k.) }h//cin SOUTH CAROLINA ELECTRIC & GAS COMPANY POST O*PiCE 764 QS101 MN CotuusIA. SouTM CApouNA 29218 O. W. OtxoN. JR.
January 20, 1983 g py WCr Opf 5; DENT mete.p o.eurio~.
Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation Nuclear Regulatory Commi'ssion U.S.
Washington, D.C.
20555
Subject:
Virgil C. Summer Nuclear Station Docket No. 50/395 Operating License No. NPF-12 Emergency Technical Specification Change
Dear Mr. Denton:
South Carolina Electric and Gas Company (SCE&G) requests that emergency changes be processed for the Technical Specification items as shown on the attached " marked-up" pages 3/4 3-19, 3/4 3-21, and 3/4 3-22.
A summary of these changes and associated justifications are as follows:
1)
Table 3.3-3, item 4(b) - The " Action" column for this 21 instead of item should address Action Statement This change is in accordance Action Statement 19.
with Westinghouse Standard Technical Specifications.
item 6(h) - The " Action" column for this Table 3.3-3, 2) item should address Action Statement 16 instead of Action Statement 16 allows for Action Statement 19.
an inoperable channel to be placed in a bypassed condition whereas Action Statement 19 requires that an l
inoperable channel be placed in a tripped condition.
By allowing an inoperable channel to be placed in a the trip logic becomes a 2 out of bypassed condition, 3 coincidence instead of a 2 out of 4 coincidence.
This maintains the intent of the Technical even with one (1)
Specification requirement, l
l inoperable channel.
Table 3.3-3, item 8(a)_ - The " Action" column for this I
I 3) item should address Action Statement 16 instead of This change is in accordance Action Statement 19.
with the Westinghouse Standard Technicalin the event of an inoperable
- Also, 16 is Spe ci f ica ti on s.the action required by Action Statement
- channel, act > apnropriata than ti, ~_ required by Action Statement 19, in that overall plant safety is enhancea,,y o
1 h (kAD $.pp 8301310263 830120 PDR ADOCK 05000395
.P PDR
Mr. Harold R.
Denton Amendment to Operating License January 20, 1983 Page 2 placing the inoperable channel in a bypassed condition as opposed to a tripped condition.
4)
Table 3.3-3, item 8(b) - the " Action" column for this item should address Action Statement 14 instead o.f Action Statement 19.
This change is in accordance with Westinghouse Standard Technical Specifications.
These changes have been reviewed and approved by both the Plant Safety Review Committee and the Nuclear Safety Review Committee as required by the Technical Specifications.
A check in the amount of twelve hundred dollars ($1,200.00) is enclosed for processing of this Class II Amendment to the Operating License.
Very truly yours,
/
/
/
O. W.
Dixon, Jr.
ARK:NEC:OWD:lkh Attachment cc:
V.
C.
Summer E.
C.
Roberts H.
N.
Cyrus T.
C.
Nichols, Jr.
O.
W. Dixon, Jr.
M. B. Whitaker, Jr.
J.
P.
O'Reilly H.
T.
Babb D. A.
Nauman C.
L. Ligon (NSRC)
W.
A. Williams, Jr.
R.
B.
Clary O.
S. Bradham A.
R.
Koon M.
N. Browne G.
J.
Braddick J.
L.
Skolds J.
B.
Knotts, Jr.
B.
A.
Bursey NPCF File
.