BOSTON lEDISO N COMPANY BDO BOYLETON STREET 80sTON, MABBACHUSETTs D2199 i WILLIAM D. HARRINGTON May 13,1983 BECo Letter No. 83 122
""5*""
Mr. Domenic B. Vassallo, Chief Operating Reactors Branch #2 Division of Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.
20555 License No. DPR-35 Docket No. 50-293
Subject:
Fire Protection Technical Specification Change Submittal
Dear Sir:
In a telephone conver. cation between Boston Edison and Mr. Eccleston (NRC Project Manager for Pilgrim Station), Boston Edison committed to supply a schedule for changes to Technical Specifications which would address requirements militated by the fire protection issue.
We herein provide a schedule to satisfy that commitment.
Although we expect NRC to issue this as a single amendment, we intend to submit it in segments to facilitate our preparation and your review processes.
The segments and their respective schedules are shown below:
i General Segmentation l
l SECTION 3/4.12 LCO's and Surveillances A.
Detection B.
Fire Water Supply and Distribution C.
Spray / Sprinkler System D.
Fire Hose Stations E.
Halon System F.
Alternate Shutdown Panels A.
DETECTION (SM0KE) o Turbine and Control Building o
Radwaste Control Area o
Reactor Auxiliary Building ( Aux. Bay)
-C)g)j, o
Diesel Generator Building o
Reactor Building o
A.0.G.
This will be submitted December 30, 1983.
8305170173 830513 PDR ADOCK 05000293 F
r COSTON EDI2ON COMPANY Mr. Domenic B. Vassallo, Chief May 131983 Page 2 B.
FIRE WATER SUPPLY AND DISTRIBUTION o
Elec. Pump o
Diesel Pump o
Tanks o
Interior / Exterior Loop and Associated Valves This will be submitted November 15, 1983.
C.
SPRAY / SPRINKLER SYSTEM o
Diesel Generator and Day Tanks Pre-Action System o
Diesel Fire Pump Day Tank o
Auxiliary Boiler Room o
Recire. Pump MG Set Room o
Standby Gas Treatment System i
o Hydrogen Supply 011 Unit o
Turbine Basement Addition This will be submitted November 15, 1983 D.
FIRE HOSE STATIONS o
Reactor Building o
Reactor Aux. Bay o
Turbine Building o
Retention Building o
Radwaste Area o
Diesel Generator Rooms o
Screenhouse o
Switchgear Rooms Elev. 23' and 37' and Stairwell This will be submitted November 15, 1983.
E.
HALON SYSTEM o
Cable Spreading Room (3.1.3 Gas Fire Systems) o Dry Chemical System This will be submitted October 17, 1983.
/
CORTON KDICON CO M PANY e
Mr. Domenic B. Vassallo, Chief May 13,1983 Page 3 F.
FIRE BARRIERS o
Active Dampers Doors o
Passive Penetration Seals This will be submitted September 16, 1983.
G.
ALTERNATE SHUTDOWN PANELS o
Core Spray M0V's o
RBCCW Pump o
HPCI Pump and valves o
RCIC Pump and valves o
ADS Operation o
SSW Pumps This will be submitted July 20, 1983.
We believe this satisfies our commitment to provide a schedule for Fire Protection Technical Specifications.
Should you require further information concerning this submittal, please contact us.
Very truly yours, b
,