Notifies That Response to NUREG-0612 Delayed Due to Large Number of Cranes & Hoists in Plant & Unit 1 Startup Activities.Section 2.1-2.4 Concerns Will Be Addressed by 810922
ML20010A689
Person / Time
Site: McGuire, Mcguire  
Issue date: 08/05/1981
From: Parker W
DUKE POWER CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0612, RTR-NUREG-612 NUDOCS 8108120037
Download: ML20010A689 (1)


Text

Duxe POWER COMPANY Powza Dunwnwo 422 SouTn Gruncu Srazer, CILAHWTTE, N. C. 28242 WIL LI AM O. PAR M ER. J R.

vc,e c.mru, August 5, 1981 ruc,. ouc:4.c.7o.

Sttans PaoovcTeow 373-4083 tw 4?

k(j()gfj*'

N/A Mr. Harold R. Denton, Director E

I Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission 5

. f ".s. %,d, G 111981 m ;

Washington, D. C.

20555

-- w Attention:

Ms. E. G. Adensam, Chief

\\

.7/

Licensing Branch No. 4 p

Re: McGuire Nuclear Station Docket Nos. 50-369, 50-370 Control of Heavy Loads, NUREG-0612

Dear Mr. Denton:

My letter of June 2, 1981 identified the basic program.that Duke Power Company was pursuing to resolve the concerns identified in Mr. Darrell Eisenhut's letter of December 22., 1980 and in NUREG-0612. Due to the large number of cranes and hoists.in the plant and the Unit 1 startup activities, the evaluation has not been completed.

It is our intention to provide the informa:: ion requested in Sections 2.1-2.4 of Enclosure.2 to Mr. Eisenhut's letter by September 22, 1981.

Very truly yours, w

William O. Parker, Jr.

7/C GAC:krh cc:

M. J. Graham Mr. James P. O'Reilly, Director Resident Inspector U. S. Nuclear Regulatory Commission McGuire Nuclear Station Region II 101 Marietta. Street, Suite 3100 Atlanta, Georgia 30303 S #

PDR' w--