TENNESSEE VALLEY AUTHORITY CH ATTANOOGA. TENNESSEE 374ot 400 Chestnut Street Tower II November 23, 1982 Director of Nuclear Reactor Regulation Attention:
Ms. E. Adensam, Chief Licensing Branch No. 4 Division of Licensing U.S. Nuclear Regulatory Commissicn Washington, D.C.
20555
Dear Ms. Adensam:
In the Matter of
)
Docket Nos. 50-327 Tennessee Valley Authority
)
50-328 Enclosed is the basis for our request to perform a short duration integrated leak rate test (Type A) at our Sequoyah Nuclear Plant. The short duration test will be performed in accordance with the enclosed Bechtel Topical Report NB-TOP-1, Revision 1 dated November 1, 1972,
" Testing Criteria for Integrated Leakage Rate Testing of Primary Containment Structures for Nuclear Power Plants." We understand that use of this topical report has been previously approved by NRC. Use of this topical report will not require any FSAR or technical specification changes. Please provide your response to this request as soon as possible in order for this test to be scheduled for Sequoyah Nuclear Plant unit 1 operations.
If you have any questions concerning this matter, please get in touch with J. E. Wills at FTS 858-2683 Very truly yours, TENNESSEE VALLEY AUTHORITY L. H. Mills, nager Nuclear Licensing ubse gr before me Sworn o this_
of, //#3v, 1982 Not,argublic' My Cotimission Expires ff Enclosure h
cc:
U.S. Nuclear Regulatory Commission Region II Attn:
Mr. James P. O'Reilly, Regional Administrator 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303
~
8211300173 821123 i
PDR ADOCK 05000327 P
t
.PDR t Equal Opportumty Employer
.j
TENNESSEE VA' LEY AUTHORITY CHATTANOOO* *ENNESSEE 37401 400 Chestnut Street Tower II November 23, 1982 Director of Nuclear Reactor Regulation Attention:
Ms. E. Adensam, Chief Licensing Branch No. 4 Division of Licensing U.S. Nuclear Regulatory Commission Washington, D.C.
20555
Dear Ms. Adensam:
In the Matter of
)
Docket Nos. 50-327 Tennessee Valley Authority
)
50-328 Enclosea is the basis for our request to perform a short duration integrated leak rate test (Type A) at our Sequoyah Nuclear Plant. The short duration test will be performed in accordance with the enclosed Bechtel Topical Report NB-TOP-1, Revision 1 dated November 1, 1972,
" Testing Criteria for Integratec Leakage Rate Testing of Primary Containment Structures for Nuclear Power Plants." We understand that use of this topical mport has been previously approved by NRC. Use of this topical report will not require any FSAR or technical specification changes. Please provide your response to this mquest as soon as possible in order for this test to be scheduled for Sequoyah Nuclear Plant unit 1 operations.
If you have any questions concerning this matter, please get in touch with J. E. Wills at FTS 858-2683 Very truly yours, TENNESSEE VALLEY AUTHORITY
(
L. M. Mills, Manager Nuclear Licensing Sworn and subscr before me t hi.
day of 1982
[
Notar Public
/
Hy ct5mmission Expires f/hjfp i
Enclosure cc:
U.S. Nuclear Regulatory Commission Region II Attn:
Mr. James P. O'Reilly, Regional Administrator 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303 An Equal Opportunity Employer
TENNESSEE VALLEY AUTHORITY CH ATTANOOG A. TENNESSEE 37401 400 Chestnut Street Tower II November 23, 1982 Director of Nuclear Reactor Regulation Attention:
Ms. E. Adensas, Chief Licensing Branch No. 4 D111sion of Licensing U.S. Nuclear Regulatory Commission Nashington, D.C.
20555
Dear Ms. Adenream:
In the Matter of
)
Docket Nos. 50-327 Tennessee Valley Authority
)
50-328 Enclosea is the basis for our request to perform a short duration integmtea leek rate test (Type A) at our Sequoyah Nuclear Plant. The short duration test will be performed in accorcance with the enclosea Bechtel Topical Report NB-TOP-1, Revision 1 cateo November 1, 1972,
" Testing Criteria for Integratec Leakage Rate Testing of Primary Containment Structures for Nuclear Power Plants." Ne underst nd that use of this topical report has been previously approved by NRC. Use of this topical mport will not require any PSAR or technical specification changes. Please provide your response to this request as soon as possible in order for this test to be scheduled for Sequoyah Nuclear Plant unit 1 operations.
If you have any questions concerning this matter, please get in touch with J. E. Wills at FTS 858-2683 Very truly yours, TENNESSEE VALLEY AUTHORITY l.
L. M. Mills, bger Nuclear Licensing Sworn to and subsc bed before me th
- 3Lby of N,
1982 N
Nots $ Publio "
(/
My Commission Expires i /
Enclosure co:
U.S. Nuclear Regulatory Comunission Region II Attn:
Mr. James P. O'Reilly, Regional Administrator 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303 An Equal Opportunity Employer
\\