ML20012B368

From kanterella
Jump to navigation Jump to search
Submits Info Re Reactor Trip & Associated Events on 900305. Evaluation Being Performed to Identify Cause of Failure of Inverter 1PC1 & Reenergizing Procedures Will Be Reviewed & Revised,As Necessary
ML20012B368
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 03/07/1990
From: William Cahill
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
TXX-90103, NUDOCS 9003140277
Download: ML20012B368 (1)


Text

- -

i t

i Lhe#TXX-90103 F

  1. 10110 L"" 9 760.1 m

nlELECTRIC March 7, 1990 l

EO"/ ids $,

U. S. Nuclear Regulatory Commission Attn: Document Control Desk i

Washington, D. C.

20555 l

SUBJECT:

COMANCHE PEAK STEAN ELECTRIC STATION (CPSES) f DOCKET NOS. 50-445 AND 50 446 REACTOR TRIP AND ASSOCIATED EVENTS t

DCCURRING ON MARCH 5, 1990 Gentlemen:

3 As discussed on March 5, 1990, between Mr. Joel Wiebe, NRC Resident Inspector, CPSES, and Mr. William Guldemond, TU Electric, Manager, Site Licensing, concerning tha reactor trip and the associated events which occurred on March 5, 1990, the following information is provided.

An evaluation is currently being performed to identify the cause(s) of the failure of Inverter IPCI on March 5, 1990.

Prior to further control rod s

movement, the cause of the inverter failure will be corrected or, should a i

root cause not be identified. TV Electric will establish suitable monitoring

. programs to detect inverter degradation.

In addition, reenergizing procedures will be reviewed and revised as necessary

~f to address reenergizing equipment after inverter failure.

These revised procedures will be effective prior to entering Mode 4.