__
DlDA/RYLAND h
[k COOPERAT/VE
- P.O. BOX 817 2615 EAST AV SOUTH LA CROSSE WISCONSIN M601 (608) 788 4 000 August 16, 1983 In reply, please refer to LAC-9253 DOCKET NO. 50-409 Office of Management Information and Program Control U. S. Nuclear Regulatory Commission Washington, D. C.
20555
SUBJECT:
DAIRYLAND POWER COOPERATIVE LA CROSSE BOILING WATER REACTOR (LACBWR)
PROVISIONAL OPERATING LICENSE NO. DPR-45 MONTHLY OPERATING DATA REPORT FOR JULY,1983
Reference:
(1) DPC Letter, Linder to Office of Management and Program Control, LAC-9249, dated August 10, 1983 Gentlemen:
Reference 1 stated that significant Mechanical Maintenance Department items performed during the July 1983 reporting period would be submitted in a supplementary report. Enclosed is the Mechanical Maintenance listing for the month of July,1983.
Please contact us if there are any questions concerning this report.
Very truly yours, DAIRYLAND POWER COOPERATIVE
.WI Frank Linder, General Manager FL:LSG:eme cc:
J. G. Keppler, Dir., NRC-DRO III NRC Resident Inspector WP-6.8 P309080165 830816 PDR ADDCK 05000409 Qd R