ML20028E738

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-382/82-28 on 821101-30.No Noncompliance Noted.Major Areas Inspected:Independent Design Review,Mgt Meeting,Control Room Design Review,Preoperational Testing & Instrumentation & Control
ML20028E738
Person / Time
Site: Waterford Entergy icon.png
Issue date: 01/05/1983
From: Constable G, Crossman W, Cummins J, Flippo T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20028E733 List:
References
50-382-83-28, NUDOCS 8301280161
Download: ML20028E738 (10)


See also: IR 05000382/1982028

Text

.

_

APPENDIX

U. S. NUCLEAR REGULATORY COMISSION

-

REGION IV

NRC Inspection Report:

50-382/82-28

License: CPPR-103

Docket:

50-382

Licensee: Louisiana Power and Light Company

142 Delaronde Street

New Orleans, Louisiana 70174

Facility: Waterford Steam Electric Station, Unit 3

Inspectica At: Taft, Louisiana

,

,

Inspectiori Conducted: November 1,1982, through November 30, 1982

Inspectors-

_

17/z

PL

G. L. Tohstable, Senior Resident Inspector

Date'

'

/

12.b9 /7 7--

J. E. Cummins, Resident Inspector

Date

d G. h

n/u/ex

T. A. Flippo, Rbsident Inspector

Date

Yb'Y//JM!w 3

//Jb3

l

Approved:

A. C Crossma

Chief ~

Da(e/

Reactor Pr ect Section B

Inspection Summary

Areas Inspected: Routine, announced inspection of: _(1) Independent

Design Review; (2) Management Meeting; (3) Control Room Design Review;

(4) Preoperational Testing; and (5) Instrumentation and Control. This

inspection involved 130 inspector-hours by three NRC inspectors.

,

Results: Within the areas inspected, no violations or deviations were

-

identified.

.

8301280161 830110

PDR ADOCK 05000382

O

PDR

,

,

-

-

_

.-

.

-2-

,

DETAILS

1.

Persons Contacted

  • D. Lester, Plant Manager

L. Arnold, Unit Coordinator Operations Testing

B. Toups, QA Engineering Technician

G. Pittman, QA Engineer

  • J. Woods, Plant QC Engineer

T. K. Armington, Lead Startup Engineer

  • B. Morgan, QA Engineer

T. Gerrets, QA Manager

  • G. Rogers, Site Director

C. Wells, Advisor to Vice President Nuclear Operations

  • Present at exit interviews.

In addition to the above personnel, the NRC inspectors . held discussions

with various operations, construction, engineering, technical support,

and administrative members of the licensee's staff.

2.

Plant Status

The Waterford 3 site is presently in the preoperational testing phase.

The licensee completed the RCS and SG hydrostatic tests during October.

Pre core hot functional testing is scheduled to begin in January. The

current, published fuel load date is May 1983. Construction is

indicated as approximately 94% complete.

j

3.

Independent Design Review

During this inspection period, NRC inspectors visited Torrey Pines

Technology to review the ongoing independent design review of the

emergency feedwater system. The NRC inspectors reviewed the " Program

Plan," Revision B, dated September 13, 1982, and discussed the review

activities with engineers and managers associated with the independent

review. Persons contacted during this review are listed below:

!

,

l

l

i

l

!

.

. . - '"'

_ _ _ _ . _ .

_

__

__

_ . .

_

. _ .

.

9

-3-

i

Torrey Pines Technology

(

L. Johnson

Manager - Projects'

.

F. Carpenter

Project Manager

M. Dunlap

Senior Quality Assurance' Engineer-

'

A. Schwartz

Engineering Task Leader

,

M. Verdugo

Staff Engineer

,

.

A. Chuang

Staff Engineer

i

F. Lin

Senior Engineer

M. Gitternan

Senior Technical Coordinator

V. Flanagan'

Staff Engineer

J. Graves

Offsite Field Engineering Supervisor

NRC

G. L. Constable

Senior Resident Inspector - Waterford 3

L. E. Martin

Reactor Inspector - NRC Region IV

"

a.

Independence

!

I

The NRC inspector had discussions with the project'managerLfor

the Waterford Unit 3 design review to determine any contractural

obligations between General Atomics (Torrey Pines) and Louisiana

Power and Light Company (LP&L), Ebasco. Services, Inc. (Ebasco),

.

!

or Combustion Engineering, Inc. (C-E). Since .the cancellation

of the St. Rosalie Station for LP&L, there did not appear to-

i

be any areas of significant conflict.

The NRC inspector reviewed Project Directive 3, dated September 23,

1982, " Technical Independence," which pertains to signed statements

by all General Atomic employees that are.providing significant

input into the Waterford 3 design review. Twenty-one of the

signed statements and 20 professional resumes were reviewed

to determine if possible conflicts of interest might exist and

the qualification of: involved personnel. All'of the personnel

appeared to be highly qualified and the experience levels ranged

from 10 to 25 years. There were no areas identified that appeared

to be of concern regarding personal conflict of interest.

b.

Training

The I4RC inspector had reviewed the training requirements for the

'

Waterford 3 design review and the designated' training records.

The training requirements were adequate and the material. covered

was appropriate.

4

4

.

- -

- .

..

-.

.:

-

. . . -.

-.

. - -

.

.

..

.

-4-

,

c.

Design Procedure Review - Task A

Review of the design procedures utilized in'the Waterford 3

emergency feedwater system is complete. The review'was done

to the requirements of Amendment 44 of the Waterford 3 Preliminary

Safety Analysis Report. No potential findings were identified

in Task A.

d.

Design Procedure Implementation - Task B

This task is in process and approximately 50% complete. ' The

master checklist is complete; however, no individual checklist

has been completed yet. The master checklist was comprehensive

and adequately detailed.

e.

Technical Review - Task C

The NRC inspectors interviewed staff engineers involved in the

following portions of the independent design review:

Emergency Feedwater System Performance

Instrumentation and Controls

Piping

Piping Supports

Cable Raceway Supports

The NRC inspectors concluded that the individuals involved in the

review were highly qualified for the work they were doing.

Early potential findings were discussed in terms of how they were'

identified and how they are to be evaluated. The review system

(Task E) appears to be adequate.

f.

Physical Verification Walkdown - Task D

i

l

The scope of the physical verification does not reflect a complete

evaluation of the system. The sample size of what is looked at

I

in depth is limited.

It appears that-the purpose of the overall

review is to ascertain that controls are sufficient to result in

!

an adequately designed and installed system; however,-ther

review does not appear to be broad enough to give complete

confidence . hat the system will ultimately operate as intended.

. _ _ _ - _ _ _ . . _ , . . . _

,

_

__

_

_ --_ . _ ._

. _ - .

. - - _ . _

.

'

.

1

-5-

!

As an example, only 1 hanger out of 14 is inspected in

-

detail to verify that it was constructed as designed. The

'

other hangers were looked at to determine if the location and

crientation were correct, but no attempt will be made to

i

determine if the other hangers will support their intended '

loads. Also, the scope of the review does not include anchor -

bolts or embed plates to which the hangers are attached to

the plant structure.

.

The selection of items reviewed does appear to meet specific

i

program and procedt al requirements and should-give a good

understanding of types of problems; however, it is not clearf

-

what kind of conclusion can be drawn on the adequacy of the

installed system.

g.

Conclusion

,

'

Individuals involved in the design review were very impressive

'

j

in their areas of expertise.

It was not. clear if the scope

i

of the physical verification walkdownLis appropriate to meet

!

the objectives of the overall design review. .This will be

discussed during subsequent meetings on this subject. The.

>

final report (Task F) and potential findings-(Task.E) will be

'

reviewed when they become available.

!

No violations or deviations were identified.

4.

Management Meeting

l

A meeti.ng was held with representatives of LP&L on November 23,1982,

to discuss NRC Inspection Report 82-14 which identified significant'

quality assurance (QA) problems at the Waterford 3 facility. : The

)

QA problems had been identified in two areas of construction activity.

'

NRC management specifically requested that LP&L include in their

'

reply to NRC Inspection Report 82-14 what actions they have taken.or-

'

will take to assure that similar QA problems do not exist in other-

l

areas.

The following individuals attended the meeting:

~

'

[

NRC Representatives.

J. E. Gagliardo, Director, Division of Resident, Reactor Project

& Engineering Program, RIV

P. Keshishian,. Senior Reactor Construction Engineer

J. W. Craig, Enforcement Specialist'

'

,

J. H. Sniezek, Deputy Director IE

i

G. L. Constable, Senior Resident Inspector

J. E. Cummins, Resident Inspector

i

T. A. Flippo, Resident Inspector

W. A. Crossman, Chief, Reactor Project Section B

,

.

_

_

- m , , a -- _ . . _ . , _ .

_

_. , _ _

. .

. .

- -

. .

-

.._ .

_.

.

_

.

.

.

-6-

LP&L Reoresentatives

'

^

G. D. McLendon, Senior Vice President

,

L. V. Maurin, Vice President, Nuclear Operations

T. F. Gerrets, QA Manager

G. B. Rogers, Site Director

R. W. Prados, Licensing Engineering Supervisor

,

S. A. Alleman, Assistant Plant Manager

C. A. Wells, Advisor to Vice President Nuclear Operations

J. Woods, QC Engineer

L. L. Bass, Project QA Engineer

W. M. Morgan, QA Engineer

B. Toups, QA Engineering Technician

5.

Control Room Design Review

During the course of this inspection period, the NRC inspectors

.

reviewed the ongoing human engineering modifications being made

to the control panels. Specific discussions were held between

NRC and LP&L staff regarding the scheduled completion of 'open

humanengineeringdeficiencies(HED's)(0penItem 8228-01).

Completion of the individual commit:nents will be reviewed during

future NRC inspections.

6.

Preoperational Test

NRC Regulatory Guide 1.68, Revision 2, August 1978 states that

approved test procedures for staisfying ' final safety analysis

report (FSAR) testing commitments should be made available to the

,

NRC staff approximately 60 days prior to their intended use. On

l

November 30, 1932, the Senior Resident Inspector was notified that-

certain startup preoperational test procedures (SP0's) would be late.

The NRC inspector discussed this subject with licensee. personnel

and explained that,the 60 days gave the NRC inspectors adequate time

to review the startup preoperational procedures before the actual.

test is conducted. The NRC inspector infonned the licensee that:

any substantial delays in receiving these procedures could result

in a delay in starting the test or a violation of NRC requirements.

i

No violations or deviations were noted.

.

l

<

. >

'

'

7.

Instrumentation and Control

.

The licensee, during the past few months, has been reviewing NRC.

i

I

concerns regarding the installation and testing.of various flow and

level instruments in safety-related systems. ~ 0n November 23, 1982,-

.

6

'

'

, . _ _ _ _

, , , . -

, - _ _ _

_

. .

'

.

-7-

the NRC inspectors met with the site director and selected engineers

from the LP&L and Ebasco organizations, In previous inspections

(see NRC Inspection Reports 82-10 and 82-14) NRC inspectors have

noted that instruments and the associated impulse r' ping were not

being installed in accordance with the instrument manufacturer's

recommendations. The manufacturer recommends the following

installation practices be followed in order to ensure proper

operation and to minimize the possibility of errors:

a.

For liquid flow or pressure measurements, the transmitter

should be mounted beside or below the process connection

taps so that gases will vent into the process line.

b.

For gas flow or pressure measurements, the transmitter should

be mounted beside or above the taps so that liquid will drain

into the process line,

c.

Slope piping between the process connection and the transmitter

at least 1" per foot toward the process connection.

d.

Avoid high points in liquid lines and low points in gas lines.

Ebasco Installation Instruction IC-1, " Instruction for Erection of

Instrumentation Systems," Revision 1, and Drawing LOU 1564-430,

" Instrument Installation Details," do not distinguish between an

installation for the measurement of liquid as opposed to the

measurement of gas. High points are allowed and minimum required

'

slope, where slope is required, is 1/4" per foot from these high

points.

Industry standards allow instrument installation contrary to

manufacturer's recommendations on a case-by-case basis; however,

the instruments should still respond as designed. The startup

,

testing program should identify whether instrument installations

i

operate correctly.

I

The purpose of this meeting was for LP&L to discuss their review of

I

the instrument installations and to provide comments on the adequacy

of the installations.

LP&L identified 60 flow and level instrument installations that might

be susceptible to installation problems of the type discussed above.

.

During their review thus far, they looked at 47 installations. Of

l

these,13 had high points ranging from 1.5' to 26'.

In general, LP&L

believes that all of the 13 installations will operate correctly as

,

designed for the following reasons:

'

_ . _ .

. .

. ..-.

.

-.

.

. _ .

.

.

-8-

,

a.

All impulse taps come off the horizontal plane. . Air bubbles

are not likely to get into the impulse lines unless the process

!

pipe is drained.

.

b.

Impulse lines are run in parallel. .If one line gets air-in.it',

they both should over about equal lengths of the lines.-

c.

Significant air in an impulse line of a nonoperating system

should cause the instrument to drift off zero.

In such a

condition, operators should notice the drift and request that

maintenance evaluate the problem.

-

d.

In systems that operate under significant pressure, air ~in the-

impulse lines would be compressed, minimizing any errors.-

'

e.

Air that might come out of solution due to a'depressurization is

not significant.

'

During the course of the meeting,' the NRC inspector made the following

observations:

'

a.

The review did not include differential pressure instrumentsion.thei

various emergency ventilation systems.

'

~

b.

Time response of instruments is based on speed of sound in water.

No one in the meeting could'say whether air in the impulse lines

i

would cause a problem with time response.

c.

No guidelines were available to operators to help them determine

when an instrument should have its calibration checked.

d.

System operating procedures had not been reviewed _to determine

if any modes of operation might cause improper instrument

indications,

e.

Startup testing should identify if systems need rework because

of unforseen problems; however, it is'not clear how the systems-

are to be tested.

The NRC inspector observed that there appears to be a strong underlying-

belief on the part of LP&L representatives that air in' liquid instrument

lines is not a significant problem.

In certain cases, it may not be a

problem; however, this appears to be contrary to manufacturers guidance -

.

on the subject. ~ During the course of the startup test program, the

!

.

4

"

.

-

~ ~

~

~ * . -

' T *: Y' . ~. . .

_

_

-

--

.

.

.

-9-

,

NRC inspectors will continue to monitor testing to verify ~the above

assumptions, the adequacy of instrument installations, and that the

testing program adequately tests instrument systems that have been

installed in a questionable manner. A concern remains that some of

these instrument systems at the Waterford 3 plant may not properly

indicate system parameters under all expected system operating

-

conditions.

Thisissueremainsopen(8214-03).'

8.

Exit Interviews

The NRC inspectors met with the licensee representatives (denoted in

paragraph 1) at various times during the course of the inspection.

The scope and findings of the inspection were discussed.

.

-

.

4

Q

" .

I,

'

-

S

x -

,

,

-

w,

-

. . -- .---

- --

.

.. .

.

wic FORM 7es

U.S. NUCLEAR REGULATORY COMMISSION

PRINOPALINSPECTOR(Name est. 4rst Jnammeaw)

'i" an

G. L. Constable

INSPECiOR'S REPORT

R,y,E

ER

Office of Inspection and Enforcement

W. A. Crossman

' ' " ' ' "

G. L. Constable

T. A. Flioco

J. E. Cummins

4

Ta^=,$,goa

a'*o"

"'" *SnC oAn

oOCuT NO

OR uCE=SE

_

oCE,,,EE,,E,,xR

NO igv PRODUCTH13e9m

NO.

530.

MO

YR

Louisiana Power and

X

i - ~S'"

0

5 0 0 0

3 8 2

8

2 2 R

a

Licht Company

[

" - " ' "

"

o - oELETE

c

~

l

R - REPtACE

PL 9 % ;+T W j $ r+'2 *CMr7; ~ _' . _ . -

54

15

to

PERCO OF INVESTaGATON/INSPECTCN

INSPECTCN PERFORMEO SY

ORGANIZATION COCE OF REGCN/MO CONDUCT.

]OTHER

ING ACTmTY (Se e IEM,C,0$30

.M. gg y

anpower Mooort.

I

FROM

TO

1 - REGCNALOrFICE STAFF

wg g,,

,

MO.

oAY

YR.

MO

oAY

YR

RESCENT mSPECTOR

REGCN

i

D'VISW)N

'

SAANCH

ll1

0 11

812 1Il

310 812

2 - "a'oau^ac8 *a^' SAL TEAM

pry

I

c

l _3

i

25

as

si

-

.-

- m2m

-

$2

i

34 -

l

25

REGCNAL ACTIO4

TYP' OF ACTIVITY CONDUCTED ICheck one Dos omys

  • "" #

X

02 - S AFETY

_

us - MGMT. VISIT

_

to . PLANT SEC.

_

14 - lNOU*RY

l

1 -- NRC FORM 591

03 - INCIDEN f

07 - SPECAL

11 - INVENT. VER.

15 sNVESTIGATCN

2 - K'EGCN1.L OFFICE LETTER

04 - ENFORCEMENT

OB - VENDOR

12 - SMiPMENT/ EXPORT

05 - MGMT. AUDIT

09 - MAT. ACCT.

13 IMPORT

.. g ,' ' ' % l,

,

(* ,

37 3

,,

y

-

--

6,s 5 PE C T s0 6NwE5T GATsON FsNwNG5

TOTAL NUMBER

ENFORCEMENT CONFERENCg

RE POR T C@TAIN 2R

LETTER C# RE POAT TR ANSMITTAL D ATE

' * * oa* ba o'WY'

OF VOLATONS AND

HELD

FOR M ATON

l

e

C

D

DEVIATONS

NRC FORM 561

REPORTSENT

l

1 - CLEAR

OR REG.

TO HQ FOR

LETTERisSUED

ACTION

l

2 - VIOLATION

l

3 - DEVIATON

A

8

C

D

A

B

C

D

A

B

C

D!

, ,MO.

_ DAY

_YR.

MO.

DAY

YA

l

4 - VIOLATION & DEVIATON

1 - YES

l 1 - YES

lNf 1$ M

l

l

l

1

,

,

,

,

< ,A449 ',

,7.'e*: 42

5M's

. 43

44

49

50

SS

3

.

MODULE tNFORMATCN

MODULE *NFORMATION

Ik

MODULE REQ. FOLLOWUP

MODULE NUMSER iNSP.

6g g

vlODULE PEO FOLLOWUP

MODULE NUM8ER INSP.

yg g

[iik5 3e

r

EgIE5 48

r

9

5:

:

8 .,

s

8-

e a-9s-

5:

-

.

t5

g-

s

8-

e cm.su

-

a

,

-

se-

.

s

s

a

at

-z

s

a

s

-m

3 :< E}a

o -ra

a

L.55 E38

3 'I g:

-s

s:

"

-

5<

8g

y 2 6

z

-z

.

.

.

.

E.g3.gK =8e

ig

8g

g

t g

d

s

1

zo

4

<

I

r ,E

5

g

~53

<

a

..

r

I

so

r,

1

z

a, 5

t

z 2 5

r,

g

1

ro-

.

c

==

r

=

-

=

.

.

3 3,0 l7,0,3 lB

liil

7 i1 3 :0 7 l

1

45

50

C

i liil

i i2'

^

'

e

i

3

1

i

i

i i

i

!!

'

' '

'

' '

d '

' '

'

Exit

Plant Tour

liil

liil

c

c

i i

ii

i

, ,

i s

i

Ie i l

i i

i i

i !ii!

O

0

i i

i i

i

liil

3 9 ,2 l7 ,0 ,6 b

i 41 6

i i

i

3 3,0 l7 0 2 lB

liil

^

i i8

i i

i

^

i

.

,

'

Management

Independent Effor$

' '

' '

'

' '

' '

'

liil

Control Room

c

liil

Meeting

ii

i i

i

c

ii

i i

i

o

l

l

EFW Design Review

lf

l

o

.i

i t

t

it

i I

ii

f f

I

f

,

3 3 ,5 l3 0 ,1 l

l

l

3 7pl3,0i21

i i4

60

i liiI

25

9,5

,

^

^

.i

i

i

. i

ii

i

!I

' '

' '

' II

'

' '

' '

'

QA

Pre Op Program

liil

Implementation

liil

c

c

i i

i i

i

,,

, ,

,

liil

I,il

o

o

, i

s i

i

i ,

, ,

,

liil

liil

liil

. i

i

i i

i i

i liil

^

>

i

i

s i

i i

i

I

Iii1

liiI

'

ii

i i

i

. .

, .

i

l

liiI

liil

c

-

c

i i

i i

i

i i

i i

i

ciRCtf SEOm,.CE iF

=

=

t wotATC= OR otviATON

i i

, e

i l

i l

_._

1 3.

i

_

j ll g l

.

D

0