ML20024C212

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-298/83-10 on 830427-29,0504-13 & 23-27.No Noncompliance Noted.Major Areas Inspected:Inservice Insp, Actions Taken in Response to IE Bulletin 83-02 & Review of Evaluation & Repair of Mark I Mods
ML20024C212
Person / Time
Site: Cooper Entergy icon.png
Issue date: 06/16/1983
From: Hunnicutt D, Tomlinson D, Westerman T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20024C203 List:
References
50-298-83-10, IEB-83-02, IEB-83-2, NUDOCS 8307120414
Download: ML20024C212 (7)


See also: IR 05000298/1983010

Text

.

_ _ _ - _ _ _ _ _ _ _ _

.

APPENDIX

U. S. NUCLEAR REGULATORY COMMISSION

REGION IV

Report: 50-298/83-10

License: DPR-46

Docket: 50-298

Licensee: Nebraska Public Power District (NPPD)

.P. O. Box 499

Columbus, Nebraska 68601

Facility Name: Cooper Nuclear Station

Inspection At: Cooper Nuclear Station, Nemaha County, Nebraska

Inspection Conducted: April 27-29, May 4-13, and May 23-27, 1983

Inspectors

k

M

///4/8.3

D. P. Tomlinson, Reactor Inspector

Ddte /

Engineering Section

Approved:

f//

E#

t//4/83

D. M. Hunnicutt, Chief

Date'

Engineering Section

$ $ in

&

S//6f25

-T.lestermati, Chief / ' A

Date

Reactor Project Section

Inspection Summary

Inspection Conducted April 27-29, May 4-13, and May 23-27, 1983 (Report 50-298/83-10)

Areas Inspected: Routine, unannounced inspection of activities related to

inservice inspection, actions taken as a result of IE Bulletin 83-02, and a

review of the evaluation and repair of Mark I modifications. The inspection

involved 129 inspector-hours ensite by one NRC inspector.

Results : Within the three areas inspected, no violations or deviations were

Tdintified.

8307120414 830617

PDR ADOCK 05000298

(D

PDR

l

-2-

DETAILS

1.

Persons Contacted

Principal Licensee Employees

  • P. Thomason, Station Superintendent
  • V. L. Wolstenholm, Quality Assurance Supervisor

W. Rushton, Engineering Supervisor

D. Torczon, Quality Assurance Specialist

M. Henry, Quality Assurance Engineer

General Electric (GE)

R. Hooper, Field Engineer

M. Williams, Field Engineer

G. Craigo, Field Engineer

M. Heath, Inspector Level III

J. Briggs, Inspector Level III

E. Secko, Inspector Level III

Others

M. Basford, Nuclear Power Consultants, Inc.

E. Hartnett, EDS Nuclear, Site Project Manager

  • D. DuBois, Region IV Resident Reactor Inspector
  • Indicates those attending the exit interview on May 13 and May 27,-1983.

2.

Inservice Inspection

The NRC inspector reviewed six of the ten inspection procedures being

used by GE in the performance of -Inservice Inspection (ISI) during the

current refueling outage. These procedures, covering visual, magnetic

particle, and ultrasonic examinations, contained all of the elements

required by Section XI of the ASME B&PV Code including personnel

qualifications requirements, equipment to be used, acceptable consumable

supplies, examination directions and angles, manual scanning speed,

and reportability requirements. The NRC inspector reviewed the

documentation for three calibration standards used for the inspection

of 10" Schedule 140 stainless steel piping, 12" Schedule 140 carbon steel

,

piping, and 16" Schedule 80 carbon steel piping.

Records indicate

1

that each standard was fabricated of the proper material, each was

certified to the proper material grade or heat treat condition, and

the heat number of each was traceable to an acceptable certified

.

-

.

-3-

material test report (CMTR). The personnel qualification records

for ten of the GE inspectors were reviewed to assure that the

minimum experience, time, and educational requirements of ASNT TC-1 A

for each inspector level had been met.

The NRC inspector accompanied one inspection team and observed the

visual and ultrasonic inspection of six welded joints on three

supports. All six welds were acceptable visually in that each was of

the proper size, configuration, and contour.

Anomolies such as

undercut, porosity, and lack of penetration were not noted on any

of the welds. The ultrasonic inspection revealed that minor slag

inclusions were present in two welds but were not of sufficient size

or number to be a cause for rejection. These slag inclusions were

reported to NPPD.

The NRC inspector randomly selected and reviewed the records for

the ultrasonic examination of ten welded joints.

Each record package

noted the names and certification levels of those performing the

inspections. The instrument used, the transducer size and frequency,

inspection angles, and the location of recordable indications

were recorded on each inspection sheet. The records of the total

inservice inspection could not be reviewed, as this activity was still

in progress at the end of this inspection period. These records will

be reviewed during a subsequent inspection.

No violations or deviations were identified during this portion of

the inspection.

3.

Actions Taken as a Result of IE Bulletin (IEB) 83-02

As a result of IEB 83-02, an inspection has begun on the stainless steel

recirculation and residual heat removal piping to determine the

existence and extent of intergranular stress corrosion cracking (IGSCC).

Two GE inspection teams and an NPPD observer attended a qualification

and certification session at the EPRI NDE Center in Charlotte, North

Carolina. The purpose of this session was to demonstrate for NPPD and

NRC that the GE procedure, equipment, and personnel are capable, as a

unit, of locating and dimensioning IGSCC. Six GE inspectors and two

ultrasonic instruments were certified at this time, utilizing selected

samples of piping from Nine Mile Point containing known cracks.

Criteria for certification included crack identification and

dimensioning with strict adherence to the parameters.of GE Procedure

MIGSCC-S752, Revision 5.

The NRC inspector reviewed the inspection procedure, the results of

the certification examinations, and the personnel qualification records

for each inspection team member. Due to the limited number of certified

. -

. -

-._ - - -

.

.

_ .

-

- - . . __-

- .

- - -

. -

-.

-

.

4

,

-4-

inspectors and the high radiation levels encountered, the number of

certifications was increased to preclude " burn-out" of available

personnel prior to the completion of this inspection. A verbal

,

agreement was reached between the NRC inspector, NPPD management,

and NRR representatives that onsite certification of additional

,

personnel and equipment could be accomplished, if proficiency in crack

,

detennination and dimensioning was clearly demonstrated to the satis-

faction of the NRC inspector and NPPD management. Utilizing this

,

criterion, six additional inspectors and three additional ultrasonic

instruments were certified. These certifications were based upon

'

the identification of defects during examinations of an onsite sample

of Nine Mile Point piping containing defects known to the NRC inspector

i

and NPPD.

Four. of these inspectors were tested using a remote CRT

instrument commonly known as a " slave scope." Using this technique, a

Level I inspector and the small slave scope are in close proximity with

the weld being inspected, while the Level II or III inspector performs

the actual indication recording and evaluation at a remote location. Both

instruments are calibrated simultaneously to ensure that responses

.

4

to signals are identical and head-set communications ~are maintained

j

throughout the inspections. The most important reason for the slave

.

scope is to limit the exposure to persons performing the examinations.

?

Witnessing of half of the inspection is possible by observing either the

i

slave or evaluation instrument.

The NRC inspector observed calibration operations or equipment

'

calibration verifications on approximately 15 different occasions by

the various teams. The NRC inspector also observed portions of the

.

ultrasonic examination of eleven welded joints in the recirculation

and the residual heat removal (RHR) piping systems. All activities

observed were performed in accordance with procedural requirements.

All plotting and evaluation was accomplished by a certified

Level II or III-inspector. The inspection results, including

indication lengths and depths, were forwarded to GE, San Jose,

,

California, for final evaluation utilizing fracture mechanics and

calculations.

Recommendations are then made as to specific actions

for individual weld joints. At the end of this inspection period,

approximately 90 weld joints had been inspected, with approximately

17 exhibiting IGSCC to varying lengths and depths. GE calculations,

which were incomplete at the time, indicated that four of the areas

,

- exhibiting the worst cracking should be temporarily repaired by

l

weld overlay cladding to restore the pressure boundary. material thickness.

This area will be reviewed during a subsequent inspection.

NPPD has voluntarily committed to inspect 100%.of the recirculation,

RHR, and bypass piping weld joints. This inspection,-along with

a review of inspection records and repairs. performed will be

_

monitored during a future NRC inspection.

. No violations or deviations were identified during this portion of

the inspection.

_

_

_

_ . _ - . ,_ _.

_ _ _ _ .

-

-

.

-5-

4.

Repair of Mark 1 Modifications

On October 11, 1982, NPPD notified Region IV, via correspondence number

LQA8200192, of a potential problem involving steel plate supplied by

Paxton and Vierling Steel Company (PVS). While fabricating parts

for the modification and addition of piping supports, it was noted

that a " thick steel plate contained laminations. Work was immediately

stopped and samples of all PVS steel plating were sent to an independent

testing laboratory (lab) to determine the chemical and physical properties

of each plate. The lab reports stated that four of the samples did

not meet the requirements established for A-36 steel physical properties.

All material supplied by PVS was subsequently quarantined. A

quality assurance audit was performed by NPPD of the PVS facility

which revealed that PVS had no system for positive material traceability.

PVS was immediately removed from the qualified vendors list. NPPD

determined that the nonconforming physical properties test results

would not have any adverse effects on the use of the steel due to

the nature of the nonconformances. NPPD further decided that all

parts fabricated from the laminated steel plate would be removed and

replaced with sound material. The only exceptions to this will be

parts, such as shims, upon which the stress loading is of a

conpressional nature. A total of 85 piping supports were affected

by the addition of one or more pieces of laminated steel. Seventy-five

of these have been or will be modified during the current outage to

remove the laminated plate. The ten remaining supports are considered

suitable for use "as-is" due to the compression-only loading of the

nonconforming material.

Following completion of the original Mark l modifications, an audit

performed by NPPD disclosed that welding by Dravo Utilities Constructors,

Inc. (DUCI) had been performed by welders not qualified in accordance

with the requirements of Section IX of the ASME B&PV Code.

Full pene-

tration groove welds had, in some cases, been perfonned by welders qualified

only for fillet welds. A total of 214 welds on 51 piping supports

fabricated or modified by DUCI were identified as having welds

produced by improperly qualified welders. These numbers represent

welds inside and outside the torus.

Additionally, 12 bracket welds

on 3 torus penetrations, designated as full penetration welds, were

'

l

installed by DUCI with no bevel penetrations and. welded as partial

penetration fillet welds.

One of the 12 welds was removed, the

proper configuration achieved, and a full penetration . weld redeposited.

Problems were encountered during this rework and it was decided to

replace rather than repair the 11 "emaining brackets.

NPPD has

documented these DUCI errors on NCN-2311 and NCR-2623.

This work

was in progress at the end of this report period. The final fabrication,

installation, and inspection records will be reviewed by the NRC

inspector during a subsequent inspection.

No violations or deviations were identified during this portion af

the inspection.

-

\\

.

.

-6-

5.

Exit Interview

The NRC inspector met with licensee representatives (denoted in

paragraph 1) on May 13 and May 27, 1983, to discuss the scope and

findings of this inspection. The NRC resident participated in these

meetings.

.

%

P

1

.

.

.

-____

--

_ _ _ _ _ _ _ _ __

_

._.

..

.__

.

. .

l

M.c,FOR:Me8

U.S. NUCLEAR REGULATORY COMMISSION

Par *C*AL iNSPtCTOa,New est *st aw-w* ar s i

iii ,

' ~ '

"

0

INSPECTOR'S REPORT

l

R E Wil WE R

Of fice of Irispection and Enforcement

ggg,

,g ,3

g

'N 51 E C T O45"Tb' LLt u$t.J.

b A ,a

b

,CT CN

DOCitET NO re a gas,CR LICENSE

"

REPD U

W WW M

LICI NSEt z vt NDOR

NO ig y PRODUCTH13 0.g;ts:

NO

SiO

MO

v4

dNbNb

AM (l,

@

b b O b

b b h b

h 3

\\

Q

^

e

g p g Q C)

~

M - MODIFY

,1

/9[]jgj M i J M Q ' a

( $[,.C \\

D - DELETE

C

y

R - REPLACE

D

i

1

2-

14

15

18

8 ELIOD OF INyt STIGA flON/ INSPECTION

INSPECTION PERFORM (D SY

ORGANilATON CCCE OF REGCN/MO CONDUCT-

FLOM

70

t/1 - REGCNAL OFFICE STAFF

OTHER

_ [

h

'

MO

DAY

VR.

MO

DAY

vm

2 - RESIDENT INSPECTOR

__R E G ON

.

D'CSCN

I

BA^NCH

?l4 1l7 Bl3

Ol5 '). h @b

3 - PERFORMANCE APPR AISAL TEAM

d4

l

d_

b

32

33

1

34

l

35

0

25

26

31

' ' '

<

REGIONAL ACTION

TVPE OF ACTivif Y CONDUCTED ICheck one nos one iv

"" "

~

V' 02 - SAFETY

06 - MGMT. VISIT

10 - PLANT SEC.

14 tNOUIRY

1 - NIC FORM $91

03 - INCIDENT

07 - SPECIAL

11 - INVENT. VER.

15 - INVESTIG ATION

/'2 - KEGIONAL OFFICE LETTER

04 - ENFORCEMENT

08 - VENDOR

12 - SHIPMENT / EXPORT

05 - MGMT. AUDIT

09 - M AT. ACCT.

13 - iM PO R T

35

37 3,

.Nssichv%,.Nw ESIiGATiGN Fi% NG5

TOTAL NUMBER

ENFORCEMENT CONFERENCE

REPORT CONTAIN 2 790

LETTER Of REPO1T TR ANSM:TTAL DATE

eCwm cae t>as onevs

CF VCLATCNS ANO

HELD

INFOR M ATiON

a

C

D

DEvlATONS

i

NRC FORPA $91

REPORYSENT

I~

I^

OR REG

TOMO FOR

LETT E R IS SUED

ACTCN

2 - VIOLATON

l9

C

D

Al8

C

D

A

8

C

D

,,p, [ C Av

VR

VO

DAY l VR

3 - DEVIATION

A

4 - VIOsATCN & DEvtATON

l

l

1 - VES

i - vtS

y [ q }%

l

l l l

'

,

,

,

,

33

40 41' ,.

42 l

43

44

89

50

Sk7

r.-

MODULE INFC AM A TION

MODULE INFORM ATiON

EC

"*C

f

MODULE NUMRER INSP

Og 9

MODULE REO FOLLOWUP

Oltb

MODULE NUMBER NSP

gg g

VODULE REO FOLLOWU*

sg835

e

EE 5 58

e h$$n * 5 =

? _15

r

h$$

s_s!

!s

i

  • !

!s

s

is

!s

.t

c

n!

8s

2 3;n

5 5 :gia:;

y ; a

gi

g

-

s i !a

8i s:f15;st i8e

I

s
s

I 15

s

$5:

8 S~

c3a

!t

8i

ie t

!t

8i

do5

d

15=r2r8e

i: = 5

ti

e

ni

e z 15

s

E

5 3:0l7,0dl2 ' / Cidi 2

liiIe

M i3lcisi315

^ / l iGi c

i i

i

'

Iiii

i

i i

,

i

liil

liil

i i

ii

i

i e

i i

i

liil

IiiI

c

c

s i

i i

i

i i

ii

i

liil

li,I

i i

ii

i

, ,

, ,

i

5 9 2.17, q 3lB ' I c,yl

liiIe

5 7,3lC,T GlE ^ / J,4,c

i ,

l,il

i

i i

i

,

i

i

liil

I,il

'

i i

ii

i

i i

i i

i

Ii,I

liiI

c

c

i i

i ,

,

i ,

ii

i

I,,1

I,,1

o

o

, ,-

, ,

,

, ,

,,

,

c)i 17 ci6le

^ l ci ill

liiie

liil

IiiI

?

i s

^

i

i ,

i

i

i

i i

ii

i

liil

i i

i i

i liii

'

'

i i

, i

i

l

l

C

t i

, i

i

, i

, i

t t

i

, i

Ie il

I,,I

o

o

, i

i i

i

, ,

, ,

,

i s 7i3loi%11B* l oioS

, ,

IiiIe

IiiI^

,

i

i

i ,

i i

i Iiii

!

I,il

liil

'

a

, i

i ,

,

i ,

, ,

i

.__1__1__ __1__1___

____

1 l_ h L __

-

hm

.-

1 ! h l-

_