Interim Deficiency Rept Re Lubricating Oil Sys Defect in Delaval Standby Diesel Generator Model DSRV16.Pre-engine Start Testing Now Scheduled for Oct 1982.Final Rept Will Be Submitted by 820415
ML20011A671
Person / Time
Site: Perry  
Issue date: 10/22/1981
From: Davidson D
CLEVELAND ELECTRIC ILLUMINATING CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, 10CFR-50.55E, NUDOCS 8110290267
Download: ML20011A671 (1)


Text

THE CLEVELAND ELECTRIC ILLUMIN ATING COMPANY P o. box 5000 e CLEVELAND. OHIO 44101 e

TELEPHONE (216) 622-9800 m ILLUMINATING BLOG e

55 PUBLICSoVARE e ng a Best Locanon in the Nation Dalwyn R. Davidson VICE PRESiOENT

~s SYSTEM EP'GINEERENd ANS CONSTRUCTION g '-

gw s;t'q N

October 22, 1981

< e' C'

l~f f i.

l/

v% e Q

OcQ, /Sg "E Mr. James G. Keppler

~

s.

Director, Region III i

' 4 Z

O[l q

Office of Inspection and Enforcement

\\

C U. S. Nuclear Regulatory Commission

, p.

+

799 Roosevelt Road

\\

Glen Ellyn, Illinois 60137

\\

O. A

/},g\\

RE:

Perry Nuclear Power Plant, Docket Nos. 50-440; 50-441, Lubricating Oil System Defect in DeLaval Standby Diesel Cenerator Model DSRV16 (RDC 24(81))

Dear Mr. Keppler.

The Interim Report concerning subject deficiency states the Final Report is scheduled to be submitted to your office during October, 1981.

As discussed with Mr. E. R. Schweibinz of your office on October 19, 1981, our final report is now scheduled to be submitted by April 15, 1982.

Pre engine start testing is now tentatively scheduled for October, 1982, and delay in the modification of the turbocharger lubricating oil system has been due, in part, to construction activities. Additionall y, completion of procurement activities for modification parts is requiring more time than originally estimated.

If there are any questiora, please do not hesitate to call.

Sincerely, THE CLEVELAND E'.ZCTRIC ILLUMINATING COMPANY f]ld$d Y

Dalwyn R. Davidson Vice President System Engineering and Construction DRD/llp cc:

NRC Resident Inspector's Office Perry 1;uclear Powcr Plant Director, Of fice of Inspection and Enforcement U. S. Nuclear Regulatory Commission

[ Si o Washington, D. C.

20555 l

U.S. Nuclear Regulatory Commission c/o Document Management Branch Washington, D.C.

20555 8110290267 811022 OCT 2 6 190I R ADOCK OSoco4po g