Boiling Water Reactor Submittal of Final Status Survey Final Report - Phase 3
Date released: 02/04/2020 Download: ML20031C839


Boiling Water Reactor Submittal of Final Status Survey Final Report - Phase 3
ML20031C860
Person / Time
Site: La Crosse File:Dairyland Power Cooperative icon.png
Issue date: 01/28/2020
From: Gerard van Noordennen
LaCrosseSolutions
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards
References
LC-2020-001
Download: ML20031C860 (9)
Boiling Water Reactor Final Status Survey Final Report - Phase 3
ML20031C858
Person / Time
Site: La Crosse File:Dairyland Power Cooperative icon.png
Issue date: 01/28/2020
From: Yetter R
LaCrosseSolutions
To:
Office of Nuclear Material Safety and Safeguards
References
LC-2020-001
Download: ML20031C858 (61)
Boiling Water Reactor Final Status Survey Final Report - Phase 3, Survey Unit L1-SUB-TDS B RPGPA (Release Record)
ML20031C857
Person / Time
Site: La Crosse File:Dairyland Power Cooperative icon.png
Issue date: 01/28/2020
From: Yetter R
LaCrosseSolutions
To:
Office of Nuclear Material Safety and Safeguards
References
LC-2020-001
Download: ML20031C857 (1131)
Boiling Water Reactor Final Status Survey Final Report - Phase 3, Survey Unit L1-SUB-TDS a Eastern Portion TB, Sump, Pit, Diesel (Release Record)
ML20031C855
Person / Time
Site: La Crosse File:Dairyland Power Cooperative icon.png
Issue date: 01/28/2020
From: Uz M
LaCrosseSolutions
To:
Office of Nuclear Material Safety and Safeguards
References
LC-2020-001
Download: ML20031C855 (341)
Boiling Water Reactor Final Status Survey Final Report - Phase 3, Survey Unit L1-SUB-CDR Stack, Pipe Tunnel, RPGPA Excavation (Release Record)
ML20031C853
Person / Time
Site: La Crosse File:Dairyland Power Cooperative icon.png
Issue date: 01/28/2020
From: Yetter R
LaCrosseSolutions
To:
Office of Nuclear Material Safety and Safeguards
References
LC-2020-001
Download: ML20031C853 (272)
Boiling Water Reactor Final Status Survey Final Report - Phase 3, Survey Unit L3-012-109 Plant Access, ISFSI Haul Road Grounds East (Release Record)
ML20031C852
Person / Time
Site: La Crosse File:Dairyland Power Cooperative icon.png
Issue date: 01/28/2020
From:
LaCrosseSolutions
To:
Office of Nuclear Material Safety and Safeguards
References
LC-2020-001
Download: ML20031C852 (479)
Boiling Water Reactor Final Status Survey Final Report - Phase 3, Survey Unit L3-012-101 North End of Licensed Site (Release Record)
ML20031C850
Person / Time
Site: La Crosse File:Dairyland Power Cooperative icon.png
Issue date: 01/28/2020
From:
LaCrosseSolutions
To:
Office of Nuclear Material Safety and Safeguards
References
LC-2020-001
Download: ML20031C850 (283)
Boiling Water Reactor Final Status Survey Final Report - Phase 3, Survey Unit L2-011-104 G3 Crib House, Circ. Water Discharge Land (Release Record)
ML20031C849
Person / Time
Site: La Crosse File:Dairyland Power Cooperative icon.png
Issue date: 01/28/2020
From: Yetter R
LaCrosseSolutions
To:
Office of Nuclear Material Safety and Safeguards
References
LC-2020-001
Download: ML20031C849 (247)
Boiling Water Reactor Final Status Survey Final Report - Phase 3, Survey Unit L2-011-101 Area North of Lse Fence
ML20031C847
Person / Time
Site: La Crosse File:Dairyland Power Cooperative icon.png
Issue date: 01/28/2020
From: Yetter R
LaCrosseSolutions
To:
Office of Nuclear Material Safety and Safeguards
References
LC-2020-001
Download: ML20031C847 (279)
Boiling Water Reactor Final Status Survey Final Report - Phase 3, Survey Unit L1-010-107 Outside East Lse Area
ML20031C846
Person / Time
Site: La Crosse File:Dairyland Power Cooperative icon.png
Issue date: 01/28/2020
From: Yetter R
LaCrosseSolutions
To:
Office of Nuclear Material Safety and Safeguards
References
LC-2020-001
Download: ML20031C846 (322)
Boiling Water Reactor Final Status Survey Final Report - Phase 3, Survey Unit L1-010-106 North Loading Area
ML20031C845
Person / Time
Site: La Crosse File:Dairyland Power Cooperative icon.png
Issue date: 01/28/2020
From: Yetter R
LaCrosseSolutions
To:
Office of Nuclear Material Safety and Safeguards
References
LC-2020-001
Download: ML20031C845 (335)
Boiling Water Reactor Final Status Survey Final Report - Phase 3, Survey Unit L1-010-105 North Interim Debris Storage Area
ML20031C844
Person / Time
Site: La Crosse File:Dairyland Power Cooperative icon.png
Issue date: 01/28/2020
From:
LaCrosseSolutions
To:
Office of Nuclear Material Safety and Safeguards
References
LC-2020-001
Download: ML20031C844 (277)
Boiling Water Reactor Final Status Survey Final Report - Phase 3, Survey Unit L1-010-104 North Lse Grounds
ML20031C843
Person / Time
Site: La Crosse File:Dairyland Power Cooperative icon.png
Issue date: 01/28/2020
From:
LaCrosseSolutions
To:
Office of Nuclear Material Safety and Safeguards
References
LC-2020-001
Download: ML20031C843 (301)
Boiling Water Reactor Final Status Survey Final Report - Phase 3, Survey Unit L1-010-103 LSA Building, Maintenance Eat Shack Grounds
ML20031C842
Person / Time
Site: La Crosse File:Dairyland Power Cooperative icon.png
Issue date: 01/28/2020
From: Uz M
LaCrosseSolutions
To:
Office of Nuclear Material Safety and Safeguards
References
LC-2020-001
Download: ML20031C842 (285)
Boiling Water Reactor Final Status Survey Final Report - Phase 3, Survey Unit L1-010-102 Turbine Building, Turbine Office Building, 1B Diesel Generator Building Grounds
ML20031C841
Person / Time
Site: La Crosse File:Dairyland Power Cooperative icon.png
Issue date: 01/28/2020
From: Uz M
LaCrosseSolutions
To:
Office of Nuclear Material Safety and Safeguards
References
LC-2020-001
Download: ML20031C841 (283)
Boiling Water Reactor Final Status Survey Final Report - Phase 3, Survey Unit L1-010-101 Reactor Building, Wtb, Wgtv, Ventilation Stack Grounds (Release Record)
ML20031C840
Person / Time
Site: La Crosse File:Dairyland Power Cooperative icon.png
Issue date: 01/28/2020
From: Uz M
LaCrosseSolutions
To:
Office of Nuclear Material Safety and Safeguards
References
LC-2020-001
Download: ML20031C840 (281)