..f PP&L TWO NORTH NINTH STREET. ALLENiQWN, PA.18101 PHONE: (21 $) 770 5151 NORM AN W. CURTIS Vice President Ergreering & Construction Nuclear G
7745381 g
. Q'
( f I.{
k
/-D'NLJhf' August 28, 1981 it, SEP 031984 3
p u.a.
massant
,p[
\\
9 Mr. Boyce H. Grier, Director Region I
~
- yj s
U.S. Nuclear Regulatory Commission m
631 Park Avenue King of Prossia, PA 19406 SUSQUEHANNA STEAM ELECTRIC STATION IE BULLETIN 79-27 ER 100450 FILE 842-3 DOCKET NOS. 50-387 PLA-907 AND 50-388
Dear Mr. Grier:
The following information updates our response to IE Bulletin 79-27. " Loss of Non-class-1-E Instrumentation and Control Power System Bus During Operation."
4 This letter supplements our previous response in PLA-632 dated February 13, 1981 and PLA-820 dated June 1, 1981.
PP&L has identified the power sources for all the instrumentation in the main control room sorted by panel and power supply, including those instruments and controls required to attain cold shutdow-Existing preliminarv emergency operating procedures already identif*;. approximately 90% of all I&C devices to attain cold shutdown.
Remaining work involves identification of those power busses required for I&C outside the control room and to determine if either equipment changes or procedural changes are needed.
Expectet completion date for determining equipment changes (if any) is October 15, 1981. Expected c mpletion date for determining procedural sp' !I I
St l
i 8109040213 810828 YLVANIA POWER & LIGHTCOMPANY PDR ADOCK 05000387 0
m
',, y'
~
s.
Mr. Boyce H. Grier Page 2 August 28, 1981 cnanges is December 1, 1981. An update will be provided to NRC in November, 1981.
Very truly yours, s
N.
.. Curtis Vice President-Engineering & Construct'on-Nuclear RJP/mks cc:
Director Division of Reactor Construction Inspection Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Washington, D.C.
20555 Mr. G. G. Rhoads U.S. Nuclear Regulatory Commission P.O. Box 52 Shickshinny, PA 18655 Mr. L. D. Narrow U.S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, PA 19406 l
<