Forwards IE Insp Repts 50-460/81-06 & 50-513/81-06 on 810622-26 & 0706-10.No Noncompliance Noted
ML20031A488
Person / Time
Site: Washington Public Power Supply System
Issue date: 09/11/1981
From: Faulkenberry B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Mazur D
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
Shared Package
ML20031A489 List:
References
NUDOCS 8109230564
Download: ML20031A488 (2)


See also: IR 05000460/1981006

Text

_ _ _ _ _ _ _ _ _ _

.

.

. _ _ _ _ _ _ _ _ _ _

._____ _

.

,

P

yt x+s

}

'k

f-

.{

(

1

SEP 11 B81

Docket No. 50-460, 50-M3

6

O)

f

Of h j\\ J R) -f.}

Washington Public Power Supply System

P. O. Box 968

[

3000 George Washington Way

-

Richland, Washington 99352

-

SEP 2 21981"' h

G')"' M s on

-.

-

?

Attention: Mr. D. W. Mazur

&

Program Director, WNP-1/4

Gentlemen:

/ %1

Subject: NRC Inspection of Washington Nuclear Projects 1 and 4

This refers to the inspection conducted by Messrs. R. T. Dodds, D. P. Narbut,

G. Hernandez and A. D'Angelo of this office on June 22-26 and July 6-10,

1981 of activities authorized by NRC Construction Pemit Nos. CPPR-134 and

CPPR-174, and to the discussion of our findings held with you and other

members of your staff at the conclusion of the inspection.

Areas examined during this inspection are described in the enclosed inspection

report. Within these areas, the inspection consisted of selective examinations

of procedures and representative records, interviews with personnel, and

observations by the inspector.

No items of noncompliance with NRC requirements were identified within the

scope of this inspection.

In accordance with 10 CFR 2.790 of the Comission's regulations, a copy

of this letter and the enclosed inspection report will be placed in the

NRC's Public Document Room.

If this report contains any information that

you (or your contractors) believe to be exempt fmm disclosura unde.r 10

CFR 9.5(a)( ), it is necessary that you (a) notify this office by telephone

within ten (10) days from the date of this letter of your intention to file

a request for withholding; and (b) submit within 25 days from the date of

this letter a written application to this office to withhold such information.

If your receipt of this letter has been delayed such that less than seven

(7) days are available for your review, please notify this office promptly '78d

.

so that a new due date may be established.

Consistent with section 2.790

5

(o)(1), any such application must be accompanied by an affidavit executed

/

by the owner of the infonnation which identifies the document or part sought

///

to be withheld, and which contains a full statement of the basis on which

it is clained that the information should be withheld fro" public disclosure.

8109230564 810911

PDR ADOCK 05000460'

G

PDR'

m

omer >

NV/ dot

%

"" ,dobbs"' ' "kX8U1' ""1EM

EZ"

D'ANGELD

.TA 'KENBERRY

"""""""""-

""""""""""

o u ,,4,

_c.......urnuvvvuc -870ur - - 877.1sc

urnuc

-

-- -

,

- - - -

i

...........

... ......... . .....

....... .. ..........

... ... ..........

. ...................

. . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . .

nne ronu me no,soi nncu o2"

OFFICIAL RECORD COPY

wmm e-329 24 l

- ____/ /_J

- - - - - - - - - - .- .

.

.

Washington Public Power Supoly System

-2-

u _1

.

This section further requires the statement to address with specificity

the considerations listed in 10 CFR 2.790(b)(4).

The information sought

to be withheld shall be incorporated as far as nossible into a separate

cart of the affidavit.

If we do not hear from you in this regard within

the specified periods noted above, the report will be place <* in the Public

Document Room.

>

Should you have any questions concerning this inspection, we will be gleJ

l

to discuss them with you.

Sincerely,

.0c

.

c N

<h , &

'

j,_

B. ft. Faulkenbefry, Chef

f

Reactor Construction Projects Branch

Enclosure:

IE Inspection Report

,

No. 50-460/81-06

50-513/81-06

'

cc w/o enclosure:

R. B. Glasscock, quality Assurance Director

Sent to DMB for DCS processing.

Distributed by RV:

}

RV PDR

Resident Lispector (3)

State of WA (Lewis)

RHE (w/o enclosure)

i

.

.

mm