ML20012D345

From kanterella
Jump to navigation Jump to search
Forwards SSFI Followup Team Insp Rept 50-309/90-80 on 900114-19.Requests Response within 30 Days W/Justification for Listed Electrical Issues Being Resolved in Two Yrs Time & Assurance That No Operability Concerns Exist in Interim
ML20012D345
Person / Time
Site: Maine Yankee
Issue date: 03/15/1990
From: Kane W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Frizzle C
Maine Yankee
Shared Package
ML20012D346 List:
References
NUDOCS 9003270214
Download: ML20012D345 (2)


See also: IR 05000309/1990080

Text

Gj-w[.

~

.

,~

,,

it- ,

.c

/

MAR 151990

,,

Docket No.- 50-309

Maihe Yankee Atomic' Power Company

= ATTN:

Mr. Charles D.

Frizzle, President

83 Edison Drive

Augusta, Maine

04336

Gentlemen:

Subject:

NRC SAFETY SYSTEM FUNCTIONAL INSPECTION FOLLOW-UP TEAM

REPORT NO. 50-309/90-80

This letter forwards the report of a Safety System Functional

Inspection (SSFI) Follow-up performed by an NRC Team from January-

14 through January 19, 1990, at Maine Yankee Station. The Team's

findings and preliminary conclusions were summarized for you and

members of your staff at a meeting held on site on January 19,

1990.

We found that you have invested considerable effort in addressing

individual SSFI Team findings.

This work includes calculational

revisions, component testing to confirm equipment performance,

procedural revisions and drawing changes, and additional training

-of plant staff as needed.

Extensive programs to resolve several

programmatic concerns have been developed and were observed to be

underway. Except for scheduled heat exchanger performance testing,

the design capability of the Component Cooling Water system has

been satisfactorily verified.

We recommend that you continue your evaluation of revised data for

the critical electrical protection issues involving large AC motor

overload protection,

fault protection for the DC buses,

short

circuit analyses for 4160-volt switchgear, and the effects of

multiple diesel generator starts on motor control center load

protection.

Your schedule for completion by the end of the 1991

refueling outage is of some concern to us, since we believe at

least partial corrective actions are possible prior to startup from

the April 1990 refueling outage, particularly regarding operability

concerns for the diesel generators.

Accordingly, we request that you respond in writing within 30 days

with justification for the above electrical issues being resolved

in approximately two years time, and the assurance which you have

that no operability concerns exist in the interim.

Also, your

proposal to administratively allow cross-tie of the DC buses for

up to seven days is, in our estimation, excessive and your safety

basis for this proposal should be addressed in your response.

9003270214 900313

PDR

ADOCK 05000309

o

pnr

9 m

L

[.j -

'

'

et

,

y

.

,

.

e ,s t

,

F

Maine Yankee' Atomic-PoNer Company

7

- We encourage:you towards-upgrading instrument setpoint bases and

' documentation.

We also understand your setpoint open item resolu-

,

tion process incorporates a review of input and assumptions for

both

original' and

newly

formulated

calculations,

and

should

identify- any

safety

concerns

in

order

to

take

appropriate

corrective actions as necessary.

Sincerely,

William F.

Kane, Director

Division of Reactor Projects

Enclosure: As stated

cc w/ encl.

J. Randazza, Assistant Chairman of the Board

J.

Garrity, Vice President, Engineering and Licensing

Dr.

E. Boulette, Vice President, Operations / Plant Manager

P. Anderson, Project Manager

G. Whittier, Manager, Nuclear Engineering and Licensing

J. Ritsher, Attorney (Ropes and Gray)

J.

Firth, Vice President, Public and Governmental Affairs

P. Ahrens,-Esquire

Public Document Room (PDR)

'

Local Public Document Room (LPDR)

Nuclear Safety Information Center (NSIC)

NRC Resident Inspector

State of Maine

!

bec w/ encl:

Region I Docket Room (with concurrences)

l

Management Assistant, DRMA (w/o encl)

W.

Kane, DRP

J. Wiggins, DRP

J. Johnson, DRP

l

E. McCabe, DRP

l'

Team Members and Their Supervisors

L

J.

Dyer, EDO

!

B.

Boger, NRR

fgj

J. Mauch, NRR

conc *

.

.

TSS

DR -

RP

PB3 : DRP

EB :

RS

IR

-

.

E

G Kell

J Johnson

JD

r

JKane

3/[/90

3

/90

3/7/90

3/

/90

3/ti/90

l

b

.

.