Notifies That Since Violation Noted in Insp Rept 50-219/92-07 Re Failure to Promptly Correct Conditions Adverse to Quality Occurred,Organizational Changes Occurred to Improve Timeliness of Action in Regard to Deficiencies
ML20029E221
Person / Time
Site: Oyster Creek
Issue date: 05/11/1994
From: J. J. Barton
GENERAL PUBLIC UTILITIES CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
C321-94-2072, NUDOCS 9405170286
Download: ML20029E221 (2)


Text

. -

... ~

GPU Nuclear Corporation

U Nuclear

":=:2388 Forked River, New Jersey 08731-o388 609 971-4000 Writer's Direct Dial Number:

C321-94-2072 May 11, 1994 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555

Dear Sir:

Subject:

Oyster Creek Nuclear Generating Station Docket No. 50-219 Response To Inspection Report 92-07 Notice of Violation GPU Nuclear Corporation (GPUN) provided a response to the Notice of Violation (NOV) cited in Inspection Report 50-219/92-07 by letter dated June 18, 1992.

Thi,s violation was issued as a result of a failure of a " prop spring" in Diesel Generator #2 output breaker. The NOV cited a failure to promptly correct conditions adverse to quality.

GPUN concurred with the violation and provided the required response pursuant to 10 CFR 2.201.

Recently, during an NRC inspection, the inspector' requested information relative to corrective actions taken as a result of the violation described above in order to complete the NRC closecut of the v.iolation.

During the course of this review and GPUN efforts to provide the necessary closecut documentation, it was found that a statement made in GPUN's response was in

)

error.

Specifically, the response stated " Revisions to action item requirements and due dates procedurally require the concurrence of the assigned manager (this is at least one level of management higher than the person performing the work)".

This statement was incorrect.

It was also stated in the NOV response that Plant Engineering Management would periodically review the backlog to assure assignments and schedules are appropriate. This action has been proceduralized.

)

It should be noted that since the time of this violation a number of organizational changes have occurred which are expected to significantly improve the timeliness of action in regard to deficiencies.

These changes include the establishment of the System Engineer and System Performance Team structure.

This initiative has proved to significantly improve system evaluation and work coordination.

9405170286 940511 1-PDR ADDCK 05000219

'l A

O PDR i

GPU Nuclear Corporation is a sut;sidiary of the General Pubhc Ubbties Corporation h

C321:04-2072

'Page 2 All safety related 4160v Magne Blast breakers with greater than 1000 cycles have been repaired or replaced to correct deficiencies identified in GE SAL 348.1 with regard to prop spring failure.

All affected breakers remaining will be upgraded prior to or during the upcoming 15R outage commencing in September of this year with the exception of the Station Blackout breaker which will be upgraded in cycle 16.

If you should have any questions or require any additional information please call Mr. George Busch at (609) 971-4643.

ery tr force Johl J. B r;on Vic b Pre i ent & Director Oy ter Cr>ek JJB/GB: Jc cc: Administrator, Region 1 Senior Resident NRC Inspector Oyster Creek NRC Project Manager i