ML20024D907

From kanterella
Jump to navigation Jump to search
Forwards IE Const Appraisal Team Insp Rept 50-397/83-29 on 830516-27 & 0606-22,executive Summary & Potential Enforcement Findings
ML20024D907
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 07/26/1983
From: Deyoung R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
To: Mazur D
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
Shared Package
ML20024D908 List:
References
NUDOCS 8308080412
Download: ML20024D907 (7)


See also: IR 05000397/1983029

Text

JUL 2 61983

Docket No. 50-397

Washington Public Power Supply System

ATTN: Mr. D. W. Mazur, Managing Director

P.O. Box 968

Richland, Washington 99352

Gentlemen:

SUBJECT: Construction Appraisal Inspection 50-397/83-29

This refers to the Construction Appraisal Inspection by the Office of Inspec-

tion and Enforcement (IE) on May 16-27 and June 6-22, 1983, at the Washington

Nuclear Plant Number 2 (WNP-2) site and your Richland offices. The Construc-

tion Appraisal Team (CAT) was composed of members of IE, Region V, and a number

of consultants. The inspection covered construction activities authorized by

NRC Construction Permit CPPR-93.

This inspection is the third of a series of construction appraisal inspections

being planned by the Office of Inspection and Enforcement. The results of

these inspections will be used to evaluate implementation of management control

of construction activities and the quality of construction at nuclear plants.

The enclosed report identifies the areas examined during the inspection.

Within these areas, the effort consisted of detailed inspection of selected

hardware subsequent to Quality Control inspections, a comprehensive review of

selected portions of your Quality Assurance Program, examination of procedures

and records, observation of work activities and interviews with management and

other personnel.

Appendix A to this letter is an Executive Summary of the results of this

inspection and of conclusions reached by this office. The NRC CAT noted no

pervasive breakdown in meeting construction requirements in the samples of

installed hardware inspected by the team. However, deficiencies in installed

hardware were noted by the NRC CAT which indicate a need for increased manage-

ment attention to the WNP-2 Quality Verification Program. These deficiencies

include the areas of concrete reinforcement steel placement, mechanical equip-

ment installation, the as-built inspection program, weld repairs, and other

detailed deficiencies discussed in the attached report. An indication that

prompt management attention is being given to the identified deficiencies is

contained in the submittal provided to the NRC dated July 15, 1983 entitled,

" Nuclear Project 2 Construction Assessment Team Issues".

8308080412 830726

PDR ADOCK 05000397

IE01

0

PDR

Copy to RCPB, IE

.

. _ .

-

.

.

.

.. -

-

--

__

-

JUL 2 61983

Washington Public Power Supply System

-2-

Appendix B to this letter contains a list of potential enforcement actions

based on the NRC CAT inspector observations. These have been referred to tne

Region V office for review and necessary actions.

In accordance with 10 CFR 2.790(a), a copy of this letter and the enclosures

will be placed in the NRC Public Document Room unless you notify this office,

by telephone, within 10 days of the date of this letter and submit written

application to withhold information contained herein within 30 days of the

date of this letter. Such applications must be consistent with the

requirements of 10 CFR 2.790(b)(1).

No reply to this letter is required at this time.

NRC Region V will address

the potential enforcement findings at a later date and any required response

will be addressed at that time.

Should you have any questions concarning this inspection, please contact us or

the NRC Region V office.

Sincerely,

. Original signeW.

R. C. Dave"'"?

Richard C. DeYoung, Director

Office of Inspection and Enforcement

Enclosures:

1.

Appendix A - Executive Summary

2.

Appendix B - Potential Enforcement Findings

3.

Inspection Report 50-397/83-29

1

4

9

$

W

f

c

W8""* RCPB:QASIP:IE RCP :QASIP:IE RCPB:QASIP:IE RCPB:QASIP:IE DI -

IE DI

r

'

RDM d

'g

""*" HWong/vjj

KHerring

RRohrbacher

RHei

JTz

1 or

07/ phman

War /n

07/gf/83

07/;ff83

07/45/83

p g83

07)

83

07/p/83

-

.

.

.-

.

--

APPENDIX A

EXECUTIVE SUMMARY

An announced Construction Appraisal Team (CAT) inspection was performed at the

WNP-2 site during the period May 16-27, 1983 and June 6-22, 1983.

OVERALL CONCLUSIONS

It is the position of the Construction Appraisal Team that the results of this

inspection indicate several construction program weaknesses.

NRC Region V has

been made aware of these weaknesses and is pursuing them with licensee manage-

ment.

The licensee is initiating corrective action and/or continuing efforts

to resolve the identified concerns. An indication that prompt management

attention is being given to the identified deficiencies is provided in the

submittal provided to the NRC by the licensee dated July 15, 1983 entitled,

" Nuclear Project 2 Construction Assessment Team Issues."

The identified construction program weaknesses are as follows:

(1) The "as-built" program for piping and supports, while identifying a number

of hardware deficiencies does not appear completely effective in that the

NRC CAT findings indicate additional deficiencies, some of which are

considered significant.

In addition, the subsequent audit conducted by

the licensee of a larger sample found essentially the same types of

deficiencies as those identified by the NRC CAT inspectors.

(2) The reinforcing steel placement deficiencies identified during the

inspection indicate questionable conditions which require additional

destructive examination or analysis to determine the effects on the

structures.

(3) Several wel-is were identified that appeared to the NRC CAT inspectors to

have linear type root indications which were not in accordance with code

requirements.

In addition, weld repairs were not controlled to ensure

that the proper areas were repaired and that the repairs were adequately

performed.

(4) Mechanical equipment deficiencies identified during the inspection indi-

cate questionable bolting installation and control of parts.

i-

In summary, the identified weaknesses require increased attention by management

at all levels to assure completed installations meet design requirements.

AREAS INSPECTED AND RESULTS

,

Electrical and Instrumentation Construction: Activities in the electrical and

'

instrumentation construction areas appear to be adequate. Although deviations

from requirements were observed in QC accepted hardware, these were isolated

and not considered repetitive in nature.

The existing program for inspection of electrical raceway does not appear

completely adequate to verify that redundant cable trays are installed in

accordance with the applicable separation criteria.

j

,

A-1

d_

The review of records associated with the corrective action system and several

deficiencies observed in battery and instrument rack hardware, indicate that

the applicants startup and test work activities in that area were ineffectively

controlled by the existing quality control program.

Mechanical Construction:

Deficiencies identified by the NRC CAT and subsequent

licensee / contractor inspections indicate that some pipe and pipe support /

restraint deficiencies have not been identified by previous as-built programs.

Quality Class II, Seismic Class I supports / restraints significantly deviate

from design drawings and are not included in the as-built program.

Expansion

anchor bolts for pipe supports appear to be adequately installed.

Significant

deficiencies were identified in the area of installation of fasteners and other

mechanical equipment. The deficiencies involve:

foundation bolts for

non-rotating equipment; bolting torques for rotating and non-rotating equip-

ment; control of materials and parts for roechanical equipment; and the absence

of visible marking and traceability records on the RPV holddown studs. The

HVAC systems appeared to have been constructed in accordance with requirements

except for minor discrepancies in installed hardware.

Welding / Nondestructive Examination: Several hardware problems were identified

relating to welding /NDE activities. Welder qualifications and vendor radio-

graphic film appear to conform to requirements. Weaknesses were identified in

the onsite welding inspection and NDE program. Areas requiring evaluation

and/or corrective action are: (1) weld repairs, (2) identification of linear

type root indications in piping welds, (3) weld surface preparation for perfor-

mance of liquid penetrant tests and (4) proper weld reinforcement on

weld-o-lets.

Civil and Structural Construction:

There is not reasonable assurance that the

reinforced concrete members and structures were constructed in conformance with

design requirements. This conclusion is supported by the findings that rebar

placement deficiencies were identified in 10 of 12 examined locations, inspec-

tion records and NCR dispositions were found in a number of cases to be erro-

neous, and the accuracy of the design drawings with regard to associated design

calculations is questionable. Structural steel installations appear to be

satisfactorily assembled except for some deficiencies in structural steel

welding. These deficiencies include undersized fillet welds on containment

penetration stiffeners. The structural steel reverification program may not be

adequately justified when considering that allowed weld deviations and critical

connections were not considered in the analysis.

Material Traceability, Storage, and Maintenance:

Procurement, onsite storage

and maintenance were found to be generally acceptable. Material traceability

of steel, weld filler material, mechanical equipment and electrical components

was consistent with requirements, however, problems were identified in the area

of fastener traceability. Specifically, improper or uncontrolled material

substitutions was noted with respect to fastener quality on pipe flanges, valve

bonnets, mechanical connections and pump couplings.

QC Inspector Effectiveness:

Interviews were held with 43 inspectors randomly

selected from contractors on the construction site. There were no instances of

intimidation or threats reported.

A-2

.

Quality Assurance: Selected portions of the QA program were reviewed. A

program of formal audit and surveillance was in place to monitor construction

activities and measuring and test equipment was controlled. Weaknesses were

identified in Quality Control for work performed during the Test and Startup

Phase.

In this area, these weaknesses included:

inspectors were not free from

schedular requirements in some cases; some inspector qualifications did not

appear to meet Supply System commitments; the program did not ensure that

deficiencies were corrected; and in some cases the corrective actions were not

documented and the records properly maintained.

i

,

A-3

.__

..

.

_

. _ _ _ - .

.

_ _ _ _ . . _ _ . . _ . _ . _

. ._

. _ . . . , _ _

APPENDIX B

POTENTIAL ENFORCEMENT FINDINGS

As a result of the CAT inspection of May 16-27 and June 6-22, 1983, the

items have been referred to NRC Region V as potential enforcement

following(Section references are to the detailed portion of the Inspection

findings

Report).

Mechanical Construction

1.

Contrary to 10 CFR 50, Appendix B, Criteria II, III and XVI; and FSAR

Sections 17.1.1.2, 17.1.1.3 and 17.1.1.16; Quality Class II/ Seismic

Category I piping supports have in some cases not been constructed and

inspected to sufficient quality standards to provide assurance of their

structural integrity commensurate with their importance to safety.

(Sections III.B.2 and 3)

2.

Contrary to 10 CFR 50, Appendix B, Criteria X and XVI, and FSAR Sections

17.1.1.10 and 17.1.1.16, the applicant's "as-built" verification program for

Quality Class I piping and supports has not successfully provided for

the identification of discrepancies between design, drawings and in-situ

configurations. Although relatively minor, the number of discrepancies

found is indicative that the program has not fully achieved its objective.

(SectionIII.B.3)

3.

Contrary to 10 CFR 50, Appendix B, Criteria III, VIII, X, and XV; and FSAR

Sections 3.9, 17.1.1.2, 17.1.1.3, 17.1.1.8, 17.1.1.10 and 17.1.1.15; the

design and installation of mechanical equipment has not been adequately

controlled to provide assurance of their structural adequacy and function

under all postulated operating and design basis events. The NRC CAT

examinations indicated lack of bolt torquing control, failures of bolting

to sustain specified torque values, installation procedures inadequate

with regard to certain bolting, and inadequate control of fastener instal-

lation.

(Sections III.B.6 and 7 and VI.B.1)

Welding and Nondestructive Examination

1.

Contrary to 10 CFR 50, Appendix B, Criteria II and X; and FSAR Section

17.1.1.2 and 17.1.1.10; several examples were noted where licensee exami-

nations and inspections did not result in the identification of rejectable

defects in radiographic film, insufficient weld reinforcement for

weld-o-lets, and rejectable liquid penetrant (PT) indications.

(Sections

IV.B.1, 4, and 5)

2.

Contrary to 10 CFR 50, Appendix B, Criteria V, X, and XVI; and FSAR

Section 17.1.1.2, 17.1.1.5, 17.1.1.10, and 17.1.1.16; examples were noted

where corrective actions and inspection activities were not adequate to

provide assurance that piping weld repairs were properly made. (Section

IV.B.4)

B-1

Civil and Structural Construction

1.

Contrary to 10 CFR 50, Appendix B, Criteria III, X and XVI; and FSAR

Section 3.8, 17.1.1.2, 17.1.1.3, 17.1.1.10 and 17.1.1.16, several cases

were noted where design controls and inspection activities were not

sufficient to provide assurance that reinforcement steel placement is in

accordance with the ACI 318-71 Code and design requirements. The NRC CAT

inspection of a sample of concrete structures indicated inadequate rebar

placement not noted in inspection records, inadequate NCR and RFI disposi-

tions, and design drawings not conforming with design calculations.

(Section V.B.2)

2..

Contrary to 10 CFR 50, Appendix B, Criterion I; and FSAR Section 17.1.1.1;

the civil / structural organization provided several erroneous NCR disposi-

tions which had nonetheless received all appropriate checker / supervisory

approvals.

(Sections V.B.2 and 4, and VI.B.1)

Quality Assurance

1.

Contrary to 10 CFR 50, Appendix B, Criterion XVI and FSAR Chapter 17.1.1.2

controls in the Test and Startup Organization were inadequate to ensure

that deficiencies, identified in sebcontractor inspection reports, were

in fact corrected.

(Sections II.B.11 and VIII.B.2.d)

2.

Contrary to 10 CFR 50, Appendix B, Criterion I and FSAR Chapter 17.1.1.2

centrols were not established in the Test and Startup Organization to

insure that QC inspections were performed by individuals who were indepen-

dent from schedular responsibility.

(SectionVIII.B.2.d)

t

B-2

_

. - . - - .

--

-

.

. - - _

- - - . _ _

. - _ .

-.