Interim Deficiency Rept Re Cutler-Hammer Motor Control Ctrs. Addl Nonconforming Starter Units Identified.All Units Not Included in PNPP Insp Will Be Inspected for Proper Wiring & Terminal Blocks
ML20031D259
Person / Time
Site: Perry  
Issue date: 10/01/1981
From: Davidson D
CLEVELAND ELECTRIC ILLUMINATING CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, 10CFR-50.55E, RDC-17(80), NUDOCS 8110130188
Download: ML20031D259 (1)


Text

6)t?($] 67).55(o l

THE CLEVELAND ELECTRIC ll.LUMIN ATING COMPANY 1

P o Box 5000 m CLEVELAND. oHlo 44101 e TELEPHONE (216) 622-9800

  • ILLUMINATING BLOG_

e 55 PUBLICSoUARE "9

C## "

Dalwyn R. Davidson VICE PRESIDENT SYSTEM ENGINEERING AND CONSTRUcitoN October 1, 1931 i

Mr. James G. Keppler Director, Region III l

Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137 RE:

Perry Nuclear Power Plant Docket Nos. 50-440; 50 l.41 Repairs to Motor Control Centers [RDC 17(80)]

Dear Mr. Keppler:

As discussed with Mr. L. McGregor of your office on September 24, 1981, the final repairs on the motor control centers supplied by Cutler-Hammer are now scheduled to be completed on December 1,1981.

While the corrective action outlined in our letters dated March 9,1981, and May 29, 1981, remains the same, additional nonconforming starter units have been identified.

These units had been inspected by Cutler-Hammer but were not among the sample of 200 inspected by PNPP inspectors. We have now decided to inspect all starter units not previously included in the PNPP inspection sample for proper wiring and terminal blocks.

~.

/.\\

1*.h" A

If you have additional questions, please don't hesitate to call.

/

J i

e Very truly yours, t

!~

OCT 9198W _

i f

% zm u.s. ng,%^"'"

I Dalwyn. Davidson

.Y Vice President System Engineering and Construction-DRD:pab gg cc: USNRC - Site Mr. Victor Stello, Director 5

i Office of Inspection and Enforcement i

U.S. Nuclear Regulatory Commission l h Washington, D.C.

20555 U.S. Nuclear Regulatory Commission c/o Document Management Branch Washington, D.C.

20555 l