Text
i I
Omaha Public Power District 1623 Harney Omaha. Nebraska 68102 l
402/536-4000 July 22, 1983 LIC-83-177 j
Mr.
H.
R.
Denton, Director i
U.
S.
Nuclear Regulatory Commission
(
Of fice of Nuclear Reactor Regulation Washington, D.C.
20555
Reference:
Docket No. 50-285 l
Dear Mr. Denton:
Fort Calhoun Station Unit No. 1 Updated Safety Analysis Report (USAR)
As required by 10 CFR 50.71(e), thirteen (13) controlled copies (numbered 1 through 13) of the " Fort Calhoun Station Unit No. 1 Updated Safety Analysis Report" have been for-warded under separate cover.
The annual update encompasses revisions from January 22, 1982 through January 22, 1983.
l The update was performed to incorporate all plant modifi-cations made to the Fort Calhoun Station and to reflect information and analyses submitted to the Commission since the previous submittal of the USAR.
All changes to the USAR received a rigorous technical review, as well as a formal final review and approval by the District's Plant Review Committee.
Based upon this review and approval process, the District believes the USAR accurately reflects the design of the Fort Calhoun Station as it existed January 22, 1983.
There have been no changes made under the provisions of 10 CPR 50.59 which have not previously been submitted to the Commission.
l Sinc, rely, b
(
Divis({ Jones W.
C.
8309030063 830722 bn Manager PDR ADOCK 05000285 Production Operations K
PDR WCJ/DJM:jmm cc:
LeBoeuf, Lamb, Leiby & MacRae 2
1333 New Hampshire Avenue, N.W.
Washington, D.C.
20036
}O Mr.
E.
G.
Tourigny, Project Manager i
Mr.
L.
A.
Yandell, Senior Resident Inspector Employment with Equal Opportunity 4s si24 maielremale I
r
_