ML20011A388

From kanterella
Jump to navigation Jump to search
Forwards QA Program Insp Rept 99900505/81-02 on 810421-24 & Notice of Nonconformance
ML20011A388
Person / Time
Issue date: 05/18/1981
From: Potapovs U
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Tenzer B
EBASCO SERVICES, INC.
Shared Package
ML20011A373 List:
References
REF-QA-99900505 NUDOCS 8110090378
Download: ML20011A388 (2)


Text

~f

/pnea6'c, UNITED STATES o

[*

NUCLEAR REGULATORY COMMISSION "J

- j REGION IV f

$11 RYAN PLAZA DRIVE. SUITE 1000

  • (1

,, f ARLINGTON. TEXAS 76011 18 MAY 1981 Docket No. 99900505/81-02 Ebasco Services, Inc.

ATTN: Mr. B. E. Tenzer, Vice-President Materials Engineering and Quality Assurance Two World Trade Center New York, New York 10048 Gentlemen:

This refers to the inspectior conducted by Mr. J. R. Costello of this office on April 21-24, 1981, of your facility at New York, New York, and to the discussions of our findings with you' and members of your staff at the conclusion of the inspection.

Areas examined during this inspection and our findings are discussed in the enclosed report. Within these areas, the inspection consisted of an examination of procedures and representative records, interviews with personnel, and obser-vations by the inspector.

During this inspection it was found that you failed to meet certaia commitments in your Topimi Report No. ETR-1001.

The specific findings and references to tne pertinent requirements are identified in the enclosures to this letter.

Please provide us within 25 days of the date of this letter a written state-ment containing, (1) a description of steps that have been or will be taken to correct these items, (2) a description of steps that have been or will be taken to prevent recurrence, and (3) the dates your corrective actions and preventive measures were or will be completed.

In accordance with 10 CFR 2.790 of the Comission's regulations, a copy of this letter and the enclosed inspection report will be olaced in the NRC's Public Occument Room.

If this report contains any information that you believe to be exempt from disclosure under 10 CFR 9.5(a)(4), it is necessary that you (a) notify this office by telephone within 10 days from the date of this letter of your intention to file a request for withnolding; anc (b) suo-mit within 25 days from the date of this letter a written acclication to this office to withnold such information.

If your receiot of this letter nas been delayed sucn that less than seven days are available for your review, please notify this office promptly so that a new due data may be established.

Consistent with Sectian 2.790(b)(1), any sucn application must be acc;moaniec ey an 1Tfiday1t execu ed by tne owner of the information wnich ident171es the cocumerit or cart sougnt to be withneid, and wnicn contains a full statement of the reasons on the basis wnicn it is claimed tnat tne information should be 8110090378 810626 PDR GA999 EECEBAS 99900505 PDR

=

Ebasco Ser/ ices, Inc.

2

~

withheld from public disclosure.

This section further requires the statement to address with specificity the considerations listed in 10 CFR 2.790(b)(4).

The information sought to be withheld shall be incorporated as far as possible into a. separate part of the affidavit.

If we do not hear from you in this regard within the specified periods noted above, the report will be placed' in the Public Document Room.

Should you have any questions concerning this inspection, we will be pleased to discuss them with you.

Sincerely, 1

\\

ir C

l'W U181sPotapovs, hief 1 Vendor Inspection Branch

Enclosures:

1.

Notice of Nonconfonnance 2.

Inspection Report No. 99900505/81-02 a g

-