ML20027A340

From kanterella
Jump to navigation Jump to search
Repts That Final Rept Which Was to Be Transmitted 780801 Has Been Delayed Due to Longer Analysis by Portland Cement Assoc of Low Strength Concrete Test Cylinders.Rept Should Be Available 780930
ML20027A340
Person / Time
Site: Wolf Creek 
Issue date: 08/15/1978
From: Koester G
KANSAS GAS & ELECTRIC CO.
To: Seidle W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
Shared Package
ML20027A334 List:
References
NUDOCS 7811160189
Download: ML20027A340 (1)


Text

,

~

jf\\

{

~

l

  • KANSAS GAS AND ELECTRIC COMPANY

,, ~,

j l- - - !

g coc== t.aocarc=

9tu August 15, 1978 hv l'

in Mr. W.C. Seidle, Chief U

Reactor Construction and Engineering Support Branch U.S. Nuclear Regulatory Co:rmission Region IV 611 Eyan Pla:a Drive, Suite 1000 Arlington, Texas 76011 j

Subject:

Interim Report - Investigation of Low Strength 90-day Concrete Test cylinders 50-482

Dear Mr. Seidle:

In the sheet report transmitted with my letter of May 25, it

^

was. indicated that a final report would be completed by August 1, 1978.

An extensive testing program has been coc:pleted for some time now, but it is taking our censultants (Portland Cement Assoc.)

Icnger to analyze the data and prepare their findings than we anticipated. It now appears the report will not be available before the end of September.

j Please advise if you need additional information.