Text
-
PO BOX 5000 -
CLEVELAND. OHIO 44101 - TELEPHONE (216) 622-9800 - ILLUMINATING BLDG
- $5 PUBLICSOUARE Serving The Best Location in the Nation l
MURRAY R. EDELMAN January 6, 1983 VICE PRESIDENT NUCLI A R Mr. James G. Keppler Regional Administrator, Region III Of fice of Inspection and Enforcement U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137 RE:
Eerry Nuclear Power Plant Docket Nos. 50-440; 50-441 Extension for Corapletion on Location of Governor Lube 011 Cooler /Etandby Diesel Generator
[RDC 45(82)]
Dear Mr. Keppler:
As stated in onr letter dated June 28, 1982, it is still our intention to complete the relocation of the governor lubrication oil cooler during the final assembly stages of the diesel generators.
In our last letter the corrective action was scheduled to be completed by January 1,1983.
This date is in need of revision. The reason for this delay is to prevent possible damage that may be incurred during the repair of a subsequent 50.55(e) concerning defective welding on code pipe [RDC 52(82)].
The scheduled date for relocating the governor lubrication oil cooler for Unit 1 is July 1983 and the relocation for Unit 2 is tentatively scheduled to be completed by September 1983.
If there are any questions, please do not hesitate to call.
Very truly yours, Murray R.
Edelman 8301170261 830106 Vice President PDR ADOCK 05000440 Nuclear Group S
PDR MRE:pab cc:
Mr. M. L. Gildner NRC Site Office Ditector Of fice of Inspect ton and Enforcement U.S. Nuclear Regula tory Commission Washington, D.C.
20555 U.S. Nuclear Regula tory Commission dh c/o Document Management Branch 4[M7 Washington, D.C.
20555
-