Notice of Violation from Insp on 830515-0630
ML20024E635
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 07/25/1983
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20024E633 List:
References
50-498-83-11, 50-499-83-11, NUDOCS 8308160261
Download: ML20024E635 (1)


Text

.

APPENDIX A NOTICE OF VIOLATION Houston Lighting & Power Company Dockets:

50-498/83-11 South Texas Project, Units 1 and 2 50-499/83-11 Permits:

CPPR-128 and 129 Based on the results of an NRC inspection conducted during the period of May 15-June 30, 1983, and in accordance with the NRC Enforcement Policy (10 CFR Part 2, Appendix C), 47 FR 9987, dated March 9, 1982, the-following vinlation was identified:

Inadequate Procedures / Instructions Criterion V to Appendix B of 10 CFR Part 50, states, " Activities affecting quality shall be prescribed by documented instruction, procedures, or drawings, of a type appropriate to the circumstances and shall be accomplished in accordance with these instructions, procedures or drawings."

Contrary'to the above, Specification for Concrete Construction 2A010CS0028

,^

and Construction Procedure CSP-4 Concrete Placement do not adequately address the placing of concrete on a sloping surface or the free-form method. On June 3,1983, Concrete Placement 1-RC-W-210-013/CSI-R10 was placed by the free-form method and the craft (finishers, vibrators) involved had insufficient experience and no apparent instruction prior to this placement and type method used.

This is a Severity Level V Violation.

(Supplement II.E) (50-498/8311-01)

Pursuant to the provisions of 10 CFR 2.201, Houston Lighting and Power Company is hereby required to submit to this office, within 30 days of the date of this Notice, a written' statement or explanation in reply, including:

(1) the corrective steps which have been taken and the results. achieved; (2) corrective steps which will be taken to avoid further violations; and (3) the date when full compliance.will be achieved.

Consideration may be given to extending your response time for good cause shown.