MONTHYEARML20247B3941989-07-13013 July 1989 NRC Staff Response to Rl Anthony Request for Hearing & for Intervention.* Commission Should Deny Anthony Request Due to Anthony Interest Not within Scope of Remand.W/Certificate of Svc ML20246P0581989-07-0707 July 1989 Answer by Philadelphia Electric Co to Request by Rl Anthony for Hearing & Admission as Intervenor.* Anthony Not Entitled to New Hearing on Emergency Plannning or Other Safety Issues & Request Should Be Denied.W/Certificate of Svc ML20245J3681989-06-23023 June 1989 Request by Intervenor Rl Anthony to Be Continued as Intervenor in Licensing Process for Unit 2 & for Hearing Under 42 ESC Section 2239(a) as Affected Person,Endangered by Philadelphia Electric Failure to Satisfy Plant....* ML20235B4271987-09-16016 September 1987 Response of NRC Staff to Proposed Contentions of Air & Water Pollution Patrol & Rl Anthony.* Board Should Deny Requests That Hearing Be Held in Connection W/Proposed Amend. Certificate of Svc Encl ML20238F1771987-09-11011 September 1987 Licensee Answer to Contentions Proposed by Intervenors Air & Water Pollution Patrol & Rl Anthony.* Air & Water Pollution Patrol & Rl Anthony Failed to Plead Single Admissible Contention.W/Certificate of Svc ML20214N1231987-05-22022 May 1987 Licensee Answer in Opposition to Petition by Rl Anthony for Leave to Intervene and for Hearing.* Petition Deficient Under Rules for Intervention.Certificate of Svc Encl ML20214N2251987-05-20020 May 1987 Licensee Answer in Opposition to Request for Hearing & Leave to Intervene by Air & Water Pollution Patrol.* Supporting Info Encl.Certificate of Svc & Notices of Appearance Encl ML20214A9301987-05-14014 May 1987 Licensee Opposition to Petition by Graterford Inmates for Review of ALAB-863.* Review Opposed on Grounds That Inmate Petition Failed to Show ALAB-863 Erroneous or Justify Claims of Prejudice.Certificate of Svc Encl ML20214M7331986-09-0404 September 1986 Petition of Air & Water Pollution Patrol for Leave to Intervene Opposing Applicant 860819 Application for Amend to License NPF-39.NRC Address List Encl ML20212N2871986-08-25025 August 1986 Petition of Rl Anthony for Leave to Intervene & Request for Hearing ML20210N4841986-04-29029 April 1986 Petition for Reconsideration of 860227 Petition to Suspend License NPF-39 Due to Faulty Referral to Director of NRR, Inappropriate Response & Restating of Petition Under 10CFR50.100 & 10CFR2.201(c) ML20154R5151986-03-26026 March 1986 Answer Opposing Rl Anthony 860226 Contention Suppls on Amends 1 & 2 to License NPF-39 Due to Failure to Satisfy or Discuss Lateness Criteria & Lack of Standing ML20154R5261986-03-26026 March 1986 Answer Opposing Fr Romano 860319 Late Filed Suppl in Response to Notice of Opportunity to Request Hearing on Proposed Amend 1 to License NPF-39.Romano Failed to Plead Admissible Contention.Certificate of Svc Encl ML20210E1911986-03-19019 March 1986 Suppl to 860215 Petition for Leave to Intervene on 860130 & 0205 Requests & Provides List of Contentions Vs Amend to License NPF-39 ML20138A8931986-03-17017 March 1986 Response Opposing Petition of Air & Water Pollution Patrol for Leave to Intervene & Request for Hearing Re Amend 1 to License NPF-39.W/Certificate of Svc ML20138A9081986-03-17017 March 1986 Response Opposing Rl Anthony 860215 Contentions Re Util Request for Amend 1 to License NPF-39,extending 18-month Surveillance Interval by 14 Wks Beyond Max 25% Extension Allowed by Tech Specs.W/Certificate of Svc ML20138A9511986-03-17017 March 1986 Response Opposing Rl Anthony Contentions Re OL Amend. Contentions Lack Requisite Specificity & Bases Under 10CFR2.714(b).Notice of Appearance & Certificate of Svc Encl ML20138A8851986-03-13013 March 1986 Petition of Rl Anthony & Friends of the Earth for Leave to Intervene & Request for Hearing ML20141N1611986-02-26026 February 1986 Petition of Rl Anthony & Friends of the Earth for Leave to Intervene & Request for Hearing in Opposition to Util Request to Amend Tech Specs 4.6.1.2.d & 4.6.1.2.g to License NPF-39 ML20205K5471986-02-25025 February 1986 Response Opposing Rl Anthony/Friends of the Earth 860205 Petition to Intervene & Request for Hearing Re 851218 Proposed Schedular Amend from Testing Certain Excess Flow Check Valves for 14-wk Period.Certificate of Svc Encl ML20141N1371986-02-24024 February 1986 Petition of Air & Water Pollution Patrol for Leave to Intervene & Request for Hearing ML20214C9141986-02-19019 February 1986 Answer Opposing 860130 late-filed Petition for Leave to Intervene & Request for Hearing by Rl Anthony.Certificate of Svc Encl ML20154D5771986-02-15015 February 1986 Petition of Rl Anthony & Friends of the Earth for Leave to Intervene & Request for Hearing ML20141M8271986-02-12012 February 1986 Petition of Rl Anthony & Friends of the Earth for Hearing & Immediate Stay on Effectiveness & Implementation of Amend 1 to License NPF-39.Util Should Be Required to Suspend Operations on Deadline Until Tests Performed ML20151Y7851986-02-10010 February 1986 Opposition to 860126 Petition by Friends of the Earth for Review of ALAB-828.Intervenor Has Shown No Issue of Fact,Law or Policy Which NRC Should Review.Certificate of Svc Encl ML20151T9881986-02-0505 February 1986 Amend to 860130 Petition of Rl Anthony & Friends of the Earth for Leave to Intervene & Request for Hearing.Extension of 96 Days for Testing Instrumentation Lines Vital to Safe Operation & Shutdown Requested.W/Certificate of Svc ML20094A2831984-11-0202 November 1984 Answer to Intervenor Del-Aware Unlimited,Inc,Revised Contentions V-14 & V-16.Proposed Contentions Should Be Denied & Del-Aware Dismissed as Party.Certificate of Svc Encl ML20094A8691984-10-23023 October 1984 Appeal from Second Partial Initial decision,LPB-84-31 & ASLB 840901 Motion to Set Aside & Reopen Contentions V-3a & 3B & Petition for Stay ML20106C5081984-10-19019 October 1984 Revised Contentions 14 & 16 Re Destruction of Eligible Natl Historic District of Point Pleasant & Adverse Effect on Salinity Levels & Water Quality in Delaware River, Respectively.Certificate of Svc Encl ML20093F0851984-10-0909 October 1984 Response to Limerick Ecology Action Refiled Deferred Offsite Emergency Planning Contentions.Certificate of Svc Encl ML20093D6331984-10-0909 October 1984 Answer Opposing Limerick Ecology Action (Lea) Deferred Offsite Emergency Planning Contentions.Lea Respecified Contentions Should Be Denied.Certificate of Svc Encl ML20093C0991984-10-0101 October 1984 Respec of Offsite Emergency Planning Contentions.Certificate of Svc Encl ML20097C5551984-09-13013 September 1984 Answer Opposing Limerick Ecology Action (Lea) 840906 Respecification of Offsite Emergency Planning Contentions. ASLB Should Dismiss Any Contentions for Which Lea Fails to Proffer Direct Testimony.Certificate of Svc Encl ML20096A7221984-08-29029 August 1984 Response Opposing Air & Water Pollution Patrol 840814 Pleading on Reopening Contention VI-1 Re Welding & Welding Insp Infractions.Certificate of Svc Encl ML20095E4271984-08-21021 August 1984 Answer Opposing late-filed Air & Water Pollution Patrol 840808 New Contention Re Evacuation.Contention Lacks Basis & Specificity & Fails to Show Good Cause for Late Filing. Certificate of Svc Encl ML20095E4401984-08-20020 August 1984 Provides Addendum to Air & Water Pollution Patrol 840816 New Info Contention Re Polyvinyl Chloride.Fifth Criterion Re Breakdown of Polyvinyl Chloride Inadvertantly Omitted.Small Delay in Proceedings Ack for Large Public Good ML20095C0251984-08-16016 August 1984 New Info Contention Re Health Hazard Via Polyvinyl Chloride Fill Used in Reactor Cooling Towers.W/Svc List ML20094K0871984-08-0909 August 1984 Reply to Applicant & Staff Answers to Cepa Safety Contentions.Contentions Should Be Admitted.Certificate of Svc Encl ML20094J7761984-08-0808 August 1984 New Contention That Applicant Must Provide Fully Testable & Capable Emergency Evacuation Plan Prior to Receipt of OL ML20093N2651984-07-27027 July 1984 Answer to Consumer Educ & Protective Assoc 840717 Safety Contentions.Contentions Lack Basis,Concern Ratemaking Matters Outside NRC Jurisdiction & Should Be Denied. Certificate of Svc Encl ML20093E4241984-07-16016 July 1984 Safety Contentions Re Util Inability to Conduct Full & Safe Test Procedures.Certificate of Svc Encl ML20090A6751984-07-10010 July 1984 Answer to New Proposed Contention by Air & Water Pollution Patrol Re Gross Alpha.Certificate of Svc Encl ML20092N1501984-06-26026 June 1984 New Contention That EPA Max Containment Levels for Gross alpha,Ra-226 & Ra-228 Inadequately Verified by Applicant & Nrc.W/Svc List ML20092P7701984-06-19019 June 1984 Motion Opposing Util 840509 Motion for Expedited Partial Decision & Low Power License.Util & NRC Should Certify That All Nonconformance Items & Open Insp Items Corrected & Complete Before Nuclear Fuel Moved Onsite ML20092P7721984-06-18018 June 1984 Motion for Admission of Contentions Based on JW Gallagher & Js Kemper Requesting Remaining Portion of License to Move Fuel to Refueling Floor,Insp & Storage of Fuel & Petition for Stay ML20091R4601984-06-13013 June 1984 Answer Opposing Friends of the Earth 840518 Supplemental Motion for Admission of New,Late Contentions Re Applicant Motion for Expedited Partial Initial Decision & Issuance of Low Power License.Certificate of Svc Encl ML20091C9221984-05-29029 May 1984 Response Opposing Petition by Citizen Action in the Northeast for Late Intervention & Admission of Financial Qualifications Contention.Contentions Lack Requisite Bases & Specificity.Certificate of Svc Encl ML20087M8061984-03-30030 March 1984 New Addition to Contention Re Asbestos Fiber Discharges Into Schuylkill River & Air.Discharge Not Identified Nor Included in Plant Operation Discharge Descriptions.W/Svc List ML20087M6381984-03-28028 March 1984 Response Opposing M Lewis 840314 Motion for New Contention Based on IE Info Notice 84-17 Cooling of Vital Components by Liquid Nitrogen.Certificate of Svc Encl ML20087K8651984-03-23023 March 1984 Motion to Dismiss Particular Onsite Emergency Planning Contentions for Which Discovery Not Provided or No Litigable Basis Shown.Certificate of Svc Encl 1989-07-07
[Table view] Category:RESPONSES & CONTENTIONS
MONTHYEARML20247B3941989-07-13013 July 1989 NRC Staff Response to Rl Anthony Request for Hearing & for Intervention.* Commission Should Deny Anthony Request Due to Anthony Interest Not within Scope of Remand.W/Certificate of Svc ML20246P0581989-07-0707 July 1989 Answer by Philadelphia Electric Co to Request by Rl Anthony for Hearing & Admission as Intervenor.* Anthony Not Entitled to New Hearing on Emergency Plannning or Other Safety Issues & Request Should Be Denied.W/Certificate of Svc ML20245J3681989-06-23023 June 1989 Request by Intervenor Rl Anthony to Be Continued as Intervenor in Licensing Process for Unit 2 & for Hearing Under 42 ESC Section 2239(a) as Affected Person,Endangered by Philadelphia Electric Failure to Satisfy Plant....* ML20235B4271987-09-16016 September 1987 Response of NRC Staff to Proposed Contentions of Air & Water Pollution Patrol & Rl Anthony.* Board Should Deny Requests That Hearing Be Held in Connection W/Proposed Amend. Certificate of Svc Encl ML20238F1771987-09-11011 September 1987 Licensee Answer to Contentions Proposed by Intervenors Air & Water Pollution Patrol & Rl Anthony.* Air & Water Pollution Patrol & Rl Anthony Failed to Plead Single Admissible Contention.W/Certificate of Svc ML20214N1231987-05-22022 May 1987 Licensee Answer in Opposition to Petition by Rl Anthony for Leave to Intervene and for Hearing.* Petition Deficient Under Rules for Intervention.Certificate of Svc Encl ML20214N2251987-05-20020 May 1987 Licensee Answer in Opposition to Request for Hearing & Leave to Intervene by Air & Water Pollution Patrol.* Supporting Info Encl.Certificate of Svc & Notices of Appearance Encl ML20214A9301987-05-14014 May 1987 Licensee Opposition to Petition by Graterford Inmates for Review of ALAB-863.* Review Opposed on Grounds That Inmate Petition Failed to Show ALAB-863 Erroneous or Justify Claims of Prejudice.Certificate of Svc Encl ML20214M7331986-09-0404 September 1986 Petition of Air & Water Pollution Patrol for Leave to Intervene Opposing Applicant 860819 Application for Amend to License NPF-39.NRC Address List Encl ML20212N2871986-08-25025 August 1986 Petition of Rl Anthony for Leave to Intervene & Request for Hearing ML20210N4841986-04-29029 April 1986 Petition for Reconsideration of 860227 Petition to Suspend License NPF-39 Due to Faulty Referral to Director of NRR, Inappropriate Response & Restating of Petition Under 10CFR50.100 & 10CFR2.201(c) ML20154R5151986-03-26026 March 1986 Answer Opposing Rl Anthony 860226 Contention Suppls on Amends 1 & 2 to License NPF-39 Due to Failure to Satisfy or Discuss Lateness Criteria & Lack of Standing ML20154R5261986-03-26026 March 1986 Answer Opposing Fr Romano 860319 Late Filed Suppl in Response to Notice of Opportunity to Request Hearing on Proposed Amend 1 to License NPF-39.Romano Failed to Plead Admissible Contention.Certificate of Svc Encl ML20210E1911986-03-19019 March 1986 Suppl to 860215 Petition for Leave to Intervene on 860130 & 0205 Requests & Provides List of Contentions Vs Amend to License NPF-39 ML20138A8931986-03-17017 March 1986 Response Opposing Petition of Air & Water Pollution Patrol for Leave to Intervene & Request for Hearing Re Amend 1 to License NPF-39.W/Certificate of Svc ML20138A9081986-03-17017 March 1986 Response Opposing Rl Anthony 860215 Contentions Re Util Request for Amend 1 to License NPF-39,extending 18-month Surveillance Interval by 14 Wks Beyond Max 25% Extension Allowed by Tech Specs.W/Certificate of Svc ML20138A9511986-03-17017 March 1986 Response Opposing Rl Anthony Contentions Re OL Amend. Contentions Lack Requisite Specificity & Bases Under 10CFR2.714(b).Notice of Appearance & Certificate of Svc Encl ML20138A8851986-03-13013 March 1986 Petition of Rl Anthony & Friends of the Earth for Leave to Intervene & Request for Hearing ML20141N1611986-02-26026 February 1986 Petition of Rl Anthony & Friends of the Earth for Leave to Intervene & Request for Hearing in Opposition to Util Request to Amend Tech Specs 4.6.1.2.d & 4.6.1.2.g to License NPF-39 ML20205K5471986-02-25025 February 1986 Response Opposing Rl Anthony/Friends of the Earth 860205 Petition to Intervene & Request for Hearing Re 851218 Proposed Schedular Amend from Testing Certain Excess Flow Check Valves for 14-wk Period.Certificate of Svc Encl ML20141N1371986-02-24024 February 1986 Petition of Air & Water Pollution Patrol for Leave to Intervene & Request for Hearing ML20214C9141986-02-19019 February 1986 Answer Opposing 860130 late-filed Petition for Leave to Intervene & Request for Hearing by Rl Anthony.Certificate of Svc Encl ML20154D5771986-02-15015 February 1986 Petition of Rl Anthony & Friends of the Earth for Leave to Intervene & Request for Hearing ML20141M8271986-02-12012 February 1986 Petition of Rl Anthony & Friends of the Earth for Hearing & Immediate Stay on Effectiveness & Implementation of Amend 1 to License NPF-39.Util Should Be Required to Suspend Operations on Deadline Until Tests Performed ML20151Y7851986-02-10010 February 1986 Opposition to 860126 Petition by Friends of the Earth for Review of ALAB-828.Intervenor Has Shown No Issue of Fact,Law or Policy Which NRC Should Review.Certificate of Svc Encl ML20151T9881986-02-0505 February 1986 Amend to 860130 Petition of Rl Anthony & Friends of the Earth for Leave to Intervene & Request for Hearing.Extension of 96 Days for Testing Instrumentation Lines Vital to Safe Operation & Shutdown Requested.W/Certificate of Svc ML20094A2831984-11-0202 November 1984 Answer to Intervenor Del-Aware Unlimited,Inc,Revised Contentions V-14 & V-16.Proposed Contentions Should Be Denied & Del-Aware Dismissed as Party.Certificate of Svc Encl ML20094A8691984-10-23023 October 1984 Appeal from Second Partial Initial decision,LPB-84-31 & ASLB 840901 Motion to Set Aside & Reopen Contentions V-3a & 3B & Petition for Stay ML20106C5081984-10-19019 October 1984 Revised Contentions 14 & 16 Re Destruction of Eligible Natl Historic District of Point Pleasant & Adverse Effect on Salinity Levels & Water Quality in Delaware River, Respectively.Certificate of Svc Encl ML20093F0851984-10-0909 October 1984 Response to Limerick Ecology Action Refiled Deferred Offsite Emergency Planning Contentions.Certificate of Svc Encl ML20093D6331984-10-0909 October 1984 Answer Opposing Limerick Ecology Action (Lea) Deferred Offsite Emergency Planning Contentions.Lea Respecified Contentions Should Be Denied.Certificate of Svc Encl ML20093C0991984-10-0101 October 1984 Respec of Offsite Emergency Planning Contentions.Certificate of Svc Encl ML20097C5551984-09-13013 September 1984 Answer Opposing Limerick Ecology Action (Lea) 840906 Respecification of Offsite Emergency Planning Contentions. ASLB Should Dismiss Any Contentions for Which Lea Fails to Proffer Direct Testimony.Certificate of Svc Encl ML20096A7221984-08-29029 August 1984 Response Opposing Air & Water Pollution Patrol 840814 Pleading on Reopening Contention VI-1 Re Welding & Welding Insp Infractions.Certificate of Svc Encl ML20095E4271984-08-21021 August 1984 Answer Opposing late-filed Air & Water Pollution Patrol 840808 New Contention Re Evacuation.Contention Lacks Basis & Specificity & Fails to Show Good Cause for Late Filing. Certificate of Svc Encl ML20095E4401984-08-20020 August 1984 Provides Addendum to Air & Water Pollution Patrol 840816 New Info Contention Re Polyvinyl Chloride.Fifth Criterion Re Breakdown of Polyvinyl Chloride Inadvertantly Omitted.Small Delay in Proceedings Ack for Large Public Good ML20095C0251984-08-16016 August 1984 New Info Contention Re Health Hazard Via Polyvinyl Chloride Fill Used in Reactor Cooling Towers.W/Svc List ML20094K0871984-08-0909 August 1984 Reply to Applicant & Staff Answers to Cepa Safety Contentions.Contentions Should Be Admitted.Certificate of Svc Encl ML20094J7761984-08-0808 August 1984 New Contention That Applicant Must Provide Fully Testable & Capable Emergency Evacuation Plan Prior to Receipt of OL ML20093N2651984-07-27027 July 1984 Answer to Consumer Educ & Protective Assoc 840717 Safety Contentions.Contentions Lack Basis,Concern Ratemaking Matters Outside NRC Jurisdiction & Should Be Denied. Certificate of Svc Encl ML20093E4241984-07-16016 July 1984 Safety Contentions Re Util Inability to Conduct Full & Safe Test Procedures.Certificate of Svc Encl ML20090A6751984-07-10010 July 1984 Answer to New Proposed Contention by Air & Water Pollution Patrol Re Gross Alpha.Certificate of Svc Encl ML20092N1501984-06-26026 June 1984 New Contention That EPA Max Containment Levels for Gross alpha,Ra-226 & Ra-228 Inadequately Verified by Applicant & Nrc.W/Svc List ML20092P7701984-06-19019 June 1984 Motion Opposing Util 840509 Motion for Expedited Partial Decision & Low Power License.Util & NRC Should Certify That All Nonconformance Items & Open Insp Items Corrected & Complete Before Nuclear Fuel Moved Onsite ML20092P7721984-06-18018 June 1984 Motion for Admission of Contentions Based on JW Gallagher & Js Kemper Requesting Remaining Portion of License to Move Fuel to Refueling Floor,Insp & Storage of Fuel & Petition for Stay ML20091R4601984-06-13013 June 1984 Answer Opposing Friends of the Earth 840518 Supplemental Motion for Admission of New,Late Contentions Re Applicant Motion for Expedited Partial Initial Decision & Issuance of Low Power License.Certificate of Svc Encl ML20091C9221984-05-29029 May 1984 Response Opposing Petition by Citizen Action in the Northeast for Late Intervention & Admission of Financial Qualifications Contention.Contentions Lack Requisite Bases & Specificity.Certificate of Svc Encl ML20087M8061984-03-30030 March 1984 New Addition to Contention Re Asbestos Fiber Discharges Into Schuylkill River & Air.Discharge Not Identified Nor Included in Plant Operation Discharge Descriptions.W/Svc List ML20087M6381984-03-28028 March 1984 Response Opposing M Lewis 840314 Motion for New Contention Based on IE Info Notice 84-17 Cooling of Vital Components by Liquid Nitrogen.Certificate of Svc Encl ML20087K8651984-03-23023 March 1984 Motion to Dismiss Particular Onsite Emergency Planning Contentions for Which Discovery Not Provided or No Litigable Basis Shown.Certificate of Svc Encl 1989-07-07
[Table view] Category:LEGAL TRANSCRIPTS & ORDERS & PLEADINGS
MONTHYEARML20151L3671997-08-0505 August 1997 Order Prohibiting Involvement in NRC Licensed Activities (Effective Immediately).Orders That SA Blacklock Prohibited from Engaging in Activities Licensed by NRC for 5 Yrs from Date of Order ML20151L5181997-08-0505 August 1997 Order Prohibiting Involvement in NRC Licensed Activities (Effective Immediately) Re SL Nevin Deliberately Falsifying Records of RECW Sample Documentation on 960207 ML20203H6891997-06-0202 June 1997 Transcript of 970602 Enforcement Conference in King of Prussia,Pa ML20083N3971995-04-26026 April 1995 Comment Supporting Proposed GL, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20081B3811995-03-0101 March 1995 Comment Supporting Proposed Suppl 5 to GL 88-20, IPEEE for Severe Accident Vulnerabilities ML20058K7381993-12-0303 December 1993 Memorandum & Order CLI-93-25.* Commission Denies State of Nj Petition for Leave to Intervene & Request for Adjudicatory Hearing Filed on 931008.W/Certificate of Svc.Served on 931203 ML20059B0301993-10-22022 October 1993 NRC Staff Response to Commission Questions Posed W/Respect to State of New Jersey Petition for Leave to Intervene & Request for Hearing.* Denies Petition to Intervene & Request for Hearing.W/Certificate of Svc & Notice of Appearance ML20059B1111993-10-20020 October 1993 Philadelphia Electric Co Response to NRC 931014 Order.* State Failed to Demonstrate Entitlement to Hearing to Challenge Util Amend to Permit Util to Receive Shoreham Fuel ML20057G2141993-10-14014 October 1993 Order.* Requests for Simultaneous Responses,Not to Exceed 10 Pages to Be Filed by State,Peco & Lipa & Served on Other Specified Responders by 931020.NRC May File by 931022. W/Certificate of Svc.Served on 931014 ML20059A4581993-10-14014 October 1993 Order Requesting Answers to Two Questions Re State of Nj Request for Immediate Action by NRC or Alternatively, Petition for Leave to Intervene & Request for Hearing. Operations Plans for Marine Transportation Withheld ML20059B1291993-09-14014 September 1993 Affidavit of Jh Freeman.* Discusses Transfer of Slightly Used Nuclear Fuel from Shoreham Nuclear Power Station to Limerick Generating Station.W/Certificate of Svc & Notice of Appearance ML20045D8121993-06-14014 June 1993 Comment Supporting Proposed Rules 10CFR50 & 54 Re FSAR Update Submittals. ML20126F2721992-12-21021 December 1992 Comment Endorsing Positions & Comments of NUMARC & BWROG Re Draft GL, Augmented Inservice Insp Requirments for Mark I & Mark II Steel Containments,Refueling Cavities & Associated Drainage Sys ML20062C6561990-10-22022 October 1990 Affidavit Requesting Withholding of Summary Rept on Evaluation of Recirculation Nozzle to Safe End Weld Indication & Proposed Disposition to Permit Unit 1 Cycle 4 Operation, from Public Disclosure,Per 10CFR2.790 ML20246J4521989-08-30030 August 1989 Memorandum & Order (Terminating Proceeding).* Terminates Proceeding Per Settlement Agreement Between Limerick Ecology Action,Inc & Licensee.W/Certificate of Svc.Served on 890831 ML20246F1471989-08-25025 August 1989 Settlement Agreement.* Certificate of Svc Encl ML20246F1011989-08-25025 August 1989 Joint Motion for Termination of Proceedings.* Board Moved to Accept Encl Settlement Agreement,Dismiss Limerick Ecology Action,Inc (Lea) Contention W/Prejudice,Dismiss Lea as Party to Proceeding & Terminate Proceeding ML20246F0121989-08-25025 August 1989 Memorandum & Order CLI-89-17.* Staff Authorizes Issuance of Full Power License to Licensee to Operate Unit 2 After Requisite Safety Findings Under 10CFR50.57 Completed. W/Certificate of Svc ML20246E3431989-08-22022 August 1989 Opposition of Intervenor Limerick Ecology Action,Inc to Motion by Licensee Philadelphia Electric Co to Set Schedule for Discovery & Hearing.* Requests That Schedule Be Replaced W/More Reasonable Schedule,As Proposed.W/Certificate of Svc ML20246C0271989-08-18018 August 1989 Notice of Appointment of Adjudicatory Employee.* Informs That D Nash Appointed as Commission Adjudicatory Employee to Advise Commission on Issues in Proceeding.W/Certificate of Svc.Served on 890818 ML20246B7721989-08-17017 August 1989 Correction of Memorandum & Order of 890815.* Advises That Refs to 49CFR2.730(c) on Page 1 & 49CFR2.710 & 49CFR2.711 on Page 2 Should Be Corrected to Read as 10CFR2.730(c),2.710 & 2.711,respectively.W/Certificate of Svc.Served on 890818 ML20246D7411989-08-17017 August 1989 Transcript of 890817 Meeting in Rockville,Md Re Discussion of Full Power OL for Facility.Pp 1-58.Supporting Documentation Encl ML20246B7571989-08-16016 August 1989 Order Responding to Limerick Ecology Action Motion for Reconsideration.* Denies Motion to Reconsider,Stay,Suspend or Revoke 890707 Order on Basis That Order Appropriate.W/ Certificate of Svc.Served on 890816.Re-served on 890818 ML20246B7751989-08-16016 August 1989 Memorandum & Order.* Denies Rl Anthony 890623 Request for Hearing for Intervention in Remand Proceeding & for Stay of Low Power Authorization.W/Certificate of Svc.Served on 890816 ML20246B7931989-08-15015 August 1989 Memorandum & Order (Request for Expedited Answer).* Denies Licensee 890811 Request for Expedited Answer from NRC & Limerick Ecology Action on Basis That Request Lacks Good Cause.W/Certificate of Svc.Served on 890816 ML20245H8061989-08-14014 August 1989 Supplemental Response of Intervenor Limerick Ecology Action, Inc to Memorandum & Order of Commission & to Memorandum & Order of 890807.* Requests Further Extension of Time in Which to Reply.Certificate of Svc Encl ML20245H8491989-08-14014 August 1989 Notice of Change of Address.* Advises of Council Change of Address for Svc of Documents ML20245H5991989-08-11011 August 1989 Memorandum & Order (Terminating Proceeding).* Dismisses Graterford Inmates Contention Re Adequacy of Training for Drivers Responsible for Evacuating Graterford & Terminates Proceeding.Certificate of Svc Encl.Served on 890814 ML20245H7341989-08-10010 August 1989 Motion by Licensee Philadelphia Electric Co to Set Schedule for Discovery & Hearing & Request for Expedited Answer to This Motion.* Divergence in Positions of Respective Parties Emphasizes Need to Conclude Proceeding.W/Certificate of Svc ML20245F7511989-08-0909 August 1989 Reply by Licensee Philadelphia Electric Co to NRC Staff Response to Commission Questions.* Commission Should Rely on Licensee Cost Analysis in Response to Question 5 & Rc Williams Affidavit.W/Certificate of Svc ML20245F7341989-08-0909 August 1989 NRC Staff Response to Commission Memorandum & Order of 890807.* Advises That NRC Will Provide Comments on Limerick Ecology Action 890814 Filing Prior to Commission Meeting Scheduled for 890817.W/Certificate of Svc ML20245F7161989-08-0909 August 1989 Reply by Licensee Philadelphia Electric Co to Response of Intervenor Limerick Ecology Action,Inc to Memorandum & Order of Commission Dtd 890726.* Environ Benefits for Operating Unit 2 Outweigh Small Risk of Severe Accident ML20245F7291989-08-0808 August 1989 Affidavit.* Discusses Costs Incurred While Plant Inoperable. Allowance for Funds Used During Const,Security,Maint & Operational Costs Considered Proper for Calculating Costs for Delay ML20248D9241989-08-0707 August 1989 Memorandum & Order.* Extends Limerick Ecology Action Response Deadline to 890814 to Respond to Five Questions Re Severe Accident Mitigation Design Alternatives.W/Certificate of Svc.Served on 890807 ML20248D7871989-08-0303 August 1989 Correction for NRC Staff Response to Commission Questions.* Forwards Corrected Page 5 to NRC Response to Questions Filed on 890802,deleting Phrase by Nearly Factor 2.5 in Next to Last Line.W/Certificate of Svc ML20248D5391989-08-0202 August 1989 Affidavit of MT Masnik.* Advises That Author Prepared Response to Question 3 ML20248D7111989-08-0202 August 1989 Response of Intervenor Limerick Ecology Action,Inc to Memorandum & Order of Commission Dtd 890726.* Commission Order Fails to Provide Intervenor Adequate Time for Response & Should Therefore Be Revoked.W/Certificate of Svc ML20248D5671989-08-0202 August 1989 Affidavit of SE Feld.* Advises That Author Prepared Response to Question 5.W/Certificate of Svc ML20248D4971989-08-0202 August 1989 Joint Affidavit of Gy Suh & CS Hinson.* Advises That Authors Prepared Responses to Questions 1 & 4 ML20248D6451989-08-0202 August 1989 Affidavit.* Advises That Author Read Responses to Request for Comments by NRC & Knows Contents.W/Certificate of Svc ML20248D4721989-08-0202 August 1989 NRC Staff Response to Commission Questions.* Provides Info for Use in Commission Effectiveness Review of Plant Full Power Operation,Per Commission 890726 Memorandum & Order. Supporting Affidavits Encl ML20248D5981989-08-0202 August 1989 Response by Licensee Philadelphia Electric Co to Commission Request for Comments by Memorandum & Order Dtd 890726.* Licensee Requests Commission Issue Full Power OL for Unit 2 Conditioned Upon Outcome of Pending Litigation ML20248D5311989-08-0202 August 1989 Affidavit of Rj Barrett.* Advises That Author Prepared Response to Question 2 ML20245J1321989-07-27027 July 1989 Transcript of 890727 Meeting in Rockville,Md Re Facility Severe Accident Mitigation Issues.Pp 1-130.Supporting Info Encl ML20247N3261989-07-26026 July 1989 Transcript of 890726 Affirmation/Discussion & Vote in Rockville,Md on SECY-89-220 Re Order Requesting Info from Parties for Immediate Effectiveness Review of Full Power Authorization for Limerick Unit 2.Pp 1-4 ML20248D7331989-07-24024 July 1989 Second Rept of Parties & Request for Dismissal of Graterford Inmates Contention & Termination of Proceeding.* Requests Board to Enter Order to Terminate Proceeding Based on Parties Agreeing to Dismissal of Remaining Contention ML20247Q4621989-07-23023 July 1989 Response of Intervenor Rl Anthony to Answer of Philadelphia Electric Co (PECO) to Request for Hearing on PECO Application for Low Power Operation of Unit 2 & Stay of Any Operation in Keeping W/Us Circuit Court Remand Of....* ML20247B7261989-07-20020 July 1989 Notice of Appointment of Adjudicatory Employee.* Advises That H Vandermole Appointed to Advise Commission on Issues in Proceeding Re Severe Accident Mitigation Design Alternatives.W/Certificate of Svc.Served on 890720 ML20247B3821989-07-18018 July 1989 Memorandum & Order.* Orders That Severe Accident Mitigation Alternatives,Per Nepa,To Be Considered Include Containment Heat Removal,Core Residue Capture & Venting.Certificate of Encl.Served on 890719 ML20247B7641989-07-13013 July 1989 Motion of Intervenor,Limerick Ecology Action Inc,To Reconsider/Stay/Suspend/Revoke Order Authorizing Issuance of Low Power OL for Limerick 2.* Consideration of Accident Mitigation Alternatives Imperative.Certificate of Svc Encl 1997-08-05
[Table view] |
Text
. .
c' q.
UNITED STATES OF AMERICA [, 3 NUCLEAR REGULATORY COMMISSION ~ g#rgf gy ,
Before the Atomic Safety and Licens'inc Boa: h In the Matter of )
) N Philadelphia Electric Company ) Docket Nos. 50-352 (Limerick Generating Station, )
Units 1 and 2) /,s'
)
S[s y$ s I &
APPLICANT'S ANSWER TO ROBERT L. ANTHONY lpj 4,4007 T1 g
l,[UA ,,
AND FRIENDS OF THE EARTH PETITION TO INTERVERE ,, g ,j Preliminary Statement / /
OK U On August 21, 19 81, the Nuclear Regulatory Comm 1N
(" Commission" or "NRC") published a notice on the Federal Register entitled " Philadelphia Electric Co. (Limerick Generating Station, Units 1 and 2), Receipt of Application for Facility Operating Licenses; Consideration of Issuance of Facility Operating Licenses; Availability of Applicant's 1/
Environmental Report; and Opportunity for Hearing" (" Notice").
In response to the Notice, a petition for intervention was filed by Robert L. Anthony, on his own behalf and as a representative of Friends of the Earth (" FOE"), dated September 18, 1981. Attached to the petition was a letter to the NRC from Kathleen O' Leary, Chairperson, Friends of the Earth in the Delaware Valley regarding the representation of FOE in this proceeding. A list of proposed contentions was also attached.
9 50]
1/ 46 Fed. Reg. 42557 (August 21, 1981). 5;[
f[
1 l
l 8110090374 811005 l PDR ADOCK 05000352 O PDR
I, o For the reasons discussed more fully . below, petitioner
! 2/
~~
i, FOE has failed to state the requisite personal interest
.for intervention in an NRC proceeding. Accordingly, the petition should be denied.
Argument Under the Commission's Rules of Practice, a petition to intervene in a licensiny proceeding may be granted only if the requirements of 10 C.F.R. SS 2. 714 (a) (2 ) and (d) have been satisfied. In essence, the regulations require the petitioner to state his specific interest in the proceeding and explain how that interest may La affected by the outcome of the proceeding.
It is now well settled that " organizations . . . are not clothed with independent standing to intervene in NRC licensing proceedings. Rather, any standing which [an organization) may possess is wholly derivative in character."
Houston Lighting and Power Company (Allens Creek Nuclear Generating Station, Unit 1), ALAB-535, 9 NRC 377, 390 (1979). --3/
In other words, an organizational petitioner must establish that at least one of its members has legal standing to
--2/ Inasmuch as the positions of FOE and Mr. Anthony appear to be equivalent, we assume that Mr. Anthony wishes to be designated the " sole spokesman." We shall therefore refer to FOE as the " petitioner" except when Mr. Anthony is specifically mentioned.
_3/ See also Texas Utilities Generating Company (Comanche Peak Steam Electric Station, Units 1 and 2), LEP-79-18, 9 NRC 728 (1979); Detroit Edison Company (Enrico Fermi Atomic Power Plant, Unit 2), LBP-79-1, 9 NRC 73 (1979).
intervene in this proceeding under the rules applicable to individual petitioners.
In response to the petition of Marvin I. Lewis to intervene in this . proceeding, Applicant has stated' its position as to the necessary particularization of an in-dividual petitioner's identifiable interest in a licensing proceeding, including an explanation of how that interest would be affected by any given outcome in the proceeding.
This position is equally applicable to the form af fidavits of petitioner's . members herein. Rather than furnish the Licensing Board with repetitive pleadings, Applicant here-by incorporates and respectfully refers the Board to its answer to the Lewis petition for a statement of the ad-ditional authorities upon which it relies in opposing the 4/
instant petition.-~
FOE states that it is "a national environmental and i
conservation public-interest organization dedicated to the protection of U.S. citizens' laws, health and well-being,"
and that the Delaware Valley branch c ? FOE serves these goals for that region. FOE states that it is "in a unique position because of its national connections and local expertise to call upon legal, technical and other profes-
-~
5/
sional experts.
On his own behalf, petitioner Anthony states that he and his wife hold jobs in Chester County which "could be
,4/ Petitioner herein has been served a copy of Applicant's answer to the Lewis petition.
_5/ FOE petition at 1.
~ . drastically changed by the operation of the Limerick nuclear pl an ts . " He believes that "(flunds from community campaigns could be cut because of increases in electric rates and the
. movement of families from the-county; the number of young people in -residential treatrent from out of state could be sharply - cut by fear on the part of agencies and parents .to
-- 6/
l Place young patients within fif teen miles of the plants.
He also states that he lives 25 miles from the Limerick l facility.
l The petition is accompanied by a number of affidavits using the same or nearly the same format from a number of individuals who live 4 to 25 miles from the Limerick plant.
l i
They state essentially that the affiant'is a customer of the applicant and opposes issuance of licenses for the Limerick reactors because "they will adversely affect my health, well being, and economic security." Each affiant then states that he wishes to have his interests represented by Mr. Anthony as the representative of FOE.
7/
For the reasons prevmly stated,- Applicant has taken the position that mere proximity to a nuclear facility, without more, is not a sufficient basis for standing in an NRC licensing proceeding under the decisions of the Commis-l sioners and judicial precedents they have adopted as the Commission's law on standing. The form affidavits submitted 1 6/ Id.
_7/ See Applicant's answer to the Lewis petition.
l
,A
with the FOL. petition vividly demonstrate the invalidity of making mere proxinity to a reactor the sine cua non of standing. As noted, these 'affiants merely state in the most conclusionary terms possibl.e that the Limerick reactors "will adversely affect my health, well being, and economic
~~ 8/
security." Moreover, none of these affiants even states that he or she is a member of FOE. Thus, these affidavits
-~ 9/
cannot create derivative standing for FOE.
~~
8/ Of course, certain economic interests are beyond the scope of the operating statutes of the NRC. For ex-ample, ratepapers lack standing to litigate possible increases in electric power rates. Portland General Electric Company (Pebble Springs Nuclear Plant, Units 1 and 2), CLI-76-27, 4 NRC 610, 614 (1976); Houston Lichtina and Power Company (Allens Creek Nuclear Generating Station, Unit 1), ALAB-582, 11 NRC 239, l 243 n.8 (1980); Public Service Company of Oklahoma (Black Fox, Units 1 and 2), LBP-77-17, 5 NRC 657, 659 (1977), aff'd, ALAB-397, 5 NRC 1143, 1147 (1977);
Metropolitan Edison Company (Three Mile Island Nuclear Station, Unit 1) , Docket No. 50-289 (Restart), " Memo-randum and Order Ruling on Petitions and Setting Special Prehearing Conference" (September 21, 1979)
(slip opinion at 7).
Also, the Appeal Board has held that licensing boards "are not authorized . . . to require an applicant to accept or reject an alternative svlely on the basis of its economic costs" because this is a business judgment for the applicant. Illinois Power Company (Clinton Power Station, Unit Nos. 1 and 2), ALAB-340, 4 NRC 27, 48 (1976). See also Consumers Power Comoany (Midland Plan t , Units 1 and 2), ALAB-458, 7 NRC 155 (1978);
Portland General Electric Company (Trojan Nuclear Plant) ,
ALAB-531, 9 NRC 263 (1979); Virginia Electric and Power Company (North Anna Nuclear Power Station, Units 1 and 2), ALAB-584, 11 NRC 451, 456 (1980).
9/ See Ho'Iston Lichtinc and Power Company (Allens Creek l Nuclear Generating Station, Unit 1), ALAB-535, 9 NRC ]
377, '32-93 (1979); Detroit Edison Company (Enrico '
Fermi Atomic Power Plant, Unit 2), LBP-79-1, 9 NRC (Footnote _9/ continued on next page) l l
l
The other interests stated by petitioner Anthony are equally generalized or otherwise- invalid. Petitioner s,
apparently believes that the licensing of Limerick would lead to a loss of psychiatric patients. However, community reaction to the operation of a nuclear facility is simply not within the " zone of interests" cognizable under the 10/
operating statutes of the NRC. Further, the adverse 11/
consequences to petitioner's earnings are so " speculative"--
that they cannot satisfy the injury in fact requirements for standing. Such drastic and conjectural changes as petitioner
_9,/ (con tinued) 73, 77 (1979); Texas Utilities Generating Company (Comanche Peak Steam Electric Station, Units 1 and 2), LBP-79-18, 9 NRC 728, 729 (1979); Louisiana Power and Light Company (Waterford Steam Electrical Station, Unit 3), Docket No. 50-382, " Memorandum and Order" (March 7, 1979) (slip opinion at 4) ; Cleveland Electric Illuminating Company (Perry Nuclear Power Plant, Units 1 and 2), Docket Nos. 50-440 and 50-441, " Memorandum and Order Scheduling Prehearing Conference Regarding Petitions for Intervention" (April 9, 1981) (slip opinion at 6) ; Consumers Power Company (Big Rock Point Nuclear Plant) , Docket No. 50-155, " Memorandum and Order" (September 25, 1979) (slip opinion at 4) .
--10/ The Commission has determined that psychological stress shall not be considered in reactor licensing proceedings. See Metropolitan Edison Company , CLI-80-39, 12 NRC 607 (19 80) (2-2 vote) . In reconsidering this order, the Conmissioners voted to adhere to its previous determination "to exclude psychological y stress and community deterioration contentions. "
Id., CLI-81-20 (September 17, 1981) (slip opinion at 2) .
11/ See Simon v. Kentucky Welfare Rights Organization, 426 U.S. 26, 43 (1976); Arlington Heights v. Metro-politan Housing Development Corp., 429 U.S. 252, 262 (1977); Linda R.S. v. Richard D., 410 U.S. 614, 619 (1973).
f .
_ postulates are simply inappropriate for consideration. In' any event, this economic interest is premised upon'a wide '
spread economic downturn within the entire area and, as such, is indistinguishable from those interests shared in substantially equal measure by all or a large class of the
_ public. Petitioner has therefore' failed to "show a dis-Transnuclear, Inc., ;
tinct and palpable harm" to himself.
CLI-77-24, 6'NRCf525, 5311(1977). ~
In'short, while FOE contends that it possesses or may- ,
call upon certain legal and technical expertise, standing does not exist in the absence of a direct, personal injury to its members. In this respect, the Commission noted the Supreme Court "has held that an organization's mere interest
. 2 ~
in a problem, 'no matter how long-standing the interest and no matter how qualified the organization is in evaluating the problem,' is not sufficient for standing to obtaib judicial review."
Finally, the " injury in f act" requirement under the rules for intervention also bear upon the duty of a pet.i-tiener to designate "the specific aspect or aspects of- the subject of the proceeding as to which petitioner wishss to ,
intervene."-~13/Petitioner has chosen to attach its proposed w
~~12/ Westinghouse Electrical Corp. (Export'to South Korea),
CLI-80-30, 12 NRC 253, 258 (1990), citing Sierra Club i
- v. Morton, 405 U.S. 727, 729 (1972). q
'- i 13/ 10 C'.F.R. 52. 714 (a) (2) .
s , ,
4
.. _ _ s._ .- ' s
, qy I'
x "u' + .
8-L (
-14/.
conten3 tons-to'the. petition instead. 'Given the standing riquirergnts discbssed above, all aspects alleged by peti-Ny ti' oner,"einclyding :any contentions thereunder, must neces-sarily be limited to the demonstrated " injury in fact," if P.-
any. -,
z As a. final matter, petitioner's request to consider
, M - .y ,
, " aspects" regarding the availability of water supplies
{ related .ne ick may not be heard because this matter lies witltin the. plenary jurisdiction of the Delaware River 23asin Ccomission, see generally Philadelphia Electric Company (Limerick Generating Station , Units 1 and 2),
, ALAB-26 , 1lHRC'l63 (1975), which has granted final approval 15/'
to the supplemental cooling water plan for Limerick. --
This action of the DRBC was approved by the United States District Court for the Eastern District of Pennsylvania on August 17, s , 1081. Moreover, this matter was fully " ventilated and re-s solved at thc construction permit stage" and petitioner has
- c. not made "any supported assertion of changed circumstances or the pocs[ Ele existence of some special public interest factors inb.he particular case." Alabama Power Comoany (J'oseph M. Earley Nuclear Plant, Units 1 and 2) , CLI-74-12, r
7 AEC 203 (1974).
x 14/ As noted at pages 2-3 of Applicant's answer to the
- Lewis petition, Applicant will reply to the contentions at a later date.
15/ It may be noted that permits related to the Point Pleasant project itself, specifically for the Point Pleasant intake structure and for the Chalfont waste treatment plant, are
~
now pending before the United States Corps of Engineers.
' %s
- w ., ,
j .
. J Conclusion
," For the reasona discussed.more fully tbove, petitioner has f ailed to satisfy the requirements for intervention in
,g '
~
L an NRC proceeding as applied to organizations because it has failed to establish the personal interests of its members in the outcome of'the proceeding. Accordingly, the petition to intervene should be denied. Applicant has no objection, t however, to a limited appearance by petitioner pursuant to '
10 C .F. R. 5 2. 715 (a) .
Respectfully submitted, CONNER & WETTERHAHN f A '
Tro Conner, Jr.
Mark J. Wetterhahn Robert M. Rader Suite 1050 1747 Pennsylvania Avenue, N.W.
Washington, D.C. 20006 202/833-3500 Counsel ror the Applicant October 5, 1981 J
m UNITED STATES 01 AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of )
)
PHILADELPHIA ELECTRIC COMPANY ) Docket Nos. 50-352
) 50-353 (Limerick Generating Station, )
Units 1 and 2) )
CERTIFICATE OF SERVI _CE I hereby certify that copies of " Applicant's Answer to Robert L. Anthony and Friends of the Earth Petition to Intervene, in the captioned matter have been served upon the following by deposit in the United States mail this 5th day of October, 1981. A copy of Applicant's answer to the Marvin I. Lewis petition has also been served on petitioner.
Judge Lawrence J. Brenner Alan S. Rosenthal, Esq.
Chairman, Atomic Safety and Chairman, Atomic Safety and Licensing Board Licensing Appeal Board U.S. Nuclear Regulatory U.S. Nuclear Regulatory Commission Commission Washington, D.C. 20555 Washington, D.C. 20555 Judge Peter A. Morris Eugene J. Bradley, Esq.
Atomic Safety and Licensing 2301 Market Street Board Philadelphia, Pennsylvania 19101 U.S. . Nuclear Regulatory Commission Colleen P. Woodhead, Esq.
Washington, D.C. 20555 Office of the Executive Legal Director Judge Richard F. Cole U.S. Nuclear Regulatory Atomic Safety and Licensing Commission Board Washington, D.C. 20555 U.S. Nuclear Regulatory Commission Mr. Chase R. Stephens, Chief Washington, D.C. 20555 Docketing and Servi:e Branch Office of the Secretary Paul B. Cotter, Jr., Esq. U.S. Nuclear Regulatory Chairman, Atomic Safety and Commission Licensing Board Washington, D.C. 20555 U.S. Nuclear Regulatory Commission Washington, D.C. 20555 I
E 2-t Robert L. Anthony Friends of the Earth 103 Vernon Lane Dox 186 Moyland, Pennsylvania 19065 b >
Robert M. Rader Counsel for the Applicant
.