

I

the item will remain open pending resolution of inspector comments,

completion of licensee review and subsequent review by the in-

spector.

3.

Jtartup Manual Review

During the Startup Manual review, the inspector noted that :n

Section 3.5.2 entitled Major Changes to Pre-Operational Tests or

Startup Tests, sub paragraphs 2.1 and 2.1.1, 2.1.2, and 2.1.3

were contradictory.

Paragraph 2.1 was consistent with the title

-

,

stating that "any change that changes the intent of a procedure is

a major change." However, sub paragraphs 2.1.1, 2.1.1 and 2.1.3

all describe minor change attributes such a in 2.1.2, "The revision

'

-

does not change the intent of the procedure." The Startup Manual

describes the method of making changes to the manual as requiring

proofreading and review by the Startup Group, concurrence by Site

Quality Assurance and authorization by the Project Manager. Failure

to adequately review and proofread the chaage to the Startup Manual

is considered to be a violation of 10 CFR 50, Appendix.B, Criterion

VI and the Startup Manual paragraph 1.4.4 and is an example of an

,'

item of noncompliance (454/81-11-01).

4.

Preoperational Test Procedure Results Review

l

During the revi w of completed test procedure PT 2.21.10, 125V DC

Distribution, the inspector questioned how the test engineer was

able to " Verify all installed instrumentation in the SDP (System

~

Documentation Package) is within current calibration intervals" as

'

required by paragraph 6.3 of PT 2.21.10.

Since the particular test

engineer had subsequently left the licensee's employ, members of

,

the Technical Staff agreed to determine how th.is requirement was

'

satisfied. Upon investigation, Tech Staff representatives stated

that "being calibrated" was satisfied by asking OAD (Operational'

Analysis Department) but they did not know-how "within current

'

intervals" was satisfied since OAD reported ta the Tech dtsff that

!

f

i

-3-

i

~~~..-,-,,.n

,,,ne,----,,.,...-~,-,,-,~,,-.~-u-..,e,.a..

, , , , ~ , , - , . - . . ,

,

_

.

.

.

.

t

the calibration intervals for the instruments in question were not

yet established. Failure to perform the test in accordance with

the procedure is considered to be a violation of 10 CFR 50 Appendix

B, Criteria V and XI and is an example of an item of noncompliance

(454/81-01c).

5.

Cold Hydrostatic Test

The inspector reviewed a copy of the completed construction test pro-

cedure 2.63.810, Reactor Coolant Cold Hydrostatic Test and inter-

viewed one of the test conductors, one of the operating engineers,

a member of the Technical Staff and one of the instrument foremen

with respect to the Celd Hydro. The inspector noted the fallowing

problems:

a.

Paragraph 6.2 of the test procedure states, " Verify that all

instrumentation in Appendix A is within current calibration in-

te rvals . " In the completed procedure, Appendix A consisted

,

of a computer printout of many instrun,ents and components (many

of which cannot be calibrated) listing the date on which the

instrument was calibrated. Review of the list showed several

components with a calibration date of "1/1/90N." When the in-

spector questioned the meaning of a 1990 date, the instrumenc

foreman indicated this was a fictituous date deliberately

applied to allow the computer to printout and indicating the

component was not a "calibrateable" component. However, the

inspector noted that a pressure switch, IPS/-RC0403, which

the instrument foreman said should be able to be calibrated,

showed a 1/1/90N date.

Since the list contained several 1990

i

designations, the inspector questioned how the Hydro test re-

quirement of paragraph 6.2 was actually satisfied. The test

,

conductor indicated that if the instrument contained a calibra-

tion date, it was considered satisfactory. The inspector

reviewed the list for calibration dates and noted four instru-

cents, ITS/-RC0433A, IPT-CV0115, ITE-CV0167, and ILT-SIO930

which had no calibration dates at all listed. Additionally,

the " current calibration intervals " described in paragraph 6.2

were reported by the instrenent foreman to be not yet established

for most of the instruments. The above problems constitute fail-

ure to verify the prerequisite paragraph in accordance with the

procedure which is considered to be a violation of 10 CFR 50

Appendix B, Criteria V and XI and is an example of an item of

noncompliance (454/81-11-02a).

b.

Paragraph 9.2.49 of test procedure 2.63.810 says to " increase

system pressure to 3102-0+25 psig" while the following para-

graph 9.2.50 states " Maintain the 3102-0+12.5 psig pressure for

a minimum of ten minutes". Actual p. essure recorded on the

by.irostatic test certificate was 3135 psig. While this actual

pressure meets the minimum pressure for a satisfactory strength

and tightness test and does not exceed the calculated over

p essure point, it does exceed the pressure bands of paragraphs

-4-

,

. - - , . -

. _ _ .

..

- --

-

.--

- - - .

. ..

-.

.

-

_ _

_-

.

.

4

.

' t

9.2.49 and 9.2.50.

Failure to perform the test in accordance

with the procedure is considered to be a violation of 10 CFR 50

4

Appendix B, Criteria V and XI and is an example of an item of

noncompliance (454/81-11-02b).

In addition, the inspector observed portions of the test performance

and reviewed the completed test procedure. The inspector observed

the conduct of the test, verification of prerequisites, observation

of precautions, calibration and placement of hydro test gauges,

overpressure protection, documentation of results and deficiencies.

With the exception of the previous items of noncompliance, these

areas were all considered adequate.

6.

Exit Interview

The inspector met with licensee representatives (denoted in paragraph

1) on August 28, 1981. The inspector summarized the scope and findings

of the inspection. The licensee acknowledged the statements by the

inspector with respect to the open items and the items of noncompliance

(Paragraphs 3, 4 and 5).

/

.

$

s

!

,

s

- 5-

. . _ . ,

. . _ . . _ . . - - - _ _ _ . . . _ _ _ _ _ - _ _ _ _ _ _ _ . , _ _ _ , . , . _ . _ _ - _ - _ _ , _ . _

_ . _. . .- ~, ..

-

-