ML20027E506
| ML20027E506 | |
| Person / Time | |
|---|---|
| Site: | Sequoyah |
| Issue date: | 09/16/1982 |
| From: | Kammer D TENNESSEE VALLEY AUTHORITY |
| To: | James O'Reilly NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| Shared Package | |
| ML20027E496 | List: |
| References | |
| NUDOCS 8211150440 | |
| Download: ML20027E506 (3) | |
Text
-
e w
g,39@NNESSEE VALLEY AUTHORITY p,TL ANTA.inMNOOGA, TENNESSEE 374o1 400 Chestnut Street Tower II NO September 16, 1982 32 $[P 'll U.S. Nuclear Regulatory Comission Region II Attn:
Mr. James P. O'Reilly, Regional Administrator 101 Marietca Street, Suite 3100 Atlanta, Georgia 30303
Dear Mr. O'Reilly:
SEQUOYAH NUCLEAR PLANT UNITS 1 AND 2 - NRC-0IE REGION II INSPECTION REPORT 50-327/82-18, 50-328/82 RESPONSE TO VIOLATION The subject OIE inspection report dated August 20, 1982 from D. M. Verrelli to H. G. Parris cited TVA with one Severity Level IV Violation. Enclosed is our response to the subject inspection report.
If you have any questions, please get in touch with R. H. Shell at FTS 858-2688.
{
To the best of my knowledge, I declare the statements contained herein are complete and true.
Very truly yours, TENNESSEE VALLEY AUTHORITY h
D. S. Kammer Nuclear Engineer Enclosure cc:
Mr. Richard C. DeYoung, Director (Enclosure)
Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Washington, D.C.
20555
~ 8211150440 821029 PDR ADOCK 05000327 O
PDR An Equal Opportunity Employer
V s
RESPONSE - NRC INSPECTION REPORT NOS.
50-327/82-18 AND 50-328/82-18 D. M. VERRELLI'S LETTER TO H. G. PARRIS DATED AUGUST 20, 1982 327/82-18-01 and 328/82-18-01 10 CFR 50, Appendix B, Criterion V" requires that activities affecting quality shall be accomplished in accordance with instructions, procedures or drawings. Paragraph 17.2.5 of TVA-TR75-1 " Quality Assurance Program Description," the licensee's approved quality assurance. program, states that procedures, instructions, and drawings shall be developed to prescribe those activities that affect the safety-related function of critical systems, instructions, and components (CSSC).
Contrary to the above, activities affecting the safety-related function of CSSC were not accomplished in accordance with drawings in that on July 12, 1982 it was determined that 10-amp control power fuses were installed in the control circuit of the B train Control Room Emergency Pressurization Fan instead of 1-amp fuses as designated in drawing 45N779-21 R-14.
The improperly sized fuses caused a minor component failure which resulted in a prolonged unavailability of the fan and two small fires in a safety-related switchboard.
This is a Severity Level IV Violation (Supplement I.D.2.).
This violation applies to both units.
1.
Admission or Denial of the Alleged Violation TVA admits the violation occurred as statsd.
2.
Reasons for the Violation if Admitted At 1325 on July 8,1982, after initiation of the control room emergency ventilation system, the control transformer to the control building emergency pressurizer fan failed causing a trip of the 1B1-B control and auxiliary vent board. On July 12, 1982, a replacement control transformer was installed, but this trans-former also shorted following energizing the fan. Investigation discovered a defective relay in the fan control circuit. Further investigation revealed a 10-amp fuse was installed in the control transformer, but the drawing required a 1-amp fuse. Installation of the improperly-sized fuse has been attributed to personnel
~., ~
7 x,
. i error during construction installation for the first failed trans-former. Since the 10-amp fuse did not fail in the first trans-former, maintenance personnel did not refer to the drawing for required fuse size. This resulted in the second transfomer failure.
3 Corrective Steps Which Have Been Taken and the Results Achieved A nameplate has been installed at the control transformer stating to use a 1-amp ruse. A spot-check of other control transformers was performed to ensure all had the correct size fuses installed.
4.
Corrective Steps Which Will Be Taken to Avoid Further Violations A program has begun to check all fuses protecting safety-related equipment against the controlled as-constructed drawings to ensure proper sizing of all fuses. Nameplates will also be installed alongside each fuse box indicating the correct fuse size.
5.
Date When Full Compliance Will Be Achieved Full compliance was achieved on July 12, 1982 when the correct size fuse was installed in the transformer to the control building emergency pressurizer fan. The program of checking safety-related equipment fuses against the drawings and installing nameplates will be completed by July 1, 1984.
f p
a
%.-~
6.,.e...
u -
. - - =
e