Suppls 920131 Response to NRC Bulletin 88-008, Thermal Stresses in Piping Connected to Rcs. Proposes to Complete Required Mods to Install Thermal Relief Valve to Provide Necessary Overpressure Protection During Fall 1994 Outage
ML20012G573
Person / Time
Site: Salem  PSEG icon.png
Issue date: 03/01/1993
From: Labruna S
Public Service Enterprise Group
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
IEB-88-008, IEB-88-8, NLR-N93028, NUDOCS 9303090277
Download: ML20012G573 (3)


Text

.

s Pubhc Service Electnc and Gas Cornpany Stanley LaBruna Pubbc Serv:ce Electnc and Gas Company P.O. Box 236, Hancocks Bndge, NJ 08038 609-339 1200 m r com - wear owu.m MAR 011993 NLR-N93028 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

NRC BULLETIN 88-08 THERMAL STRESSES IN PIPING CONNECTED TO REACTOR COOLANT SYSTEM SALEM GENERATING STATION UNIT NOS. 1 AND 2 DOCKET NOS. 50-272 AND 50-311 By letter dated January 31, 1992 (Ref: NLR-N91210), Public Service Electric & Gas Company (PSE&G) provided a response to address the thermal stress concerns of Bulletin 88-08 resulting from valve leakage.

PSE&G proposed to establish double isolation valves in the Safety Injection lines, and establish flow in the Auxiliary Pressurizer Spray and the Alternate Charging lines.

Prior to implementing the proposed changes, PSE&G committed in this letter to perform an evaluation of the new valve lineups.

PSE&G has completed the evaluations of the new valve lineups.

The proposed change for the Safety Injection lines, double valve isolation, will alleviate the Bulletin 88-08 concerns.

However, I

implementing this change will isolate a section of piping including the Boron Injection Tank with no overpressurization protection.

In order to implement the proposed change, PSE&G will be required to install a thermal relief valve to provide the necessary overpressure protection.

PSE&G will also provide additional administrative controls to monitor the isolated section of Safety Injection piping for under pressure due to thermal contraction.

PSE&G proposes to complete the required modifications during the Salem Unit 2 eighth refueling outage, currently scheduled for the fall of 1994 and during the Salem Unit 1 twelfth refueling outage, currently scheduled for the spring of 1995.

This schedule will allow sufficient time to obtain the required materials necessary to perform the modifications.

l 080112 jg

/ ('

l [j.

9303090277 930301

,/

PDR ADOCK 05000272 G

ppg

d MAR 011933 l

Document Control Desk 2

1 NLR-N93028 The engineering evaluation of the proposed changes to reposition valves to ensure constant flow through the Auxiliary Pressurizer i

Spray and the Alternate Charging lines shows that this change j

would eliminate the Bulletin 88-08 concerns.

However, the evaluation also concluded that additional concerns such as the potential adverse impact on RCS/CVCS/ pressurizer components due to normal operation in this configuration supported the need for an alternate solution.

Therefore, PSE&G is proposing to perform a detailed thermal fatigue evaluation, including postulated valve leakage transients instead of operating with constant flow through these lines.

This fatigue analysis will be based on plant specific conditions to demonstrate a usage factor that will preclude failures.

PSE&G proposes to complete the required analysis by December 31, 1993.

Non-destructive examinations of susceptible welds have been completed during the previous two refueling outages for both t

Unit 1 and Unit 2.

No indications of fatigue related cracks have been found to date.

Until the proposed analysis is completed and modifications installed, PSE&G will continue to conduct non-destructive testing (NDE) on the Safety Injection, Auxiliary Pressurizer Spray and Alternate Charging lines during each refueling outage.

Should there be any questions with regerd to this submittal,

~

please do not hesitate to contact us.

Sincerely,

(

/W r

i t

i b

9 l

d.'3 1

i 1

Document Control Desk 3

NLR-N93028 i

C Mr. J.

C. Stone Licensing Project Manager 4

Mr. T. Johnson Senior Resident Inspector Mr. T. Martin, Administrator Region I 1

Mr. Kent Tosch, Chief New Jersey Department of Environmental Protection j

Division of Environmental Quality J

Bureau of Nuclear Engineering CN 415 l

Trenton, NJ 08625 k

L i

I f

}

1 1

1 b

i

[

!