ML20009H482

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-423/81-06 on 810508-29 & 0601-05. Noncompliance Noted:Mechanical Snubbers in Reactor Plant Component Cooling Water Sys Installed W/O Using Required Supplier Instruction Manual
ML20009H482
Person / Time
Site: Millstone Dominion icon.png
Issue date: 07/20/1981
From: Elsasser T, Mattia J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20009H476 List:
References
50-423-81-06, 50-423-81-6, NUDOCS 8108100171
Download: ML20009H482 (9)


See also: IR 05000423/1981006

Text

. _ _ _ _ _ _ _ _

-

-

,.

.

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

Region I

Report No. 50-423/81-06

Docket No. 50-423

License No. CPPR-113

Priority

__

Category

A

Licensee: Northeast Nuclear Eneray Company

P.O. Box 270

Hartford, Connecticut 06101

Facility Name: Millstone Nuclear Pcwer Station, Unit #3

Inspection at: Waterford, Connecticut

Inspection Conducted-

May S-9

nd Jane 1-5, 1981

f

] lo 8/

Inspectors:

__ 4he/

-

J. Mattia, Se i. Resident inspector

da e

igned

,

/.

_

date signed

Approved by:

W

-

W

7 20j8/

1". C.TElsasser, ' ' iief, Rezetor Projects

da.e signed

'

Section 1B

Inspection Summary _:

Unit 3 Inspection on May S-29 and June 1-5, 1931 (P.enort No. 50-423/81-06).

Areas Inspected:

Routine inspection by the resident inspector of '..>ork act-

ivities relative to safety related concrete placement; pipe erection; in-

stallation of steam generators; raceway installation, and component installation.

The inspector also performed plant inspection tours and reviewed licensee

action on previously identified items.

The intpection involved 90 inspector-

hours, including three off-shift hours by one NRC inspector.

Results: Of the seven areas inspected, one item of noncompliance was identified

in the following area:

Failure to follow the supplier's instruction manual

for the installation of mechanical snubbers (Paragragh 8).

.

.H

8108100171 810723

PDR ADOCK 05000423

G

PDR

L-

. _J

- _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

. _ _ _ - _ _ _ .

'

.-

.

.

DETAILS

1.

Persons Contacted

Northeast Utilitfes Service Company (NUSCO)

K. Gray, Supervisor, Construction QA

S. Toth, system Superintendent Generation Construction

S. Ore' ice, Superintendent New Site Construction

F. Comstock, QA Technician

D. Diedrick, QA Manager

K. Murphy, QA Specialist

R. Vaccaro, QA Technician

J. Peterson, Construction Specialist

A. Cooper, Construction Engineer

J. Putnam, Construction Engineer

Stone and Webster Engineering Corporation (S&W)

W. Mackay, Resident Manager

F. Sullivan, Senior Resident Engineer

A. Prussi, Senior Resident Engineer

P. Gagel, QA Program Administrator

G. Turner, Field QC Superintendent

W. Anderson, Assistant Field QC Superintendent

M. Matthews, Assistant Field QC Superintendent

G. Marsh, Senior QC Engineer

W. Orr, Senior QC Er.gineer

N. Kelly, Construction Supervisor, Welding

S. Morris, Senior QC Engineer

R. Hooker, QC Inspector

R. Hagerman, QC Engineer

F. Froscello, QC Inspector

B. Sicotte, QC Inspector

F. Morales, QC Inspector

Westinghouse Corporation

E. Harlow, Site Representative

2.

Plant Tours

The inspector observed work activities in progress,- completed work and

construction status in several areas of the plant. The inspector

examined work for any obvious defects or noncompliance with regulatory

requirements or license conditions.

Partic"lar acte was taken of the

presence of Quality Control inspectors and Quality Control evidence,

such as inspection .ecords, material identification, nonconforming

material identification, housekeeping and equipment preservation.

'

-

- -

.. a

.

,.

-

.

.

3

Specifically, the inspector observed various preparations for concrete

operations for the following: cooling water discharge tunnel (fill concrete

and base slab); Auxiliary Building and Engineered Safety Feature (ESF)

Building walls; Fuel Building fill concrete, and the installation of rebar

for the ESF, Auxiliary, Discharge Tunnel and control structures.

The inspector also observed the installation of cable trays and their

supports and piping activities in the various Category I buildings.

No items of noncompliance were identified during the various plant

tours conducted, However, the following conditions were observed:

a.

The inspector noted that a Category I (aluminum) cable tray zee

(#DHH20) had two cracked welds in the rings of the tee. Ar in-

spection of other cable tray tees stored in the same area did not

reveal any unsatisfactory weld joints.

S&W issued an Inspection

Report (No. X1000279) for the tee.

The disposition was to scrap.

b.

The inspector informed the licensee that the containment persor:nel

hatch had three areas requiring corrective action which are as

follows:

(1) Excessive amount of debris on or adjacent to the hatch.

(2) Bundle of electrical cables (terminations) was uncovered and

not protected from ongoing construction activities.

(3) Circumferential field weld joints and 1/2" piping did not

have any protective coating and were rusting.

Immediate corrective actions were taken for items (1) and (2)

above. S&W issued Inspection Report No. 10002/2 for the disposition

and appropriate cor ective action for item (3).

This item is

considered unresolved pending review by NRC inspector of the

corrective action.

(423/81-06-01)

c.

The inspector noted that the heaters for the Quench Spray Pump

and Safety Injection Pump motors were not energized (Note:

the

electricians were engaged in a labor dispute). This condition

was Srought to licensee's attention and immediate corrective

activ.. sas taken.

d.

During a plant tour the inspector noted that the crafts were

straightening the end of a damaged coated pipe using hydraulic

pressure. During a review o associated drawing (No. EB-ID),

applicable specificiatic1 and weld procedure to determine that

the repair was being performed in accordance with the requirements,

the inspector noted that this pipe was part of a duct for the

supplementary leak collection and release system (SLCRS).

The

drawing (EB-ID) and associated E&DCR (No. PB-3362) were not very

a.

L.

.

..

.

.

4

clear as to what standard shall be applied, that is, if it is a

duct (per specification) then AWS D.1.1 should apply; if pipe,

then ANSI B 31.1 applies.

S&W revised the drawing to further

clarify the requirements for this duct.

The duct is considered

by S&W to be a buried pipe (exhaust to Unit 1 stack) and ANSI

B31.1Property "ANSI code" (as page type) with input value "ANSI</br></br>B31.1" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process. applies for this Category I system.

The inspector has no

further questions at this time.

3.

Receiving, Handling and Installation of Steam Generator

Two steam generators (Westinghouse Spin No. NEU-RCPCSG-3 and -4),

shipped from Tampa, Florida by barge, arrived at the Millstone 3

Construction Site. The steam generators were received, removed from

the barge and then transported to the containment and lifted into

place. The inspector witnessed most of the activities for the first

unit (-3 or Unit "C") and also verified that the requirements and

precautions in the following documents were adhered to:

--

S&W Field Construction Prccedure (FCP) #295, Rev. O, entitled

" Steam Generator Installation and Rigging."

--

S&W FCP-296, Rev. O, entitled " Setting of Steam Generator on

Temporary Supports."

--

S&W Construction Method Procedure (CMP) 10.3, entitled, " Testing

of Overhead Cranes and Monorails."

--

S&W Procedure CMP 10.1, entitled, " Rigging and Equipment Maintenance."

The inspector retiewed the following data associated with the polar

crane and lif ti ig rigs:

S&W Containment Structure Polar Crane Test Certification Reports

--

No. 9 and 10.

NDE Reports of Crane Hook, dated 7/19/80, 7/21/80, and 5/11/81.

--

Proof Load Test Report No. S191 For Westinghouse Lifting Beam

--

(DWG 1099 JIB).

S&W NDE Report for Lifting C am.

--

R. Dudgeon Inc. Test Report for 200 Ton 12" Lifting Jacks System.

--

--

Bridgeport Testing Lab and Thames Valley Steel Corporation reports

for liquid penetrant testing of the various size bolts used for

the steam generator handling.

.

Proof test reports for various slings used for the steam generator

--

lifts.

s.

L

_)

-.

-

..

- _ .

_.

.

,

-.

-

.

..

.

.

.

5

The inspector found the inspection and S&W construction personnel were

knowledgeable of the handling requirements and that they were adequately

per'orming their duties, inspection and/or surveillance activities,

during the handling of the steam generator.

No items of noncompliance were identified.

4.

Observation of Concrete Placement Activities

The inspector reviewed the S&W specification (C999) and the quality

standard, QS-10.13, requirements for placing concrete.

The. inspector

also held discussions with inspection personnel present at the concrete

'

placement locations for the containment wall (Placement No. C-3702).

Based on the review af the documents, discussions with inspection

personnel, and the d ect observation of the various activities

'

associated with the placement, the inspector determined the following:

The preplacement inspection and w0rk activities conformed to the

--

project requirements.

-

--

The inspection personnel at the placement were knowledgeable of

work requirements. They were located in close proximity to the

i

j

truck discharge and final placement location to observe and

inspect the quality of concrete and placement operations.

The quality requirements of the conc. rete being placed were verified

--

by testing near the paint of placement and at the mixing truck.

,'

The inspector verified that the delivered concrete met the specification

j

requirements for the placement as to mix design slump, air and

temperature.

--

Consolidation of concrete in the forms was adequate.

--

The form work was adequate and the rebar cover was as required by

specification.

i

--

A review of the QC inspection reports (Preplacement #S1001517 and

Placement No. S1001512) indicated they were adequate and complete.

S&W concrete pour card was properly filled out per the requirements.

--

--

The curing requirements were adhered to.

-

No items of nonccmpliance were identified, however, the' inspector

questioned the " bundling" of two No. 18 rebars horizontally around the

inner diameter of wall. The ACI 318 Building Code. Requirements, in

Section 7.4.2 (both text and commentary) specifies certain conditions

for " bundling" of rebars which are not being followed by S&W.

It is

the stated opinion of S&W (Design) that Section 7.4.2 is strictly for

a

~

v,

,.n.

. , . - . .

,-

,

,-. ,,.

, ,

,

- . , . - - , , -.,

_

___

_

._

_ _ . _

_ _ - . _ .

-

_.

_ _ _

_ _ _

,

^

.-

,.

j

.

,

6

a

columns and girders and, therefore, does not apply to the containmer...

The licensee was informed that this item is considered unresolved

i

pending review by NRC of the licensee's contention that ACI 318 Section

7.4.2 does not apply.

(423/81-06-02)

5.

Raceway Supports and Anchorages

1

The inspector observed the installation of several cable tray supports

in the control building cable spreading room for conformance to the

requirements specified in the following documents:

j

--

Stone & Webster Drawing FSK-E-140.

)

Stone & Webster Drawing FSK-CS-710-421.

--

t

Stone & Webster Drawing EE-52A.

--

--

Stone & Webster E&DCR Number FE-4239.

The inspector deten.iined the following:

)

The crafts were using approved and current drawings.

--

<

--

The materials were of the type (configuration) and size specified.

The correct weld materials and weld procedures were used by

--

qualified welders.

,

--

Weld inspection by QC inspectors was performed.

,

Location was in accordance with drawing requirements.

--

No items of noncompliance were identified.

i

6.

Safe _ty Related Piping Installation Work Activities

i

'.

a.

The following veld joints, located in the yard adjacent to the

,

'

intake structure (in various stages of welding), were inspected

j

to verify that the weld procedures and code requirements were

l

adhered to:

3-SWP-030-190-3, Field Weld #6 (completed except _ for weld . repair

!

on surface).

r

I

3-SWp-030-191B, Field Weld #6 (weld approximately 3/4 completed)

l

The S&W weld technique procedure No. W290 was being used for

!

welding these copper alloy (#706) weld joints. The inspector

also observed the liquid penetrant examination being performed on

the-weld repair. _The qualifications of the NDE examiners and

welder were also reviewed.

!

!

!

%-

~d

_ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

_ _ _ ______- - ____- ___ _ _-_ __ ___.

_ _ _ _ ________ _

_ _ _ _ _

____ _

l

.-

.

.

.

7

Welding and NDE were performed in accordance with the applicable

procedure and code rquirements.

No items of noncompliance were identified.

b.

The following weld joints, located in the Engineered Safety

Features (ESF) building, were inspected to verify that the weld

procedures and code requirements were adhered to:

3 SIL-008-14-2, FW #22 (fitup inspection was in progress).

3 CI-QSS-3, FW#2 (fitup inspection was in progress).

3-SWP-4-PSST-153 (pipe support installation and welding in progress).

3-FWA-010-20-3, FW#23 (weld joint approximately 1/3 completed).

3-QSS-3-5-4-2, FW#2 (fitup completed).

The inspector verified th t the requirements of the applicable

S&W weld technique procedures (W12F, W39F and W21U) and code

requirements were being followed.

The weld data sheets for each

weld were reviewed. The inspector also observed the QC inspector

and construction welding supervisor performing their fit-up

inspections. The correct welding materials were in use for the

welding.

No items of noncompliance were identified.

c.

A weld joint identified as 3CHS-003-72-2, FW#3 located ic. the

containment building was being welded and was approximato.y 2/3

completed. The inspector reviewed the wela data sheet and observed

the welding in progress to determine that the requirements of

weld technique procedure, W12G, and code requirements were adhered

to.

No items of nonco.mpliance were identified.

7.

Containment Dome and Wall Stud Weldfog

The inspector observed stud welding on the outside of containment at

penetration inserts 4B 313, 18 316, and 18 315 to verify compliance

with S&W weld technique procedure W718,- AWS D.1.1, drawing EV-12,

Revision 6 and specification C109 requirements. The correct materials

(size and' type) for the concrete anchor studs and deformed bar anchors

were being used. The rejected stud welds (incomplete filler weld)

were being properly repaired (using S&W weld technique Procedure

W718).

L

a

..

,.

-

.

8

No items of noncompliance were identified.

8.

Licensee Action on Previous Inspection Findings

a.

(Closed) Unresolved Item (423/81-05-02):

Lack of vendors in-

struction manual for installing mechanical shock and sway suppressors

(snubbers).

Several snubbers were installed in safety related

systems prior to receipt of the vendors instruction manual (example:

three snubbers were installed in the raactor plant component

coo! ng water piping system to the excess letdown heat exchanger

which is located inside the containment building).

The inspector

informed the licensee that the installation of snubbers without

the vendor's instruction manual is contrary to C,iterion V of 10 CFR 50, Appendix B a.,d that the previously unresolved item is now

considered an item of noncompliance (423/81-06-03).

S&W received

ITT Grinnel Corporation maintenance and installation m nual (PHD-

7594-1 Revision 3, dated 10/12/79 for the snubbers on site (stored

and installed). The manual has detailed instructicas for the

handling, storage and installation of these snubbers.

The instruction

lists mandatory " caution" notes for each of these activities.

b.

(0 pen) Unresolveo Item (423/81-05-01): The A/E has installed

signs and barriers to control access to the reactor pressure

vessel bottom head area (mirror insulation in place storage

area). The additianal supports for the in-core instrumentation

piping beneath the reactor pressure vessel have not been installed

as yet.

This item is considered unresolved pending installation

of additional support.

c.

(0 pen) Unresolved Item (423/81-05-09):

S&W received the vendor's

regenerative heat exchanger support bracket drawing (#5584). The

inspector measured several critical as-built dimensiors to de-

term, le if an unauthorized modification .to the support was per-

formed at the site.

The results indicated that the support was

not modified, however, the inspector noticed that several of the

weld joints for the clamps (detaii "D" of decwing) did not meet

the drawing requirements (weld configuration).

The licensee was

informed of this discrepancy.

The S&W issued an inspection

report (IR No. M1000159) and a ncnconformance report (N&D No.

-

0790) for this condition.

This item is still considered unresolved

pending Westinghouse disposition of discrepancy.

9.

Installation of Skid Mounted Safety-Related Pumps

The NRC inspec or was approached by some of the craf t workers (millwrights)

with a concern that S&W will not install skid mounted pumps and motors

per the vendor's instruction manual. A specific example.was given to

the inspr;tcr. The safety injection pumps (two) are presently

' stalled

(not finally leveled, aligned or grouted) in their proper location

with the intaka and discharge piping bolted to the pump flanges.

The

.-

L-

.

.-

.

.

.

9

vendor's (Pacific Pump) instruction inanual states that prior to grouting,

the motor shall be disconnected from the pump and lifted off the skid

in order to le.<el the skid.

The specific concern is that this will

not be done.

The inspector informed the licensee of the concern and

was informed that the vendor's instruction manual will be folloted or, if

not, the vendor's manual, a prope-ly approved S&'d procedure

will be followea. The inspector stated that this item is considered

unresolved pending NRC reveiw c f records and/or observations of final

installation of safety-related skid mounted pump and motors.

(423/31-

06-04)

10.

Itsta]1ation r? Prestressed Concrete Pine

The inspector observed the handling, erecting and testing of connection

of Si" diameter concrete yard pipe for compliance with S&W specification

C 966.

He also observed the QC inspection activities associated with

the installation.

No items of ncncompliance were identified.

11.

Unresolved Items

Unresolved 'tems are matters c' out which more information is required

u

in order to ascertain whether they are acceptable items, items of non-

compliance, or daviations. Unresolved items disclosed during the

inspection are discussed in Paragraphs 2, 4 and 9.

12.

igaaoement Meetings

j

At pericaic intervals during the coursa of this inspection, meetings

were helc with senior plant r..anagement to discuss the scopo and findings

of this iaspection.

c-

,