Provides Info Re Implementation of QA Measures on Electrical Conduit Installations,In Response to Concerns Raised During NRC 820909-10 Site Insp.Stop Work Order for Pulling Cable in Empty Conduits Initiated on 820913
ML20028B441
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 09/14/1982
From: Fahrner W
DETROIT EDISON CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML20028B412 List:
References
EF2-58409, NUDOCS 8211300387
Download: ML20028B441 (2)


Text

__

. L ,

e WILLIAM J. FAHRNER g En o F ermi Uot 2 Prc,eci

  • 2000 Second Avenue I n Detrost. M4chigan 48226 (313) 237-8000 September 14, 1982 .

EF2-58409 Mr. James G. Keppler Regional Administrator U.S. Nuclear Regulatory Commission Region III Office 799 Roosevelt Poad Glen Ellyn, Illinois 60137

Reference:

Enrico Fermi Power Plant - Unit No. 2

Subject:

NRC Site Inspection of Electrical Installation, September 9 & 10, 1982.

Dear Mr. Keppler:

This letter confi ms information provided to Mr. K. R. Naidu and Mr. B. H. Little during a meeting at the Fermi 2 Site on September 10, 1982.

In response to concerns expressed by Mr. Naidu regarding the inspection of electrical conduit installations, the following actions have been, or are in process of being implemented:

1. A Stop Work Order was initiated for pulling cable in empty conduits and wireways.
2. All empty Quality Level I conduits and wireways will be inspected and accepted by Quality Control inspectors prior to the installation of cable. This applies to previously installed conduit as well as new installations. Any I deviation from this will have to be approved by Detroit Edison Field Engineering.
3. Edison's Project Quality Assurance Organization will review Comstock's Field Surveillance Correction Report (FSCR) to determine if the items identified should have been reported on a Nonconformance Report. In addition, the FSCR procedure will be reviewed for definitions and applicability.
4. The Project Quality Assurance Organization will review the Comstock procedure for ambiguities and conformance with Edison specification.
5. Training of craft foreman and Quality Control inspectors in the revised procedures.

8211300387 821123 gDRADOCK 050003M SEP 17 bt2

. l

. l

. Mr. James G. Keppler September 14, 1982 EF2-58409 Page Two The Stop Work Order was issued the morning of September 13, 1982.

We expect items 2, 3 and 5 to be completed by September 20, 1982 and would then resume cab'; pulling with daily surveillance provided by Edison's QA personnel until assured that the program is working properly. Itam 4 will be completed by October 4,1982.

Very truly yours, WJF/jk cc: Mr. Bruce H. Little, Sr. Resident Inspector U.S. Nuclear Regulatory Commission 6450 North Dixie Highway Newport, Michigan 48166 Document Control - EF2 Site 1