ML20011D506

From kanterella
Jump to navigation Jump to search
Ack Receipt of Util Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-313/89-42 & 50-368/89-42
ML20011D506
Person / Time
Site: Arkansas Nuclear  
Issue date: 12/15/1989
From: Collins S
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Campbell G
ARKANSAS POWER & LIGHT CO.
References
NUDOCS 8912270337
Download: ML20011D506 (2)


See also: IR 05000313/1989042

Text

,

,

,

,

'

' '

'

m,pe

,

_

o

df

,'

'

7

s

+

lJy ";

j'Iniep1hRefeETo:

DEC 151195

'

'

L >c

Dockets
50-313/89-42

'

s ,'

..+ -

- c-50-368/89-42

7q. 4

.

,

~

,

,

, y ;, .V.

h-_

,

x

,

" + 4 Arkansas:PowerL& Light Company

A

<ATTH: Gene. Campbell, Vice President

' ' '

T ..E

Nuclear Operations

. ,

y ? + P.O.EBox;5511

.

,

.' .Little' Rock, Arkansas 72203;

< '

,, 4 Gentlemen:t

4

d$7[

',

..

?

lThank you:for your letter of December 4,1980, in "#onse to our letter .

'

Y

.

..

.

>,

. .

.

and Notice of Violation-dated November 3,1989.. We have reviewed your reply

~

,

,

. and find it respnsive to the~ concerns raised in our Notice of Violation. ,We

'

1

will revie*# the implementation of'your corrective. actions during a future

inspection to determine that fu11Ecompliance has been achieved and will be

maintained,

s

Sincerely,

~

Original Signed By:

~ Ssnoel J. coWns

,+.

Samuel s1.: Collins, Director

Division of Reactor Projects

-ccI

-Arkansas Nuclear One

,

ATTH:. Early Ewing, General Manager

Technical Support and Assessment

P.O. Box 608

- Russellville, Arkansas .72801

Arkansas. Nuclear One

ATTN: Neil Carns, Director

'

Nuclear Operations

'P.O.- Box 608

/

Russellville, Arkansas 72801

Combustion Engineering, Inc;

ATTH:

Charles B. Brinkman, Manager

Washington Nuclear Operations

12300 Twinbrook Parkway, Suite 330

f60l

@

.Rockville, _ Maryland :20852

,

,

g

[

RIV:RI:MQPS

C:MQPS $6

D:DR

a

LGilbert/cj

IBarnes

L Callan

ins

/;t /IH89

- G/ g/89

\\ /W89

\\% /

89

'

.

'

'

8912270337 891215

PDR

ADOCK 05000313

g

PDC

'

y'

,7,

,

,

. . . ..

.

'.

.

+

.

,

,

f

.

.

. -b

,

.L

Arkansas Power & Light Ccmpany

-2-

y-

',

,

Honorable Joe W. Phill'.ps

'

,

County Judge of Pope County

Pope. County Courthouse-

'

.Russellville; Arkansas 472801

Bishop, Cook, Purcell & Reynolds

.

ATTN: Nicholas S. Reynolds Esq.

+

1400-L Street, N.W

Washington, D.C.

20005-3502.:

Arkansas Department of Health

-ATTN: Ms. Greta Dieus, Director .

Division of Environmental' Health

Protection

,

4815 West Markam Street-

Littic Rock, Arkansas 72201

-

Babcock A Wilcox.

Nuclear Power Generation' Division

'

ATTN: Mr. Robert B. Borsum

1700 Rockville Pike, Suite 525

' Rockville, Maryland 20852

'

U.S. Nuclear Regulatory Comission

. ATTN: Senior Resident inspector

l Nuclear Plant Road

Pussellville, Arkansas 72801

U.S. ~ Nuclear Regulatory Comission

ATTN: Regional Administrator, Region IV

611 PJan Plaza Drive, Suite 1000

Arlington, Texas 76011

,

.bectoDMB(IE01)

'

bec distrib. by RIV:

-R. D. Martin

Resident Inspector

DRSS-FRPS

SectionChief(DRP/A)

Lisa_Shea,P.M/ALF

RIV File

'

DRP.

MIS System

RSTS Operator

ProjectEngineer(DRP/A)

DRS

-

3

C. Harbuck, NRR Project Manager (MS:

13-D-18)

!

'

L

C. Posiusny, NRR Project Manager (MS:

13-D-18)

l

.

'

'

L.-Gilbert-

9

-I. Barnes

.

I

I

.y

l

2

..

-

~-

'

4_,

i

.

AFh3*l&86 P(mtf s Ligbl

a

+> 'sN,

i TFf

'

)

.f. w

.~

=

ai2ru

.

--

r. ne , en nc.

i

,

- e a ry x,

j

- - - - - - -k ,,

.

r DlPd h h --

$J h

,

' "

'

n

/f

DEC- 719E /

!

'

December 4, 1989

b

!

  1. CAN128901

!

U. S. Nuclear Regulatory Commission

!

Document Control Desk

Mail Station P1-137

Washington, D. C.

20555

SUBJECT:

Arkansas Nuclear One - Units I and 2

,

Docket Nos. 50-313/50-368

License Nos. DPR-51 and NPF-6

i

Response to Inspection Report

'

50-313/89-42; 50-368/89-42

,

Gentlemen:

Pursuant to the provisions of 10CFR2.201, attached is the response to the

violations identified in the subject inspection report.

[

,

Very truly yours,

,0 '

i

/ E. C. Ewing

General Manager,

,

Technical Support

and Assessment

i

ECE/JDJ/sgw

'

attachment

cc:

Region Administrator

Region IV

611 Ryan Plaza Drive, Suite 1000

Arlington, Texas 76011

d'

O.

L5c- 8MO*

"~

.-

-

. . - - .

.

- - - . -.

-

.-

.

U. S. NRC

'

Page 1

,

December 4,1989

.

Notice of Violation

!

A.

Control of Welding Activities

Criterion IX of Appendix B to 10 CFR 50 and the licensee's approved

quality assurance plan require that special processes, such as

welding, be controlled and accomplished by qualified personnel using

qualified procedures.

In the following examples, this did not occur.

'

1.

The travel speed specified on Drawing 2CCB-14-2 for Weld FW18C1

is 3-10 inches per minute.

Contrary to the above, the welding speeds in use were 2 and 11/2

inches per minute.

2.

The Welding procedure Specification (WPS) for Weld FW1C1 did not

address the use of domineralized water to quench the weld.

Contrary to the above, domineralized water was sprayed on the weld

to expedite cooling below 350' F, the maximum interpass temperature

in the WPS.

3.

Flare-bevel Welds FW9, FW10, FW15, and FW16 identified on Drawing

2CCC-6-H-2 were specified to be 2 inches of weld 4-inch centers.

Contrary to the above, these welds were accepted although they were

made continuously (for 6 inches without break).

This is a Severity Level IV violation.

(Supplement II)(313/8942-01;

368/8942-01)

Response to the Violation

1.

The reason for the violation:

1

With regard to examples 1 and 2, the cause of the violation was the

failure of management to clearly communicate expectations regarding

adherence to the quality requirements built into the program to the

weld craftsmen and weld craftsmen supervision.

In example 1, the welder was not aware that the travel speed specification

1

was in the WPS.

(As stated in paragraph 3.b of the Inspection Report,

'

the WPS, not the drawing, is the document containing the travel speed

specifications.)

Concerning example 2, the use of demineralized water as a que.1ching

spray on austenitic stainless steel was an historical construction

!

'

practice not covered by procedure.

The welder was following what he

considered to be an accepted practice instead of strictly adhering to

the WPS.

l

.

-

.

.

-

--

. .

.

_ . _ .

-

- - _ - .

_ _-- _ -_ _

1

.;

U. S. NRC

-*-

Page 2

December 4, 1989

.

With regard to example 3, the cause of the violation was inattention

to detail by the welder.

After completing the welding on a nearly

identical hanger 2CCC-12-H1 which specified a continuous weld, he

failed to note the difference in the drawings and welded hanger 2CCC-6-H2

similarly.

2.

The corrective steps that have been taken:

To ensure that weld craftsmen and weld craftsmen supervision were aware

of management's expectations for the conduct of welding activities,

training was conducted on October 20, 21, and 22, 1989, which emphasized

that the requirements of the WPS must be followed and that circumstances

prohibiting WPS compliance require that work is stopped and the supervisor

is notified for resolution.

Also, supervisors began reviewing each

weld package and the WPS with the craftsman before the job is started.

These actions were previously addressed in our letter of October 26,

1989 (SCAN 198917).

Additional training which discussed weld procedure specifications and

compliance with these requirements was conducted during the week of

November 27, 1989, for plant modifications wela craftsmen and maintenance

>

weld craftsmen.

The " Control of Plant Modification Welding" and " Conduct of Maintenance

Welding" procedures have been changed to state that a copy of the WPS

shall be in the work package at the work location and that the supervisor

will review the weld packages and the WPS with the craftsmen at the

,

start of each shift. The procedures now clearly state that welding

specifications will be followed, activities not addressed in procedures

>

,

l

or specifications will not be done, and circumstances prohibiting

compliance with the specifications require stopping work and notifying

the Lognizant supervisor for resolution.

Also, to address the additional weakness identified in the inspection

report regarding Quality Control (QC) surveillance of welding activities,

,

QC has implemented a special welding surveillance checklist which has

been incorporated into QCO-6, " Welding Inspection", along with monitoring

frequency guidance.

Routine, random surveillance of in process welding

activities is being performed and documented.

Concerning the adequacy of the weld noted in example 1, the supporting

,

procedure qualification records for the WPS were reviewed by Engineering.

l

l

As a result, the WPS travel speed was determined to be overly restrictive,

L

and the WPS was revised accordingly to require 1-10 inches per minute.

As this change to the WPS was non-essential pursuant to the applicable

ASME code, the quality of the weld was not affected by the use of a

slower travel speed and the weld was determined to be acceptable.

,

.--. , , . , ,

. - . - . . - - - - . , - -

-.

, . , , , , - - - - - - . - . - - . - . _ - . _ - - , , _ _ . - - , - ,-

n

}

[

(

4

1 3,

U. S. NRC

'

,

Page 3

)

,

.

,

December 4 -1989

'

To establish the adequacy of the weld noted in example 2. Engineering

determined that the use of demineralized water to control interpass

temperature on P8 austenitic stainless steel is an appropriate use of

i

a quenching spray.

A memorandum was issued by Engineering which

j

established interim requirements for use of domineralized water as a

quenching spray until the weld specifications are revised.

(The weld

specifications will be revised by February 28, 1990.) However, prior

to this determination occurring, the weld was cut out and rewelded

without the use of quenching spray and the new weld was determined to

be acceptable.

The continuous flare-bevel welds in example 3 were determined to be

acceptable in accordance with AP&L specification APL-M-2410. Section

4.11. " Support Assemblies of Greater Strength than Required". The

.

hanger as-built drawing was revised to indicate the continuous weld.

In each of the examples given, the quality of the welds was not affected.

AP&L has no indication that procedural non-compliance has resulted in

unsafe welding practices.

3.

The corrective steps that will be taken to avoid recurrence:

,

Training on compliance with procedures and specifications will be

conducted for new welders coming on site in the future.

This on-going

training, the training and the procedure changes which have already

been completed, and the implementation of the QC welding surveillance

checklist will prevent a recurrence of this violation.

A review of AP&L/ANO ASME and AWS Welding Procedure Specifications for

accuracy and adequacy was initiated.

The 52 AWS D1.1 qualified joint

and pre qualified joint WPSs have been reviewed and no changes were

required.

Of the 57 ASME Section IX qualified WPSs, 14 of the most

commonly used WPSs have been reviewed and revised as necessary. The

remaining ASME Section IX qualified Welding Procedure Specifications

will be reviewed and revised as necessary by February 28, 1990. Any

inadequacies in the remaining WPSs will not affect welding activities

as the weld craftsmen and supervisors review the WPS prior to starting

work and they are aware that any difficulties must be resolved before

I

the work can be done.

The AP&L/AND Specification M-2415. " Nuclear

Welding Standards", will be revised to address the use of demineralized

water for controlling interpass temperature on austenitic stainless

steels by February 28, 1990.

A review of the welding program at ANO has been initiated for possible

enhancements, such as consolidation of the separate controls for the

maintenance and modifications groups into uniform, comprehensive

procedures and policies.

Such procedurer, and policies would encompass

training and qualification requirements ter all welders on site. This

review is expected te be completed by May 1, 1990.

,

.

-.

. . - - - - . - -

_ - - . _ . - - - ,

-

n-

,'c

'.

.

"

U0 S. NRC

-

'

Gage 4

.

'

j.

December 4, 1989

.

,

4.

The date of full compliance:

Compliance was achieved by October 22, 1989, with the completion

i

of the training of the weld craftsmen on compliance with procedures and

specifications.

As discussed above, the following procedures changes will be completed

by February 28, 1990:

The remaining 43 ASME Section IX qualified WPSs, to be revised as

necessary based on reviews.

AP&L/ANO Specification M-2415 to address the use of quenching spray.

Identified enhancements to the welding program as discussed above are

expected to be completed by May 1, 1990.

Notice of Violation

B.

Document Control

Criterion VI of Appendix 8 to 10 CFR 50 and the licensee's approved

quality assurance plan require that measures shall assure that document

changes are distributed to and used at the location where the prescribed

activity is performed.

Contrary to the above, out-of-date revisions of Procedures 1092.011

" Implementing and Control Welding," and 1033.003, "Weiding Filler

Material Control" were in use at the storeroom during the issue of

welding materials.

This resulted in procedurally required records not

being maintained.

This is a Severity level IV violation.

(Supplement II) (313/8942-02;

368/8942-02)

Response to the Violation

1.

The reason for the violation:

The correct revision of Procedure 1092.011 was not in the storeroom

because Materials Management was not included on the Master Procedure

Distribution List (MPDL) for 1092.011.

The MPDL is used by Document

Control to distribute new procedure revisions.

The need for this

procedure in the storeroom was apparently overlooked when distribution

of the procedure was determined.

The correct revision of procedure 1033.003 was not in the rod storeroom

because the Stores Supervisor failed to forward a copy to the rod

storeroom.

l

-

-

-.

..

-

.

-

-

.

._.

W

( .t ' .

'

U. S. NRC

'

Page 5

,

December 4, 1989

.

.

2.

The corrective steps that have been taken:

Copies of the latest revisions of procedures 1092.011 and 1033.003 were

placed in the rod storeroom on October 20, 1989.

Materials Management and the rod storeroom have been added to the MPDL

for procedure 1092.011, and the rod storeroom was added to the MPDL for

procedure 1033.003.

Revisions to these procedures will now be issued

?

directly to the rod storeroom by Document Control, and written confirmation

of receipt of each revision is required by Document Control procedures.

,

The Stores Supervisor has a controlled set of procedures required by

Materials Management.

There are no other work locations in Materials

Management (except the rod storeroom) which require distribution of

-

document changes.

The approval form for procedure revisions has recently been revised to

I

ensure that if a procedure revision affects departments other than

the department responsible for the procedure, the revision is also

'

approved by a section leader in the other affected departments.

This

,

will help ensure that procedures are distributed to the appropriate

departments.

'

3.

Corrective steps that will be taken to prevent recurrence:

Actions taken to place the procedures on the MPDL for the rod storeroom

l

will prevent recurrence of this event.

A review will be conducted of the 1033 procedure series (Materials

Management procedures) to identify referenced procedures which are the

responsibility of other departments.

These identified procedures will

(.

be reviewed to determine if Materials Management should be on the

distribution list for each procedure.

This review will be completed

'

by January 15, 1990.

4.

The date of full compliance:

l

Full compliance was achieved October 20, 1989, when the current revisions

l

were placed in the storeroom.

l

.

-,

--