Notice of Violation from Insp on 900117-0228.Violation Noted:On 900208,Unit 2 Reached 23% Power W/All Bypass Valves Inoperable & on 900208 & 09,MCPR Value Not Increased,As Required
ML20012C051
Person / Time
Site: LaSalle  
Issue date: 03/09/1990
From: Shafer W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20012C050 List:
References
50-373-90-02, 50-373-90-2, 50-374-90-02, 50-374-90-2, NUDOCS 9003200015
Download: ML20012C051 (1)


Text

_

4 NOTICE OF VIOLATION l

Commonwealth Edison Company Docket No. 50-373 Docket No. 50-374 As a result of the inspection conducted from January 17 through February 28, 1990, and in accordance with 10 CFR Part 2, Appendix C - General Statement of Policy and Procedure for NRC Enforcement Actions (1988), the following violation was identified:

Unit 2 Technical Specification Limiting Condition for Operation 3.7.10.a.2 requires that with reactor power greater than 25% and with less than four operable bypass valves that within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> the Minimum Critical Power Ratio (MCPR) value be increased.

on February 8, 1990, at 9:00 p.m., Unit 2 reactor power Contrary to the above,f the bypass valves inoperable. On February 9,1990, at reached 25% with all c 4:15 a.m., all bypass valves were declared operable after completion of the L

required surveillance testing.

Between 11:00 p.m. on February 8 and 4:15 a.m.

on February 9, the licensee did not increase the MCPR value as required.

(374/90002-01)

This is a Severity Level IV violation (Supplement I).

The inspection showed that action had beer. taken to correct the identified violation and to prevent recurrence. Consequently, no reply to the violation is required and we have no further questions regarding this matter.

MAR 9 1990 t,)

gj Dated W. D. Shafer, Chief Reactor Projects Branch I f,$k3$$ock 3