|
---|
Category:REPORTABLE OCCURRENCE REPORT (SEE ALSO AO
MONTHYEARML20045G6671993-07-0202 July 1993 RO:930702,unusual Event Declared When RCS Calculated Unidentified Leak Rate Exceeded 1 Gpm.Caused by Leakage from Reactor Coolant Pump Seal Injection Filter Drain Valve. Valves Corrected to Eliminate Leak ML20043F2961990-06-0808 June 1990 Special Rept SR-1-90-006-00:on 900509,discovered That Tech Spec Temp Limit for Main Steam Penetration Area Exceeded for Greater than 8 H.Caused by Inadequate Operating Procedure for Safeguards Bldg Ventilation Sys.Pipe Supports Insulated ML20042E5341990-04-16016 April 1990 Special Rept 1-SR-90-005-00:on 900404,positive Moderator Temp Coefficient Noted During Low Physics Testing Due to High Boron Concentration in Moderator.Rod Withdrawal Limits Imposed Per Tech Spec 3.1.1.3a,Action a.1 ML20012D9531990-03-21021 March 1990 Special Rept 1-SR-90-002:on 900221,RCS Pressure Transient Resulted in Automatic Actuation of Pressurizer Porv.Caused by Failure of Procedure to Consider Variation in Plant Response for Stated Sys.Operating Procedure Will Be Revised ML20012B8541990-03-13013 March 1990 Special Rept:On 900312,ESF Actuation Signal Occurred Which Resulted in Initiation of Train a Safety Injection & RCS Pressure Transient.Caused by Failed Blocking Diode Due to Short.Plant Restored to Stabilized Condition ML19309B8571980-03-28028 March 1980 Supplemental Ro:Violation Found Re Piping Min Wall Thickness.Cause Unstated.Engineering Review in Progress. Progress Rept Will Be Submitted by 800418 1993-07-02
[Table view] Category:LER)
MONTHYEARML20045G6671993-07-0202 July 1993 RO:930702,unusual Event Declared When RCS Calculated Unidentified Leak Rate Exceeded 1 Gpm.Caused by Leakage from Reactor Coolant Pump Seal Injection Filter Drain Valve. Valves Corrected to Eliminate Leak ML20043F2961990-06-0808 June 1990 Special Rept SR-1-90-006-00:on 900509,discovered That Tech Spec Temp Limit for Main Steam Penetration Area Exceeded for Greater than 8 H.Caused by Inadequate Operating Procedure for Safeguards Bldg Ventilation Sys.Pipe Supports Insulated ML20042E5341990-04-16016 April 1990 Special Rept 1-SR-90-005-00:on 900404,positive Moderator Temp Coefficient Noted During Low Physics Testing Due to High Boron Concentration in Moderator.Rod Withdrawal Limits Imposed Per Tech Spec 3.1.1.3a,Action a.1 ML20012D9531990-03-21021 March 1990 Special Rept 1-SR-90-002:on 900221,RCS Pressure Transient Resulted in Automatic Actuation of Pressurizer Porv.Caused by Failure of Procedure to Consider Variation in Plant Response for Stated Sys.Operating Procedure Will Be Revised ML20012B8541990-03-13013 March 1990 Special Rept:On 900312,ESF Actuation Signal Occurred Which Resulted in Initiation of Train a Safety Injection & RCS Pressure Transient.Caused by Failed Blocking Diode Due to Short.Plant Restored to Stabilized Condition ML19309B8571980-03-28028 March 1980 Supplemental Ro:Violation Found Re Piping Min Wall Thickness.Cause Unstated.Engineering Review in Progress. Progress Rept Will Be Submitted by 800418 1993-07-02
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217E8021999-10-0707 October 1999 CPSES Unit 1 Cycle 8 Colr ML20217G4151999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Cpses,Units 1 & 2 ML20212F7671999-09-24024 September 1999 SER Granting Relief Request C-4 Pursuant to 10CFR50.55a(g)(6)(i) for Unit 2,during First 10-year ISI Interval & Relief Requests B-15,B-16 & B-17 Pursuant to 10CFR50.55a(g)(6)(i) ML20216J5701999-09-16016 September 1999 Rev 2 to CPSES Unit 2 Cycle 5 Colr TXX-9920, Monthly Operating Repts for Aug 1999 for Cpses.With1999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Cpses.With ML20211M2981999-08-0606 August 1999 Rev 1 to CPSES Fuel Storage Licensing Rept, CPSES Credit for Soluble Boron & Expansion of Spent Fuel Storage Capacity, Consisting of Revised Title Page and 4-1 ML20210U4081999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Cpses,Units 1 & 2 ML20210D8321999-07-23023 July 1999 Safety Evaluation Accepting Relief Requests Re Use of 1998 Edition of Subsections IWE & Iwl of ASME Code for Containment Insp ML20209H7661999-07-15015 July 1999 Safety Evaluation Accepting GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Comanche Peak Steam Electric Station,Units 1 & 2 ML20209H2721999-07-0909 July 1999 2RF04 Containment ISI Summary Rept First Interval,First Period,First Outage ML20209H2631999-07-0909 July 1999 2RF04 ISI Summary Rept First Interval,Second Period,Second Outage ML20209G7501999-07-0808 July 1999 SER Finding That Licensee Individual Plant Exam of External Events Complete with Regard to Info Requested by Suppl 4 to GL 88-20 & That IPEEE Results Reasonable Given Design, Operation & History of Comanche Peak Steam Electric Station ML20196L0191999-07-0808 July 1999 Safety Evaluation Granting Request Relief B-6 (Rev 2),B-7 (Rev2),B-12,B-13,B-14 & C-9,pursuant to 10CFR50.55a(g)(6)(i).Technical Ltr Rept Also Encl ML20210J9391999-06-30030 June 1999 CPSES Commitment Matl Change Evaluation Rept 0003,for 970802-990630 ML20209G0801999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Cpses,Units 1 & 2 ML20196J0621999-06-29029 June 1999 Safety Evaluation Supporting Proposed Changes to Emergency Plan Re Licenses NPF-87 & NPF-89 Respectively ML20195G5141999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Comanche Peak Steam Electric Station,Units 1 & 2.With ML20216E0711999-05-21021 May 1999 1999 Graded Exercise - Comanche Peak Steam Electric Station ML20206Q0091999-05-14014 May 1999 Safety Evaluation Accepting GL 92-08, Thermo-Lag 330-1 Fire Barriers, Dtd 921217,for Comanche Peak Electric Station,Unit 1 ML20206H2061999-05-0606 May 1999 SER Accepting Exemption to App K Re Leading Edge Flowmeter for Plant,Units 1 & 2 ML20196L2241999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Cpses,Units 1 & 2 ML20205R5701999-04-14014 April 1999 Rev 6 to ER-ME-067, TU Electric Engineering Rept,Evaluation of Thermo-Lag Fire Barrier Sys ML18016A9011999-04-12012 April 1999 Part 21 Rept Re Defect in Component of DSRV-16-4,Enterprise DG Sys.Caused by Potential Problem with Connecting Rod Assemblies Built Since 1986,that Have Been Converted to Use Prestressed Fasteners.Affected Rods Should Be Inspected ML20205J7831999-04-0101 April 1999 Rev 0 to ERX-99-001, CPSES Unit 2 Cycle 5 Colr ML20205N3101999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Cpses,Units 1 & 2 ML20204H6371999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Comanche Peak Units 1 & 2 ML20205N1481999-02-28028 February 1999 Corrected Monthly Operating Rept for Feb 1999 for CPSES, Units 1 & 2 ML20203A4881999-02-0303 February 1999 Safety Evaluation Granting Requests for Relief B-3 - B-6,C-2 & C-3 for Plant,Unit 2 ML20210J9201999-02-0101 February 1999 CPSES 10CFR50.59 Evaluation Summary Rept 0008,for 970802- 990201 ML20202D0101999-01-27027 January 1999 Safety Evaluation Supporting First 10-yr Interval ISI Program Plan Requests for Relief B-9,B-10 & B-11 for CPSES, Unit 1 ML20199E9961998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Cpses,Units 1 & 2 ML20207D6091998-12-31031 December 1998 1998 Annual Operating Rept for Cpses,Units 1 & 2. with ML20197K2371998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Cpses,Units 1 & 2 ML20195F3161998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Cpses,Units 1 & 2 ML20154M8841998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Cpses,Units 1 & 2 ML20154B5741998-09-30030 September 1998 Safety Evaluation Re Licensee Response to GL 96-05, Periodic Verification of Design-Basis Capability of Safety- Related Motor-Operated Valves. Licensee Has Established Acceptable Program ML20151W0361998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Cpses,Units 1 & 2. with ML20151Q1211998-08-14014 August 1998 Rev 0 to Control of Hazard Barriers ML20237C4061998-08-14014 August 1998 Safety Evaluation Supporting Request to Implement Risk Informed IST Program ML20237C6721998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Cpses,Units 1 & 2 ML20236V3121998-07-29029 July 1998 Final Part 21 Rept Re Enterprise DSR-4 & DSRV-4 Edgs.Short Term Instability Was Found During post-installation Testing & Setup as Part of Design mod/post-work Testing Process. Different Methods Were Developed to Correct Problem ML20236R0711998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Cpses,Units 1 & 2 ML20249B2581998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Cpses,Units 1 & 2 ML20248A1671998-05-22022 May 1998 Interim Part 21 Re Enterprise DSR-4 & DSRV-4 Emergency diesel.Post-installation Testing Revealed,High Em/Rfi Levels Affected New Controllers,Whereas Original Controllers Were unaffected.Follow-up Will Be Provided No Later than 980731 ML20247G3241998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Cpses,Units 1 & 2 ML20216B8661998-04-0101 April 1998 Rev 0 to ERX-98-001, CPSES Unit 1 Cycle 7 Colr ML20216J3061998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Cpses,Units 1 & 2 ML20216J1861998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Comanche Peak Steam Electric Station ML20197A6951998-02-24024 February 1998 Inservice Insp Summary Rept,First Interval,Second Period, First Outage ML20199J5391998-02-0202 February 1998 CPSES Commitment Matl Change Evaluation Rept 0002 for 960202-970801 1999-09-30
[Table view] |
Text
. _ _ __ . . . _ - _ _ _
.e . n Log # TXX-90107 F
""" File # 10013, 10125'
- C Ref.#10CFR50.72(a)(1) nlELECTRIC i March 13, 1990 Wmism J. Cahill, Jr.
Execut6ve Vke hesident
.U.' S. Nuclear Regulatory Commission
- Attn: . Document-Control Desk .
Washington,-DC 20555 i
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION (CPSES) ;
DOCKET NO. 50-445 TRANSMITTAL 0F REPORT FOLLOWING A NOTIFICATION -
0FUNUSUALEVENT(NUREG-0654):
L
Dear Sir:
As specifie'd 'in the CPSES Emergency Plan, TU Electric hereby transmits the - '
attached report which summarizes the incident which occurred on March 12,-
1990. ' As stated in the corrective action, an evaluation'is'in process and a Licensee Event Report (LER) will be submitted in accordance with 10CFR50.73 by April 12, 1990. '
Sincerely, o
William J. Cahill, Jr.
DEN /GLB/daj Attachment c - Mr. R. D. Martin, Region IV Mr. J. H. Wilson, NRR-0SP.
' Resident-Inspectors, CPSES (3)
Mr. Robert Lansford, Division of Emergency Management 1
t COO 3160493 900313.
- PDR- ADOCK 05000445 S PDC ;
E
. 400 North Olive Street LB. 81 Dallas, Texas 75201
/
I\
, : J' - ,
Enclosure TXX-90107 Page 1 of 2 TU Electric Comanche Peak Steam Electric Station, Unit 1 Docket No. 50-445 Notification of an Unusual Event as a Result of Safety Injection Actuation Report Requirement This_ report is being submitted as recommended by NUREG-0654,
" Criteria for Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness in Support of Nuclear Power Plants" and in accordance with Comanche Peak Steam Electric Station (CPSES) Emergency Plan Procedures. The CPSES Emergency Plan procedures require that a written summary be submitted within 24. hours of the closeout of the Notification of an Unusual
- Event (NOUE).
Event Description On March 12, 1990 at 1401 CST with the plant in Hot Shutdown and the Reactor Coolant System (RCS) temperature at 250 degrees F and pressure at_370 psig, an Engineered Safety Features Actuation-
- Signal (ESFAS) occurred which resulted in the initiation of a Train ~A Safety Injection (SI). The plant staff response to the transient.was in accordance with' Emergency Operating Procedures
-(EOPs). Activation-of the Emergency Plan with the_ Notification of an Unusual Event occurred at 1420. Notification.of the-following offsite agencies was-accomplished in accordance with procedural-requirements: Hood County; Somervell County; Texas Department of Public Safety -- Waco; Nuclear Regulatory Commission, Bethesda; Texas Division of Emergency Management -
Austin; Texas Bureau of Radiation Control - Austin.
Injection flow was terminated in accordance with the EOPs, and the plant was restored _to a stable condition with RCS temperature at 180 degrees F and pressure at 350 psig. During plant recovery, Reactor Coolant flow was reinitiated-resulting in a
-RCS pressure transient; the Pressurizar Power Operated Relief Valve (PORV) actuated to mitigate the transient. The NOUE was terminated at 1625. The initial review conducted subsequent to the event indicates that all components and systems functioned as designed following the SI actuations. At no time was there a threat to the health and safety of the public as a result of-the event.
l l
b
s F
s Let ,, ..
Enclosure TXX-90107 Page 2 of 2 ,
Cause Determination At the time of the event, routine maintenance was being performed on the containment Particulate Iodine Gas (PIG) monitor.
Procedural guidance requires that the Containment PIG monitor be de-energized prior to checking / replacing the filter elements.
De-energization of the containment PIG initiates an ESFAS, causing a Containment Ventilation ILolation (CVI) Signal. A blocking diode normally prevents the CVI signal from reaching the SI relays. However, because the blocking diode failed in a shorted condition, the signal was not blocked, resulting in actuation of the SI relays.
Corrective Actions Immediate corrective actions were focused on restoring the plant to a stable condition. Actions to prevent recurrence will be determined based on the results of the Evaluation Team findings associated with-the Plant Incident investigation of this event.
, The details of the event and the subsequent recovery, including root cause determination and recommendations for. corrective actions, will be included in the Licensee Event Report to be submitted to the Commission in accordance with 10CFR50.73.
i l
l l
.